Base of concrete retaining walls, Civil Engineering

Assignment Help:

Q. Granular fill or rock fill essential at the base of concrete retaining walls?

It isn't uncommon that rock fill layers and granular fill layers are placed beneath the bottom of concrete retaining walls. Purpose of such provision is to spread the loading in view of insufficient bearing capacity of foundation material to maintain the loads of retaining walls.

Upon placing of rockfill layers and granular fill layers, same imposed loads are supported by a larger area of founding material and therefore stress exerted by loads is decreased accordingly.

Layers of rockfill and granular fill materials aren't standard details of concrete retaining wall. If we are fully satisfied that founding material could support the loads arising from retaining walls, it isn't essential to provide these layers of rockfill and granular fill materials.


Related Discussions:- Base of concrete retaining walls

Use of primers in joint sealant, Q. Use of primers in joint sealant? Mo...

Q. Use of primers in joint sealant? Most of the joint sealants applied in concrete joints are adhesive and recommended joint width/depth of joint sealant is from 2:1 to 1:1 as

Ocf, location of hydrolic jump

location of hydrolic jump

Angular messurement using total stations, write a short note on angular mes...

write a short note on angular messurement using stations?

How will you pay, when i have solved the given assignment work then how wil...

when i have solved the given assignment work then how will you pay me for that work??

The right triangle, a lighthouse standing on the cliff observed from two op...

a lighthouse standing on the cliff observed from two open boats A and B in a vertical plane thourgh the lighthouse.the angle of elevation of the top of the lighthouse viewed from B

Distomat, applications of distomat in briefly

applications of distomat in briefly

Construction material, 4. Calculate the loose volume of material needed to ...

4. Calculate the loose volume of material needed to fill in the trench as sketched below. The following information is also known: [7] o Length of trench = 250 m o Trench

Mortar mechanism vs stone contact mechanism, "Mortar mechanism" vs. "stone ...

"Mortar mechanism" vs. "stone contact mechanism" in bituminous materials 'Stone contact mechanism' applies to well graded aggregates coated with bitumen (for example dense bit

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd