An electrical contractor is preparing to place the duct bank concrete encasement for the high voltage feeders between manhole # 11 and # 12, total distance is 323-ft. The duct bank is 2-ft x 3-ft and holds nine 4.5-in Schedule 80 PVC conduits. The amount of concrete to be ordered is most nearly:
Solution:
Nominal 4-in Schedule 80 PVC pipe is 4.5-in O.D.
Total Volume = 2' x 3' x 323' = 1938-ft3 / 27-ft3/CY = 71.77-yd3
Total Deduct = 9 x (π ((4.5"/12")/ft)2)/4 x 323' = 321-ft3 / 27-ft3/CY = 11.89-yd3
Total Concrete = 71.77-yd3 - 11.89-yd3 = 59.88-yds3
why base isolation is not good for tall building
The moment of inertia calculates the opposition any kind of body will have against a certain momentum (along that similar axis) trying to rotate that body.
what is footing
HOW TO MAKE A GOOD BUILDING .? TELL ABOUT SOME TIPS OF REQUIREMENT OF GOOD BUILDING STONE? AND SAY ABOUT CEMENT?
procedure
#question.how.
what is mean by vasthu
effective CBR
Question Design of concrete structures, normally most aggregate sizes are adopted with scopes from 10mm to 20mm. Does an increase of most aggregate size advantage structures ?
First Can I use this device to test concrete specimen? I think the specimens sustain tensile strength with fixing the jaws! I want to know it is true or not?
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd