Aspects of scheduling , Mechanical Engineering

Assignment Help:

Aspects Of Scheduling 

The difficulty is a modification of a flexible manufacturing cell at ABB's plant for the manufacturing of turbocharger in Baden, Switzerland. The difficulty is a little modified to make it  more demanding via eliminating one lading station (or else the average use of the loading stations is below 40 percent for full use of all machines) and via changing the part mix to acquire an extra uniform distribution of the load in the system. Two various cases are considered. In the initial condition, the original loading times and continuous order release throughout the shifts are supposed. This concludes in moderate average queue lengths. In the second condition, the loading times are raised, various load levels for machines are generated, and the orders are released merely at the starting of each shift. These results in a considerably more tough decision problem at the loading station where currently long queues exists and the that termed as shading effect occurs.

The layout of the flexible manufacturing system is depicted in following figure. Within the underlying industrial system, there are five machines and two of them identical and two loading stations, a deburring station, and a washing station. Now, this is supposed that only one loading station is obtainable, or else utilization of the loading stations is restricted to only 40 percent. All parts have to be loaded initially after that one or two machining operations obey, and after that deburring, reloading, washing, another one or two machining operations, deburring, unloading and washing.

                         1141_Aspects Of Scheduling.png

                                            Figure: Layout of FMS

There are 11 elements types. The greatest number of operations per element type is 11, the smallest is nine. Flow diagram of all 11 elements types are represented in following figure. The operation times for machining operations are specified in Table no.1. Operation times at the stations WASH, LOAD, DEBUR are equal for all the parts. During case 1, the operation times are as:

 

Initial loading

 

8 min

 

Unload/reload

 

13 min

 

Final unloading

 

5 min

 

Deburring (each time)

 

8 min

 

Washing (each time)

 

6 min

During case 2, all the operation times on the loading stations are raised via five minutes; the other operation times keep not changed. This generates a bottleneck on the loading station through that all elements should pass three times, and thus a more demanding decision difficulty at the loading stations results.

                         1366_Aspects Of Scheduling 1.png

                                     Figure: Machining Sequences for Part Types

                                        Table no.1: Machining Times for Part Types

 

 

                                     975_Aspects Of Scheduling 2.png


Related Discussions:- Aspects of scheduling

Computer integrated manufacturing, the component of computer integrated man...

the component of computer integrated manufacturing with the diagram

Calculate quantity of steam in the vessel - thermodynamics, Calculate quant...

Calculate quantity of steam in the vessel - thermodynamics: A closed metallic boiler drum having capacity of 0.24m 3 contains steam at pressure of 11bar and a temperature

Stockholm conference, define environment and explain stockholm conference

define environment and explain stockholm conference

Kinematics, Kinematics: We have seen the various types of motions whic...

Kinematics: We have seen the various types of motions which may be undergone by particles and rigid bodies. You may be able to understand the relationships of displacement, ve

Estimate what fraction of heat loss by the fin, A tube assembly constructed...

A tube assembly constructed of Cu with an inside diameter of 1.25 cm, wall thickness of 0.8 mm and circumferential fins around the periphery. The fins have thickness of 3 mm, and a

Combustion chamber and radiant section, Q. Combustion Chamber and Radiant S...

Q. Combustion Chamber and Radiant Section? The combustion chamber and the radiant heat transfer section of the Steam Generators shall be a horizontal, multiple pass arrangement

What is pressure testing, Q. What is Pressure Testing? Pressure test sh...

Q. What is Pressure Testing? Pressure test shall be performed after completion of all welds and the PWHT of the boiler. Prior to final inspection and pressure test, the insi

Determine thermal efficiency of the cycle, (a) Compare otto, Diesel and Dua...

(a) Compare otto, Diesel and Dual combustion cycle on the basis of compression ratio, same compression ration and same Heat input and constant maximum pressure and heat supplied.

Explain about unit pipe racks, Q. Explain about Unit pipe racks? Unit p...

Q. Explain about Unit pipe racks? Unit pipe racks are the main arteries carrying the pipes and cables into the units, and as such should be centrally located. They are usually

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd