Aspects of scheduling , Mechanical Engineering

Assignment Help:

Aspects Of Scheduling 

The difficulty is a modification of a flexible manufacturing cell at ABB's plant for the manufacturing of turbocharger in Baden, Switzerland. The difficulty is a little modified to make it  more demanding via eliminating one lading station (or else the average use of the loading stations is below 40 percent for full use of all machines) and via changing the part mix to acquire an extra uniform distribution of the load in the system. Two various cases are considered. In the initial condition, the original loading times and continuous order release throughout the shifts are supposed. This concludes in moderate average queue lengths. In the second condition, the loading times are raised, various load levels for machines are generated, and the orders are released merely at the starting of each shift. These results in a considerably more tough decision problem at the loading station where currently long queues exists and the that termed as shading effect occurs.

The layout of the flexible manufacturing system is depicted in following figure. Within the underlying industrial system, there are five machines and two of them identical and two loading stations, a deburring station, and a washing station. Now, this is supposed that only one loading station is obtainable, or else utilization of the loading stations is restricted to only 40 percent. All parts have to be loaded initially after that one or two machining operations obey, and after that deburring, reloading, washing, another one or two machining operations, deburring, unloading and washing.

                         1141_Aspects Of Scheduling.png

                                            Figure: Layout of FMS

There are 11 elements types. The greatest number of operations per element type is 11, the smallest is nine. Flow diagram of all 11 elements types are represented in following figure. The operation times for machining operations are specified in Table no.1. Operation times at the stations WASH, LOAD, DEBUR are equal for all the parts. During case 1, the operation times are as:

 

Initial loading

 

8 min

 

Unload/reload

 

13 min

 

Final unloading

 

5 min

 

Deburring (each time)

 

8 min

 

Washing (each time)

 

6 min

During case 2, all the operation times on the loading stations are raised via five minutes; the other operation times keep not changed. This generates a bottleneck on the loading station through that all elements should pass three times, and thus a more demanding decision difficulty at the loading stations results.

                         1366_Aspects Of Scheduling 1.png

                                     Figure: Machining Sequences for Part Types

                                        Table no.1: Machining Times for Part Types

 

 

                                     975_Aspects Of Scheduling 2.png


Related Discussions:- Aspects of scheduling

Determine for water flow rate, A counter flow heat exchanger is used to coo...

A counter flow heat exchanger is used to cool 2000kg/hr of oil(Cp= 2.5 KJ/Kg K) from 105 o C to 30 o C by the use of water entering at 15 o C. If the overall heat transfer coeff

Manufacturing process for reinforced plastic parts, Manufacturing Process F...

Manufacturing Process For Reinforced Plastic Parts Two processes that are open mould and close mould are commonly utilized for manufacture of reinforced parts. Hand layup proce

Determine the maximum value of the coefficient of friction, Determine the m...

Determine the maximum value of the coefficient of friction: A force of 200 N inclined at 60 o to the horizontal is applied to the block A weighing 400 N. find out whether blo

Use of high temperature material flare tips, Q. Use of high temperature mat...

Q. Use of high temperature material Flare Tips? A variety of high temperature alloys (typically stainless steels and/or nickel-base alloys) are employed in the construction of

Capp for casting and welding, CAPP for Casting and Welding In this , w...

CAPP for Casting and Welding In this , we have studied the CAPP systems for Casting and Welding processes. Compared to the traditional (manual) process planning methods, CAPP

Which three principal possible in radial drilling machine, Which three prin...

Which three principal possible in radial drilling machine Between them the plain drill machine, three principal movements are possible in this type of machine, by vertical move

Explain about the eccentrically loaded footings, Explain about the eccentri...

Explain about the eccentrically loaded footings. ECCENTRICALLY LOADED FOOTINGS When footings have overturning moments and axial loads, the base pressure under the footing wi

Locomotive boiler, What are the advantages and disadvantaged of locomotive ...

What are the advantages and disadvantaged of locomotive boilers

Theory of production process, In Grey Cast Iron, carbon is present in -----...

In Grey Cast Iron, carbon is present in ------------form while in white cast iron, it is found in ----------- form.

Pultrusion, Pultrusion Structure sections of long length are generated...

Pultrusion Structure sections of long length are generated by putting the fibres via resin bath and heated dies of exact shapes. Unidirectional fibres along with high volume f

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd