Break even point:

EM Electricals, Inc., contains fixed costs of Rs. 600,000 this period. Variable costs involved labour charges of Rs.100 per unit and material cost of Rs. 200 per unit. Selling cost of the product is Rs. 500 per unit. The break even point in Rs. is determined as follows:

BEPR = F / (1 - V / P)

Strategic Planning in = 600, 000/ (1 - [200 + 100]/ 500)  = 600, 000/0.4

= Rs. 1,500,000

and the break even point in units is

BEPx = F/(P - V )

= 600, 000 / (500 - (200 + 100))

= 3000 units.


Related Discussions:- Break even point

Water hammer, how can Simulink calculate wave speed of water hammer

how can Simulink calculate wave speed of water hammer

Ecology, subdivisions of ecology

subdivisions of ecology

Find the size of the foundation required, A steam turbine with base 6 m × 3...

A steam turbine with base 6 m × 3.6 m weighs 10,000 kN. It is to be placed on a clay soil with c = 135 kN/m 2 . Find the size of the foundation needed if the factor of safety is to

Diffrence between hudsons and van der meer formula, Q. Diffrence between Hu...

Q. Diffrence between Hudsons and Van der Meer formula? Hudson's formula is usually adopted in preliminary design to attain rough initial estimate of rock size. This formula is

Advantages associated with this kind of material, Question In pumping s...

Question In pumping stations one of choices for the material of water tanks is fibre-reinforced plastic. What are main advantages associated with this kind of material? An

Determine the types of losses of prestress, Determine the types of losses o...

Determine the types of losses of prestress A loss of prestress will affect the stress distribution on a section of the member. It is therefore necessary to estimate the probabl

Define the term - cracking load and proof stress, Define the term - Crackin...

Define the term - Cracking Load and Proof Stress Cracking Load The load on the structural member at the time of the initiation of first visible crack in concrete is know

Raport, CASTE DISCRIMANIMATION

CASTE DISCRIMANIMATION

State the ground water levels, Ground Water Levels The location of the...

Ground Water Levels The location of the ground water level is essential for deep excavation, water-logged areas. The existing wells in the nearby vicinity of the proposed site

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd