Aspects of scheduling , Mechanical Engineering

Assignment Help:

Aspects Of Scheduling 

The difficulty is a modification of a flexible manufacturing cell at ABB's plant for the manufacturing of turbocharger in Baden, Switzerland. The difficulty is a little modified to make it  more demanding via eliminating one lading station (or else the average use of the loading stations is below 40 percent for full use of all machines) and via changing the part mix to acquire an extra uniform distribution of the load in the system. Two various cases are considered. In the initial condition, the original loading times and continuous order release throughout the shifts are supposed. This concludes in moderate average queue lengths. In the second condition, the loading times are raised, various load levels for machines are generated, and the orders are released merely at the starting of each shift. These results in a considerably more tough decision problem at the loading station where currently long queues exists and the that termed as shading effect occurs.

The layout of the flexible manufacturing system is depicted in following figure. Within the underlying industrial system, there are five machines and two of them identical and two loading stations, a deburring station, and a washing station. Now, this is supposed that only one loading station is obtainable, or else utilization of the loading stations is restricted to only 40 percent. All parts have to be loaded initially after that one or two machining operations obey, and after that deburring, reloading, washing, another one or two machining operations, deburring, unloading and washing.

                         1141_Aspects Of Scheduling.png

                                            Figure: Layout of FMS

There are 11 elements types. The greatest number of operations per element type is 11, the smallest is nine. Flow diagram of all 11 elements types are represented in following figure. The operation times for machining operations are specified in Table no.1. Operation times at the stations WASH, LOAD, DEBUR are equal for all the parts. During case 1, the operation times are as:

 

Initial loading

 

8 min

 

Unload/reload

 

13 min

 

Final unloading

 

5 min

 

Deburring (each time)

 

8 min

 

Washing (each time)

 

6 min

During case 2, all the operation times on the loading stations are raised via five minutes; the other operation times keep not changed. This generates a bottleneck on the loading station through that all elements should pass three times, and thus a more demanding decision difficulty at the loading stations results.

                         1366_Aspects Of Scheduling 1.png

                                     Figure: Machining Sequences for Part Types

                                        Table no.1: Machining Times for Part Types

 

 

                                     975_Aspects Of Scheduling 2.png


Related Discussions:- Aspects of scheduling

Engineering Mechanic, with usual notations the effort lost due to friction ...

with usual notations the effort lost due to friction is given by A) P-W/V.R B) P×V.R-W C) P-W×V.R D) P+W/V.R

Evaluate cross-section of leaves, A semi-elliptic multi-leaf spring is need...

A semi-elliptic multi-leaf spring is needed for the suspension of the rear axle of a truck. It consists of two extra full-length leaves and ten graduated length leaves including th

Mechanical design of the blowdown systems, Q. Mechanical design of the blow...

Q. Mechanical design of the blowdown systems? Mechanical design of the blowdown systems shall be sized for a continuous blowdown of a minimum of 1.0% of MCR. Fabricator may re

About moment of inertia, what is the difference between polar and mass mom...

what is the difference between polar and mass moment of inertia?

What is strap footing, What is strap footing? Strap Footing You have...

What is strap footing? Strap Footing You have to use cantilever or strap footings when the proximity of a property line precludes the use of other types for example an isola

Calculate the primary voltage and real power measurements, Question: A ...

Question: A 7.2kVA single phase 50Hz, 480Vrms: 240Vrms transformer can be modelled using the primary referred approximate equivalent circuit shown in Figure 1 below. Fi

Find cutting speed for prolonging tool life , Find Cutting Speed for Prolon...

Find Cutting Speed for Prolonging Tool Life A form tool machining at 24 m/minute requires re-sharpening after 30 minutes. What should be the cutting speed for prolonging tool

Calculate the whole reaction at block, Calculate the whole reaction at bloc...

Calculate the whole reaction at block: A bar weighing 1 kg/m is bent at right angles into segments 0.60 m and 0.30 m long. It takes the position illustrated in Figure, while t

Dismantle crank case and explode main shaft-gear complaints, Dismantle cran...

Dismantle crank case and explode main shaft , counter shaft, gear shifter drum and kick spindle assembly and check sequence of parts fitment while dismantling: Check all gear teeth

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd