Q. Granular fill or rock fill essential at the base of concrete retaining walls?
It isn't uncommon that rock fill layers and granular fill layers are placed beneath the bottom of concrete retaining walls. Purpose of such provision is to spread the loading in view of insufficient bearing capacity of foundation material to maintain the loads of retaining walls.
Upon placing of rockfill layers and granular fill layers, same imposed loads are supported by a larger area of founding material and therefore stress exerted by loads is decreased accordingly.
Layers of rockfill and granular fill materials aren't standard details of concrete retaining wall. If we are fully satisfied that founding material could support the loads arising from retaining walls, it isn't essential to provide these layers of rockfill and granular fill materials.
Q- What are loads and forces taken into account for designing a pile and what is load carrying capacity of a pile. Ans. For designing a pile the following loads and force ar
Ask question #chaining and rangingMinimum 100 words accepted#
Explain coulomb''s wedge theory-definition and derivation
Define Surface Cleaning Tools for Underwater Inspection of Bridge? To perform a thorough inspection, the marine growth on the structure must be removed. This can be done by var
Breakwater and its types
Determine the Steps for routine inspection? A routine inspection should normally include: - A Level I inspection on 100% of the underwater portion of the structure to determ
pert disadvantages of software support, datacollection , interpretation of results issues
Widening on Curves: Pavements have to be widened on curves because of the fact that : (a) the vehicle has a wheel base and overhang on the front and rear, and the vehicle
Soil at a borrow area has a total unit weight of 120-PCF and a water content of 15 percent. The soil from the borrow area will be used as structural fill and compacted to an avera
Disadvantages of cement sand mortor
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd