Calculate the amount of import or export, Civil Engineering

Assignment Help:

Calculate the Amount of Import or Export

For the project site shown in Figure, the amount of import or export to bring the entire site to elevation 90-ft is most nearly:

1999_Calculate the amount of import or export.png

Solution:

By inspection, the project has a combination of areas where there are imports and exports to bring the entire site to elevation 90-ft.Further, the multiple choices given for the answer should be analyzed.There is a spread of approximately 20% among the choices which suggests a broad perspective analysis to determine the solution. 

The figures to the right illustrate a broad based analysis.  Assume one grid:

  Existing          90.50-ft

  Proposed        90.00-ft

  Cut                 0.50-ft

  Total Export = [150-ft x 300-ft x 0.50-ft] ÷ 27ft3/yd3 = 833-yd3

 


Related Discussions:- Calculate the amount of import or export

Soil Mechanics, Good evening. I have two homework projects from the Soil Me...

Good evening. I have two homework projects from the Soil Mechanics. I am interesting if anybody can solve them.

TORSION, WHAT IS TRANSVERSE AND LONGITUDINAL REINFORCEMENT?

WHAT IS TRANSVERSE AND LONGITUDINAL REINFORCEMENT?

Write short notes on bricks, Q. Write short notes on Bricks? Bricks are...

Q. Write short notes on Bricks? Bricks are an important construction material required in bulk Quantities for construction of walls both sub structure & super structure. For th

Offset(survey)., what is meant by the offsets and explain its type?

what is meant by the offsets and explain its type?

Concrete cracking, Attached information shows construction details of a wat...

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped

Explain the term -tendon splices, Tendon splices Tendon splices are us...

Tendon splices Tendon splices are used to join tendons when continuous prestressed concrete , members require long tendons to achieve continuity. Several types of tendon splic

Whole base of mat, Question In modeling a nonrigid mat foundation by us...

Question In modeling a nonrigid mat foundation by using elastic springs, have a uniform modulus of subgrade reaction be used along whole base of mat ? Answer A bed of

Slump test, why only frustum cone use in slump

why only frustum cone use in slump

Strength of rivet joints, Please help me to write a c program to find stren...

Please help me to write a c program to find strength and efficiency of lap joint, single cover butt joint, double cover butt joint

Determine the amount of excavated material, The footprint of a proposed off...

The footprint of a proposed office building is overlaid on the existing contours topographic map of a sloping site as shown in the figure. The structural bays which are 65-ft by 65

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd