Calculate Equivalent Uniform Annual Cost for the Excavator

An earthwork contractor is considering the purchase of a new excavator.  Based on 10% interest, the equivalent uniform annual cost for the excavator is most nearly:  

Solution:  

EUAC   = 80,000 (A/P, 10%, 20) - 20,000 (A/F, 10%, 20) + annual operating cost

              80,000 (0.1175) - 20,000 (0.175) + 18,000      

          = 9400 - 350 + 18,000       

          = $27,050


Related Discussions:- Calculate equivalent uniform annual cost for the excavator

ceramics is what type of materials, Ceramics is what type of materials ? ...

Ceramics is what type of materials ? Answer: It is  an insulators.

What is rail lubrication, Q. What is Rail Lubrication? Rail Lubrication...

Q. What is Rail Lubrication? Rail Lubrication is done on sharp curves where lateral wear is considerable. The function of Rail Lubrication is to lubricate or oil the running fa

Chemistry, What is the difference between scale and sludge

What is the difference between scale and sludge

Design of steel structure, in compression member [strut] why no deduction o...

in compression member [strut] why no deduction of area of rivet hole?

Acid test - tests on stones, Acid Test: This test is usually carried...

Acid Test: This test is usually carried out on sand stones to examine the presence of calcium carbonate that weakens the weather resisting quality. In this particular  test,

Traverse, how to fill traverse computation sheet of opened traversig ..

how to fill traverse computation sheet of opened traversig ..

R.c.c square overhead tank, problems in estimating especially in reinforcem...

problems in estimating especially in reinforcement works

Contractor to continue concreting works, Question If on-site slump test fai...

Question If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works ? Answer This is an extremely traditional question raised by

STRUCTURAL DYNAMICS, Consider a diver weighing 200 Ib at the end of a divin...

Consider a diver weighing 200 Ib at the end of a diving board that cantilevers out 3 ft. The diver oscillates at a frequency of 2 Hz. What is the flexural rigidity E I of the divin

Avoidance of designing acute angle of concrete pavement, Q. Avoidance of de...

Q. Avoidance of designing acute angle of concrete pavement The stress persuaded in acute angle corners of concrete pavement is far much higher than right-angle corners of the

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd