Aspects of scheduling , Mechanical Engineering

Assignment Help:

Aspects Of Scheduling 

The difficulty is a modification of a flexible manufacturing cell at ABB's plant for the manufacturing of turbocharger in Baden, Switzerland. The difficulty is a little modified to make it  more demanding via eliminating one lading station (or else the average use of the loading stations is below 40 percent for full use of all machines) and via changing the part mix to acquire an extra uniform distribution of the load in the system. Two various cases are considered. In the initial condition, the original loading times and continuous order release throughout the shifts are supposed. This concludes in moderate average queue lengths. In the second condition, the loading times are raised, various load levels for machines are generated, and the orders are released merely at the starting of each shift. These results in a considerably more tough decision problem at the loading station where currently long queues exists and the that termed as shading effect occurs.

The layout of the flexible manufacturing system is depicted in following figure. Within the underlying industrial system, there are five machines and two of them identical and two loading stations, a deburring station, and a washing station. Now, this is supposed that only one loading station is obtainable, or else utilization of the loading stations is restricted to only 40 percent. All parts have to be loaded initially after that one or two machining operations obey, and after that deburring, reloading, washing, another one or two machining operations, deburring, unloading and washing.

                         1141_Aspects Of Scheduling.png

                                            Figure: Layout of FMS

There are 11 elements types. The greatest number of operations per element type is 11, the smallest is nine. Flow diagram of all 11 elements types are represented in following figure. The operation times for machining operations are specified in Table no.1. Operation times at the stations WASH, LOAD, DEBUR are equal for all the parts. During case 1, the operation times are as:

 

Initial loading

 

8 min

 

Unload/reload

 

13 min

 

Final unloading

 

5 min

 

Deburring (each time)

 

8 min

 

Washing (each time)

 

6 min

During case 2, all the operation times on the loading stations are raised via five minutes; the other operation times keep not changed. This generates a bottleneck on the loading station through that all elements should pass three times, and thus a more demanding decision difficulty at the loading stations results.

                         1366_Aspects Of Scheduling 1.png

                                     Figure: Machining Sequences for Part Types

                                        Table no.1: Machining Times for Part Types

 

 

                                     975_Aspects Of Scheduling 2.png


Related Discussions:- Aspects of scheduling

Determine the stress in composite bar, Determine the stress in composite ba...

Determine the stress in composite bar: How do you determine the stress in composite bar? What is Modular Ratio? Sol.: It becomes essential to have a compound tie or strut

Evaluate crippling load, A column of timber section 15cm x 20cm is 6 meter ...

A column of timber section 15cm x 20cm is 6 meter long both side being fixed. If the youngs modulus for timber is 17.5 KN/mm 2 , Evaluate: a) Crippling load and b) Safe load

Concept of continum, in concept of continum what is the meaning of upper cu...

in concept of continum what is the meaning of upper cure

Discover the increase in pressure, Discover the increase in pressure: ...

Discover the increase in pressure: A copper tube of 50 mm diameter and 1200 mm length contains a thickness of 1.2 mm along closed ends. This is filled with water at atmospheri

Explain cutting speed - cutting parameters, Explain Cutting Speed - Cutting...

Explain Cutting Speed - Cutting Parameters It is relative speed (V 1 ) between wheel and the Work piece. It is expressed in m/sec.   V=Cutting speed=V 1   =

Determine the reactions at supported end, A steel dia 10 mm passes through ...

A steel dia 10 mm passes through a brass tube of internal dia 15mm and external dia is 25 mm. The bolt is tightened by a nut. The length of tube is reduced by 1.5mm and the length

Cross drainage works, Cross Drainage Works: Culverts A large ...

Cross Drainage Works: Culverts A large number of culverts are needed for taking care of the streams crossing the railway lines. The culverts can be one of the followi

Manufacturing, #draw a net sketch of the geometry of a single point tool.

#draw a net sketch of the geometry of a single point tool.

Pulleys, what do you mean by law of belting and also explain the crowning o...

what do you mean by law of belting and also explain the crowning of pulleys ?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd