Calculate the Benefit-Cost Ratio for Municipal Government Project

With interest at 10%, the benefit-cost ratio for this municipal government project is most nearly:

  Initial cost                                                                          $200,000

  Additional costs at end of years 1 & 2                                 $30,000/yr

  Benefits at end of years 1 & 2                                            $0

  Annual benefits from year's 3 to 10                                     $90,000/yr

Solution:

PW Cost   = $200,000 + $30,000 (P/A, 10%, 2)

    = $200,000 + $30,000 (1.736)

    = $252,080

486_Calculate Benefit Cost Ratio for Government Project.png

PW Benefits = $90,000 (P/A, 10%, 8) (P/F, 10%, 2)     

    = $90,000 (5.335) (0.8264)     

    = $396,800

B/C = $396,800/$252,080 = 1.574


Related Discussions:- Calculate benefit cost ratio for government project

Incremental launching mode of bridge construction, In i ncremental launchin...

In i ncremental launching mode of bridge construction, what are ways adopted to increase sufficient resistance of superstructure during launching practice?

What is over vibration of fresh concrete, Q. What is Over vibration of fres...

Q. What is Over vibration of fresh concrete? For proper compaction of concrete by immersion vibrators, vibrating part of the vibrators must be completely inserted into the conc

Define fathometer with the odolite - sounding/sensing device, Define Fathom...

Define Fathometer with the odolite - Sounding/Sensing Devices? The horizontal scale problem in use of Fathometer can be solved by using equipment, which combines a Fathometer w

Calculate the horizontal distance, Calculate the Horizontal Distance A ...

Calculate the Horizontal Distance A surveyor's total station measured slope distance near station 3245+26.35 is recorded as 437.380-m with a zenith angle of 118º 48' 07" and a

Soil structure, what is soil structure and types of soil structure?

what is soil structure and types of soil structure?

What is diaphragms in bridges, Q. What is Diaphragms in bridges? Diaph...

Q. What is Diaphragms in bridges? Diaphragms in bridges The principal function of diaphragms is to provide stiffening effect to deck slab in case bridge webs aren't situat

Surveying, what are the basic two division of surveying

what are the basic two division of surveying

Define unit hydrograph - hydrology, Define Unit Hydrograph UNIT HYDROGR...

Define Unit Hydrograph UNIT HYDROGRAPH: The hydrograph developed for a drainage basin (watershed) from the runoff of a 1 in or 1 cm storm. It is the base hydrograph from which

Find the size of the foundation required, A steam turbine with base 6 m × 3...

A steam turbine with base 6 m × 3.6 m weighs 10,000 kN. It is to be placed on a clay soil with c = 135 kN/m 2 . Find the size of the foundation needed if the factor of safety is to

Explain about noise absorptive materials, Q. Explain about Noise absorptive...

Q. Explain about Noise absorptive materials? The fundamental mechanism of noise absorptive material is to change the acoustic energy into heat energy. Amount of heat produced i

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd