Asphalt mix design – durability and stability, Civil Engineering

Assignment Help:

Q. Asphalt mix design - durability vs. stability?

The main aim of asphalt mix design is to achieve a mix with economical blending of aggregates with asphalt to achieve the following: 

(i) Workability to facilitate easy placement of bituminous materials without experiencing segregation;

(ii) Sufficient stability so that under traffic loads the pavement won't undergo distortion and displacement

(iii) Durability by having sufficient asphalt

(iv)  Sufficient air voids

In asphalt mix design, high durability is generally attained at the expense of low stability. Therefore a balance has to be stricken between durability and stability requirements.


Related Discussions:- Asphalt mix design – durability and stability

Functions of bedding below storm water drains, Question What are main funct...

Question What are main functions of bedding below storm water drains ? Answer Bedding that is normally made of granular resources or concrete serves four main functions as optio

What do you mean by stock verification sheets, Q. What do you mean by Stock...

Q. What do you mean by Stock Verification Sheets? The proper custody and accountal of stores is the prime duty and function of an executive or the stockholder. To ensure this v

Water sources and requirements, Water Sources and Requirements: In thi...

Water Sources and Requirements: In this part, we have discussed: (a) Basic concepts in planning of water supply schemes. (b) Various types of water requirement. (c) S

Rolling - binder, Rolling - Binder: The layer thickness is 40-50 mm. R...

Rolling - Binder: The layer thickness is 40-50 mm. Rolling is done in three stages : Initial Rolling By 80-100 kN smooth wheeled roller. Intermediate Rolling B

Surving, describe the methods of reducing the levels,and their relative adv...

describe the methods of reducing the levels,and their relative advantages and disadvantages.

WMM, GRADATION OF WMM

GRADATION OF WMM

Calculate the total duration for the four activity project, Calculate the T...

Calculate the Total Duration for the Four Activity Project Solution:      Scheduling work activity has associated time duration. The durations shown in the Table were e

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd