Calculate the amount of cubic yards of soil, Civil Engineering

Assignment Help:

A proposed building site requires 135,000-ft3 of imported fill.  A borrow site is located 5-miles Northeast of the project site where the soil has a shrinkage of 16%.  The amount of cubic yards of soil that must be excavated from the borrow site is most nearly: 

Solution: Apply the equation, calculate the bank volume from the borrow site using the known components of the equation:  

Vcompacted = [(100% - % shrinkage) ÷ 100%] x Vbank

135,000-ft3= [(100% - 16% shrinkage) ÷ 100%] x Vbank

 = 135,000-ft3 ÷ .84 = Vbank

 Vbank = 160,715-ft3 ÷ (3-ft/yd)3 = 5,950-yds3


Related Discussions:- Calculate the amount of cubic yards of soil

Use of admixtures in concrete, Use of Admixtures in Concrete The use of...

Use of Admixtures in Concrete The use of chemical admixtures may be made in prestressed concrete construction. But the admixture should not contain chlorides in any form. This

Stacking of materials for building, briefly explain the stacking of materia...

briefly explain the stacking of materials in the site for general building?

CANTILEVER RETAINING WALL, NEED TO DESIGN A CANTILEVER RETAINING WALL 8M HI...

NEED TO DESIGN A CANTILEVER RETAINING WALL 8M HIGH, SATURATED UNIT WEIGHT IS 16KN/M3, SURCHARGE IS 7KN/M2, LOAD ABOVE WALL SUPPORTED ON WALL STEM IS 10KN/M RUN, ANGLE IN INTERNAL F

Sewer, what are the procedure of surveying for sewer projects/

what are the procedure of surveying for sewer projects/

Define the ignitability - hazardous waste, Define the Ignitability - Hazard...

Define the Ignitability - Hazardous Waste - is a liquid with flash point - Not a liquid and capable of spontaneous and sustained combustion under normal conditions - Ign

WATER SUPPLY, THE DESIGN PERIOD AVERAGE DAILY DEMAND CALCULATE. THE DESIGN ...

THE DESIGN PERIOD AVERAGE DAILY DEMAND CALCULATE. THE DESIGN DEMAND FOR THE WATER RETICULATION OR DISTRIBUTION PERIOD.

Mini projects, is there any innovative projects in disaster management ?

is there any innovative projects in disaster management ?

What is meaning of maintenance period, Question If contractor is likely...

Question If contractor is likely for defective works for 12 years with pact under seal, then what is meaning of Maintenance Period? Answer Faulty works constitute a br

Calculate the ultimate bearing capacity of the footing, A continuous footin...

A continuous footing of width 2.5 m rests 1.5 m below the ground surface in clay. The unconfined compressive strength of the clay is 150 kN/m 2 . Measure the ultimate bearing ca

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd