Calculate the amount of import or export, Civil Engineering

Assignment Help:

Calculate the Amount of Import or Export

For the project site shown in Figure, the amount of import or export to bring the entire site to elevation 90-ft is most nearly:

1999_Calculate the amount of import or export.png

Solution:

By inspection, the project has a combination of areas where there are imports and exports to bring the entire site to elevation 90-ft.Further, the multiple choices given for the answer should be analyzed.There is a spread of approximately 20% among the choices which suggests a broad perspective analysis to determine the solution. 

The figures to the right illustrate a broad based analysis.  Assume one grid:

  Existing          90.50-ft

  Proposed        90.00-ft

  Cut                 0.50-ft

  Total Export = [150-ft x 300-ft x 0.50-ft] ÷ 27ft3/yd3 = 833-yd3

 


Related Discussions:- Calculate the amount of import or export

Define compression - actions in pot bearings, Define Compression - Actions ...

Define Compression - Actions in POT Bearings? Vertical load is carried through the piston of the bearing and it is resisted by the elastomeric pad. Elastomer is incompressible,

Matrices, How to invert a matrix

How to invert a matrix

Jacking face for pipe-jacking, Ground settlement occurs ahead or behind the...

Ground settlement occurs ahead or behind the jacking face for pipe-jacking? It's reported by Lake (1992) that settlements are expected at ground surface at a distance of 1-2 ti

Solubility - Soil compaction, Solubility: Bitumen is soluble in carbo...

Solubility: Bitumen is soluble in carbon disulphide (CS2). The Indian specifications require that the bitumen should have 99 per cent solubility. Lesser value indicates prese

Major drawbacks of using inverted siphons, Question What is key application...

Question What is key application of inverted siphons? What are major drawbacks of using inverted siphons ? Answer Inverted siphons are planned at locations in which sewer s

Curved prestressed bridge, In a curved prestressed bridge , how ought to t...

In a curved prestressed bridge , how ought to the guided bearings in piers of curved region be oriented with respect to a fixed bearing in abutment?

Storm water, what are the roles of civil engineers in storm water managemen...

what are the roles of civil engineers in storm water management

Hydraulics, A tank with vertical sides contain 3m of water in the bottom, o...

A tank with vertical sides contain 3m of water in the bottom, overlain by 4m of oil with no intermixing. Draw pressure diagram due to the oil and water on one of the tank sides and

M, symbols of electrical layout

symbols of electrical layout

Cutbacks and emulsions, Cutbacks And Emulsions: Cutbacks A cu...

Cutbacks And Emulsions: Cutbacks A cutback is a bitumen whose viscosity has been reduced by adding a diluent such as naphtha or kerosene. The use of cut-back is not f

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd