Aspects of scheduling , Mechanical Engineering

Assignment Help:

Aspects Of Scheduling 

The difficulty is a modification of a flexible manufacturing cell at ABB's plant for the manufacturing of turbocharger in Baden, Switzerland. The difficulty is a little modified to make it  more demanding via eliminating one lading station (or else the average use of the loading stations is below 40 percent for full use of all machines) and via changing the part mix to acquire an extra uniform distribution of the load in the system. Two various cases are considered. In the initial condition, the original loading times and continuous order release throughout the shifts are supposed. This concludes in moderate average queue lengths. In the second condition, the loading times are raised, various load levels for machines are generated, and the orders are released merely at the starting of each shift. These results in a considerably more tough decision problem at the loading station where currently long queues exists and the that termed as shading effect occurs.

The layout of the flexible manufacturing system is depicted in following figure. Within the underlying industrial system, there are five machines and two of them identical and two loading stations, a deburring station, and a washing station. Now, this is supposed that only one loading station is obtainable, or else utilization of the loading stations is restricted to only 40 percent. All parts have to be loaded initially after that one or two machining operations obey, and after that deburring, reloading, washing, another one or two machining operations, deburring, unloading and washing.

                         1141_Aspects Of Scheduling.png

                                            Figure: Layout of FMS

There are 11 elements types. The greatest number of operations per element type is 11, the smallest is nine. Flow diagram of all 11 elements types are represented in following figure. The operation times for machining operations are specified in Table no.1. Operation times at the stations WASH, LOAD, DEBUR are equal for all the parts. During case 1, the operation times are as:

 

Initial loading

 

8 min

 

Unload/reload

 

13 min

 

Final unloading

 

5 min

 

Deburring (each time)

 

8 min

 

Washing (each time)

 

6 min

During case 2, all the operation times on the loading stations are raised via five minutes; the other operation times keep not changed. This generates a bottleneck on the loading station through that all elements should pass three times, and thus a more demanding decision difficulty at the loading stations results.

                         1366_Aspects Of Scheduling 1.png

                                     Figure: Machining Sequences for Part Types

                                        Table no.1: Machining Times for Part Types

 

 

                                     975_Aspects Of Scheduling 2.png


Related Discussions:- Aspects of scheduling

Determine about the extent of excavation, Determine about the extent of exc...

Determine about the extent of excavation The extent of excavation depends upon the construction problems like dewatering and uplift. In extreme cases anchoring of the box may b

Cement, wet process of portland cement

wet process of portland cement

Sizing a solar pv system, The Rusk's own fairly large house near San Franci...

The Rusk's own fairly large house near San Francisco and the following spreadsheet shows their month to month power use for two years.  1. What is their monthly average power us

Design a remote controlled buggy, You are required, as part of a small team...

You are required, as part of a small team, to design a remote controlled buggy that can be made to move forwards, backwards and from side to side. The basic buggy and motors are pr

Define principal process for electron beam machining, Define Principal Proc...

Define Principal Process for Electron Beam Machining A beam of electrons is emitted from the electron gun which is basically following three points. 1. A cathode whic

Space for coil removal, Q. Space for coil removal? Locations, of all co...

Q. Space for coil removal? Locations, of all coils clearly indicated on the drawings. Provide adequate space for coil removal, and access doors on both sides. Flexible connecti

What are the special considerations in planning, What are the Special Consi...

What are the Special Considerations in Planning The dimensions of the foundation should be such that for low-speed machines (operating speed less than 500  rpm) the natural fre

Briefly explain how geothermal powerplant operate, Illustrate types of nucl...

Illustrate types of nuclear reactors with diagrams? a) Give advantages and disadvantages of nuclear power plant? b) Briefly explain how geothermal powerplant operate with fig

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd