Calculate the Benefit-Cost Ratio for Municipal Government Project

With interest at 10%, the benefit-cost ratio for this municipal government project is most nearly:

  Initial cost                                                                          $200,000

  Additional costs at end of years 1 & 2                                 $30,000/yr

  Benefits at end of years 1 & 2                                            $0

  Annual benefits from year's 3 to 10                                     $90,000/yr

Solution:

PW Cost   = $200,000 + $30,000 (P/A, 10%, 2)

    = $200,000 + $30,000 (1.736)

    = $252,080

486_Calculate Benefit Cost Ratio for Government Project.png

PW Benefits = $90,000 (P/A, 10%, 8) (P/F, 10%, 2)     

    = $90,000 (5.335) (0.8264)     

    = $396,800

B/C = $396,800/$252,080 = 1.574


Related Discussions:- Calculate benefit cost ratio for government project

Importance of poles in critical load combinations, Importance of poles in c...

Importance of poles in critical load combinations The poles are generally designed for the following critical load combinations  : (a)  Bending due to wind load on the cable

Dynamics202, Determine the minimum speed of the stunt rider, so that when h...

Determine the minimum speed of the stunt rider, so that when he leaves the ramp at A he passes through the center of the hoop at B. [5 Points] 2. How far h should the landing ramp

Uses of cement, Uses of Cement Cement is utilized widely for the constr...

Uses of Cement Cement is utilized widely for the construction of several structures. Some of them are listed below: (i) Cement slurry is utilized for filling cracks in concr

Numericals on settlement of foundation, A footing foundation for a water to...

A footing foundation for a water tower carries a load of 9000 kN and is 3.6 metres square. It rests on dense sand of 9 m thickness overlying a clay layer of 3 metres depth. The cla

Define marine growth - underwater inspection of bridge, Define Marine growt...

Define Marine growth - underwater inspection of bridge? Generally, in seawater marine growth takes place. Acid generated by the marine growth attacks concrete. This can lead to

Fillet welding, Strength of member when fillet welded

Strength of member when fillet welded

Define hydraulic tools for underwater inspection of bridge, Define Hydrauli...

Define Hydraulic tools for underwater inspection of bridge? Hydraulic tools involve grinders, rotary brushes and scrubbers. The benefits of hydraulic tools are the same as thos

What is the cost of phoenix activity, Q. What is the cost of phoenix activi...

Q. What is the cost of phoenix activity? Phoenix activity has a range of impacts on the Australian economy. Employees lose entitlements when phoenix activity has occurred and w

Track design for line speed improvements, The objective of this module is:-...

The objective of this module is:- For the student to identify the track design issues and there relationships that will need to be considered in the development of a feasibil

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd