Calculate benefit cost ratio for government project, Civil Engineering

Assignment Help:

Calculate the Benefit-Cost Ratio for Municipal Government Project

With interest at 10%, the benefit-cost ratio for this municipal government project is most nearly:

  Initial cost                                                                          $200,000

  Additional costs at end of years 1 & 2                                 $30,000/yr

  Benefits at end of years 1 & 2                                            $0

  Annual benefits from year's 3 to 10                                     $90,000/yr

Solution:

PW Cost   = $200,000 + $30,000 (P/A, 10%, 2)

    = $200,000 + $30,000 (1.736)

    = $252,080

486_Calculate Benefit Cost Ratio for Government Project.png

PW Benefits = $90,000 (P/A, 10%, 8) (P/F, 10%, 2)     

    = $90,000 (5.335) (0.8264)     

    = $396,800

B/C = $396,800/$252,080 = 1.574


Related Discussions:- Calculate benefit cost ratio for government project

Define the types of sedimentation, Define the Types of Sedimentation 1....

Define the Types of Sedimentation 1. Type I Particles that settle discretely (settle as individual particles) sand, grit Pre-sedimentation for sand prior to co

Determine the flow rate from the dewatering well, A construction project in...

A construction project involves excavation below grade. A 24 inch diameter dewatering well is installed from grade (EL 586) to 80 ft below grade to lower the water table. Soil bori

Full bore flow in drainage design, Q. Full bore flow in drainage design? ...

Q. Full bore flow in drainage design? In the design of gravity drainage pipes, full bore flow capacity is usually adopted to check against design runoff. Though one should note

Define the phreatic line and phreatic zone, Define the Phreatic Line and Ph...

Define the Phreatic Line and Phreatic Zone Phreatic Line: In an unconfined aquifer, it represents the water table.   Phreatic Zone: In an unconfined aquifer, it is located b

Zero energy building , this is our final year project .please help me to gu...

this is our final year project .please help me to guide about it

Design of masonry, Describe the different types of Ant proof courses

Describe the different types of Ant proof courses

Human resource, Ask question #Minimum 100 words acceFor this discussion, lo...

Ask question #Minimum 100 words acceFor this discussion, look at a specific country of your choice. Develop two brief introductions, one for a U.S. peer, and one for a peer in anot

Sewer, what are the procedure of surveying for sewer projects/

what are the procedure of surveying for sewer projects/

What do you mean by ggbs – cement replacement, Q. What do you mean by GGBS ...

Q. What do you mean by GGBS – cement replacement? From structural point of view GGBS replacement enhances higher durability, lower heat of hydration and higher resistance to su

Levelling, the cooke''s reversible level

the cooke''s reversible level

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd