Calculate load distribution factor, Civil Engineering

Assignment Help:

Load Distribution Factor:

The formula for deriving at the number of repetitions of the standard axle load during a design period of n years is:

N =365 × A × VDF × F [(1 + r )n - 1]/r

where A = Number of commercial vehicles per day initially (both directions),

VDF = Vehicle Damage Factor,

F = Load Distribution Factor,

r = Annual rate of growth of traffic (in decimals), and

n =  Design period in years.

Thus, if a two lane road has a present commercial traffic of 4000 veh/day, and the design period is 15 years, the rate of growth of traffic is 7.5%, and the VDF is 3.5, the number of repetitions of standard axle loads during the design Period

N =365 × A × VDF × F [(1 + r )n - 1]/r

A = 4000

VDF = 3.5

F = 0.75 (Table 4.3)

r = 7.5% = 0.075

n = 15

Substituting, N = 365 × 4000 × .35 × 0.75 [1.07515 - 1]/0.075

= 365 × 4000 × 3.5 × 0.75 [2.96 - 1]/0.075

= 100 million

The million standard axles of repetitions is denoted by "msa".


Related Discussions:- Calculate load distribution factor

For the plane area shown determine the first moments, for the plane area sh...

for the plane area shown determine the first moments with respects to the x & y axis & the location of the centroid

Designing level of landings in piers, Question What is designing leve...

Question What is designing level of landings in piers? Answer Landings are designed as resting place for passengers throughout berthing and deserting of vessels. I

State highways, State Highways: These are trunk or arterial roads of a...

State Highways: These are trunk or arterial roads of a state connecting the National Highways of adjacent states and linking the district headquarters and important cities wit

Sub-base layer be served as a drainage layer , Question Would a sub-bas...

Question Would a sub-base layer be served as a drainage layer to take away water from pavement? Answer As well providing load distribution in post-construction stage a

Total volume of soil that excavated from the borrow area, Project specifica...

Project specifications require a relative compaction of 95% (modified Proctor).  Construction of a highway embankment requires 10,000-yd 3 of fill.  The borrow soil has an in-situ

Retaining walls, Retaining Walls: Needed to retain the fill portion, a...

Retaining Walls: Needed to retain the fill portion, and generally constructed in dry stone masonry with pucca bunds (Figure). Figure: Typical Design for a Retaining

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd