Assume the length of critical path in a project, Operation Management

Assignment Help:

Suppose the length of critical path in a project is 40 days and the standard deviation is 2 days. What due date should be set for the project so that the probability of completing the project is 95%? Round the answer to the nearest higher integer.


Related Discussions:- Assume the length of critical path in a project

Explain to inspire maximum performance, Many writers have stated that effec...

Many writers have stated that effective objectives should be- A. Broad - to cover many dimensions of the business B. Measurable - to track progress C. Unachievable - to in

Explain network design is a key business decision, Network design is a key ...

Network design is a key business decision as well as a technological decision. Why? Provide an example of a company you believe has a good network design, providing supporting rati

Identify the business level strategy of walmart corporation, Looking at Wal...

Looking at Walmart Corporation, identify it's Business Level Strategy. Short paper format about 100-300 words or as needed.

Explain delivered weekly freestanding ads, How your local newspaper would b...

How your local newspaper would be affected if local supermarkets switched to weekly advertising and instead used a service that delivered weekly freestanding ads directly to each h

Mba program has a high emphasis on ethical decision, Why do you think the c...

Why do you think the capstone course for the MBA program has a heavy emphasis on ethical decision making?

Explain how many people would you expect to be waiting, Suzy, a bartender, ...

Suzy, a bartender, can serve drinks at the average rate of one every 35 sec. During a hot evening recently, the bar was particularly busy and every 45 sec someone was at the bar as

Explain how many observations would be needed, To determine the standard wo...

To determine the standard working time for a special job, following observation data is collected: Observation 1 2 3 4 5 6 7 8 Time (in second) 17 18 15 14 13 15 16 13 a) If the pe

Production control, Production Control After planning the next manageri...

Production Control After planning the next managerial production function is to control the production according to the production plans because production plans cannot be acti

Investment Management Assignment, Prepare an in-depth report recommending t...

Prepare an in-depth report recommending the appropriate investment of AUD$3 million for a five year investment period for a particular investment client. The investment portfolio i

Explain were the colonists more responsible for winning it, Need reference/...

Need reference/cited for this question. • Were the British more responsible for losing the war or were the colonists more responsible for winning it? Use specific examples fr

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd