Bund and dike capacity, Mechanical Engineering

Assignment Help:

Bund / dike capacity is typically covered by local codes and regulations, however some general principles for liquid storage compounds are:

• The net capacity of a bunded / diked compound in a storage facility must be at least 120% of the net capacity of the largest tank. Take into consideration the capacity displaced by other tanks within the same bunded / diked area and any foundations. Treat interconnected tanks as a single tank of equivalent total volume.

• For flammable liquids, bund / dike capacity should be at least 133% of the net capacity of the largest tank. If an automatic fire sprinkler system is installed in or over any bunded / diked tank or drum storage compound, the capacity of the bund / dike should be increased either by a volume equal to the output from the sprinkler system for a period of at least 20 minutes, or to 133% of the capacity of the largest tank, whichever is greater.


Related Discussions:- Bund and dike capacity

Ductile mid brittle material, Ductile mid brittle material: A mater...

Ductile mid brittle material: A material that can undergo large permanent deformation in tension, that is, it can be drawn into wires is called as ductile. A material which

Evaluate elongation because of self weight of tapering rod, Determine elong...

Determine elongation because of self weight of tapering rod: Sol.: Take a tapering rod hung vertically and firmly fixed at top position. The rod is of length L tapers unifor

Calculate additional force required to maintain equilibrium, Calculate Addi...

Calculate Additional force required to maintain equilibrium: Fo r the system shown in figure find the additional single force required to maintain equilibrium. Sol.: L

Quantum mechanics, A ball is dropped from a height .If it takes0.200 second...

A ball is dropped from a height .If it takes0.200 second to cross the last 6.00 m before hitting the ground ,find the height  from which it was dropped . Ans) We need to find H

Find the maximum torque - i-section, Find the maximum torque - I-section: ...

Find the maximum torque - I-section: An I-section 150 × 80 mm has flanges 6 mm thick and web 4 mm thick. Discover the maximum torque that may be safely applied if the shear st

Determine the heat capacity, A chemical works produces an aqueous effluent ...

A chemical works produces an aqueous effluent at above ambient temperature. The Environmental Agency insists that before the effluent is discharged to the river, it must be cooled.

Thermodynamics, determine the relationships between system constants for an...

determine the relationships between system constants for an ideal gas

Computer integrated manufacturing, the component of computer integrated man...

the component of computer integrated manufacturing with the diagram

Cam nomenclature, what is the meaning of translating roller follower and to...

what is the meaning of translating roller follower and total follower travel?

V-block and clamp - angle projection drawing, A V-block clamp consists of 3...

A V-block clamp consists of 3 components, a V-block, yoke and clamping screw.  Using a rule, measure the sketches below and produce a 3rd angle projection drawing for each componen

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd