Aspects of scheduling , Mechanical Engineering

Assignment Help:

Aspects Of Scheduling 

The difficulty is a modification of a flexible manufacturing cell at ABB's plant for the manufacturing of turbocharger in Baden, Switzerland. The difficulty is a little modified to make it  more demanding via eliminating one lading station (or else the average use of the loading stations is below 40 percent for full use of all machines) and via changing the part mix to acquire an extra uniform distribution of the load in the system. Two various cases are considered. In the initial condition, the original loading times and continuous order release throughout the shifts are supposed. This concludes in moderate average queue lengths. In the second condition, the loading times are raised, various load levels for machines are generated, and the orders are released merely at the starting of each shift. These results in a considerably more tough decision problem at the loading station where currently long queues exists and the that termed as shading effect occurs.

The layout of the flexible manufacturing system is depicted in following figure. Within the underlying industrial system, there are five machines and two of them identical and two loading stations, a deburring station, and a washing station. Now, this is supposed that only one loading station is obtainable, or else utilization of the loading stations is restricted to only 40 percent. All parts have to be loaded initially after that one or two machining operations obey, and after that deburring, reloading, washing, another one or two machining operations, deburring, unloading and washing.

                         1141_Aspects Of Scheduling.png

                                            Figure: Layout of FMS

There are 11 elements types. The greatest number of operations per element type is 11, the smallest is nine. Flow diagram of all 11 elements types are represented in following figure. The operation times for machining operations are specified in Table no.1. Operation times at the stations WASH, LOAD, DEBUR are equal for all the parts. During case 1, the operation times are as:

 

Initial loading

 

8 min

 

Unload/reload

 

13 min

 

Final unloading

 

5 min

 

Deburring (each time)

 

8 min

 

Washing (each time)

 

6 min

During case 2, all the operation times on the loading stations are raised via five minutes; the other operation times keep not changed. This generates a bottleneck on the loading station through that all elements should pass three times, and thus a more demanding decision difficulty at the loading stations results.

                         1366_Aspects Of Scheduling 1.png

                                     Figure: Machining Sequences for Part Types

                                        Table no.1: Machining Times for Part Types

 

 

                                     975_Aspects Of Scheduling 2.png


Related Discussions:- Aspects of scheduling

Heat engine - thermodynamics, HEAT ENGINE - Thermodynamics: HE A T ...

HEAT ENGINE - Thermodynamics: HE A T ENGINE. A heat engine is a thermodynamics system that operates in a cycle in which heat can be transferred from heat source to heat si

How can we transfer data among cad system, How can we transfer data among C...

How can we transfer data among CAD system The three main reasons for transferring data among CAD systems (or CAE systems or agents etc.) are : (i)  To communicate with remot

Determine the ratio of the inlet pipe diameter, Air flows steadily at the r...

Air flows steadily at the rate of 0.5 kg/s through an air compressor, entering at 7m/s velocity, 100 kPa pressure, and 0.95 m 3 /kg volume, and leaving at 5 m/s, 700 kPa, and 0.19

Develop-implement method to identify numerically equivalent, For example, i...

For example, if one were provided with the set [3 1 3 -4 -6], the resulting answers would be [3 1 -4], [3 1 -4], an [3 3 -6], as these are the three sets of three values which sum

Determine the best possible angle to reduce aerodynamic drag, This is to de...

This is to determine the best possible angle to reduce aerodynamic drag. Mesh is to use tetrahedron of 0.5m wide.  I need the mesh generation and solver control on ansys 11.0. I al

Composites , For an automotive component of your choice that is traditional...

For an automotive component of your choice that is traditionally metallic, review how it could be re-engineered as a composite? How factors such as fibre & matrix type, fibre volum

Internal and external diameters - solid shaft, Internal and external diamet...

Internal and external diameters - solid shaft: Two shafts are of the similar material, length & weight. One is solid & of 100 mm diameter, the outer is hollow. If hollow shaft

Refrigeration cycle, 1.5kw/ton of refrigeration is required to maintain tem...

1.5kw/ton of refrigeration is required to maintain temp of -40c in the refrigerator.if the cycle works on carnot cycle.determine 1.cop,2.sink temp 3. heat rejejected to the sink/to

Discover the maximum torque, Discover the maximum torque: Discover the...

Discover the maximum torque: Discover the maximum torque that may be transmitted by the shaft of 400 mm diameter, if the shear stress is not to exceed 50 N/mm 2 . Solution

Thermodynamic 1st law, What is the diff between system underfoing cycle and...

What is the diff between system underfoing cycle and system undergoing process

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd