Aspects of scheduling , Mechanical Engineering

Assignment Help:

Aspects Of Scheduling 

The difficulty is a modification of a flexible manufacturing cell at ABB's plant for the manufacturing of turbocharger in Baden, Switzerland. The difficulty is a little modified to make it  more demanding via eliminating one lading station (or else the average use of the loading stations is below 40 percent for full use of all machines) and via changing the part mix to acquire an extra uniform distribution of the load in the system. Two various cases are considered. In the initial condition, the original loading times and continuous order release throughout the shifts are supposed. This concludes in moderate average queue lengths. In the second condition, the loading times are raised, various load levels for machines are generated, and the orders are released merely at the starting of each shift. These results in a considerably more tough decision problem at the loading station where currently long queues exists and the that termed as shading effect occurs.

The layout of the flexible manufacturing system is depicted in following figure. Within the underlying industrial system, there are five machines and two of them identical and two loading stations, a deburring station, and a washing station. Now, this is supposed that only one loading station is obtainable, or else utilization of the loading stations is restricted to only 40 percent. All parts have to be loaded initially after that one or two machining operations obey, and after that deburring, reloading, washing, another one or two machining operations, deburring, unloading and washing.

                         1141_Aspects Of Scheduling.png

                                            Figure: Layout of FMS

There are 11 elements types. The greatest number of operations per element type is 11, the smallest is nine. Flow diagram of all 11 elements types are represented in following figure. The operation times for machining operations are specified in Table no.1. Operation times at the stations WASH, LOAD, DEBUR are equal for all the parts. During case 1, the operation times are as:

 

Initial loading

 

8 min

 

Unload/reload

 

13 min

 

Final unloading

 

5 min

 

Deburring (each time)

 

8 min

 

Washing (each time)

 

6 min

During case 2, all the operation times on the loading stations are raised via five minutes; the other operation times keep not changed. This generates a bottleneck on the loading station through that all elements should pass three times, and thus a more demanding decision difficulty at the loading stations results.

                         1366_Aspects Of Scheduling 1.png

                                     Figure: Machining Sequences for Part Types

                                        Table no.1: Machining Times for Part Types

 

 

                                     975_Aspects Of Scheduling 2.png


Related Discussions:- Aspects of scheduling

Define conceptual engineering phase for project, Q. Define Conceptual Engin...

Q. Define Conceptual Engineering Phase for project? The primary objective of this stage is to include and clearly define the economic feasibility of the project, sensitivity to

Calculate the shear flows at the wall, The tapered, two-cell beam is subjec...

The tapered, two-cell beam is subjected to a pure torque of 50,000 in-lb counter clockwise. The length of the beam (normal to the figure) is 100 in. The flange areas are 1 sq in an

Resource management for project, Q. Resource Management for project? An...

Q. Resource Management for project? An important factor in overall project success is the provision of suitable and adequate resources. The initial estimate of engineering man

Find the minimum power of the pump, Consider the power system as designed b...

Consider the power system as designed below. The duty fluid is water, and has a mass flow 0.75 kg/ s and all piping through which the liquid flows has diameter 1'', while the steam

Evaluate the angular velocity, In a 4-Bar process the following data is giv...

In a 4-Bar process the following data is given :- Length of crank (AB) = 300 mm, Length of link AD = 600 mm, Length of links BC = CD = 360 mm, Angle BAD ie ∠BAD = 60o ,

Cone of friction, Con e of Friction: When the body is having impending...

Con e of Friction: When the body is having impending motion   in direction of P , the frictional force will be limiting friction and the resultant reaction R wil

Types of cooling system , Types of Cooling System: Two types of cooling sy...

Types of Cooling System: Two types of cooling system are used in two wheelers. (a) Natural air-cooling. (b) Forced air-cooling.

Advantages of pinion cutter generating process, Advantages of Pinion Cutter...

Advantages of Pinion Cutter Generating Process 1. A single cutter can be used for cutting all spur gears of identical pitch as that of the cutter. 2. Internal gears can be g

Find power transmitted by cross type belt, Find power transmitted by cross ...

Find power transmitted by cross type belt: Find power transmitted by cross type belt drive connecting two pulley of diameter 45.0cm and 20.0cm that are 1.95m apart. The max

#strength of material, State elongation of a conical bar due to its self we...

State elongation of a conical bar due to its self weight?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd