Aspects of scheduling , Mechanical Engineering

Assignment Help:

Aspects Of Scheduling 

The difficulty is a modification of a flexible manufacturing cell at ABB's plant for the manufacturing of turbocharger in Baden, Switzerland. The difficulty is a little modified to make it  more demanding via eliminating one lading station (or else the average use of the loading stations is below 40 percent for full use of all machines) and via changing the part mix to acquire an extra uniform distribution of the load in the system. Two various cases are considered. In the initial condition, the original loading times and continuous order release throughout the shifts are supposed. This concludes in moderate average queue lengths. In the second condition, the loading times are raised, various load levels for machines are generated, and the orders are released merely at the starting of each shift. These results in a considerably more tough decision problem at the loading station where currently long queues exists and the that termed as shading effect occurs.

The layout of the flexible manufacturing system is depicted in following figure. Within the underlying industrial system, there are five machines and two of them identical and two loading stations, a deburring station, and a washing station. Now, this is supposed that only one loading station is obtainable, or else utilization of the loading stations is restricted to only 40 percent. All parts have to be loaded initially after that one or two machining operations obey, and after that deburring, reloading, washing, another one or two machining operations, deburring, unloading and washing.

                         1141_Aspects Of Scheduling.png

                                            Figure: Layout of FMS

There are 11 elements types. The greatest number of operations per element type is 11, the smallest is nine. Flow diagram of all 11 elements types are represented in following figure. The operation times for machining operations are specified in Table no.1. Operation times at the stations WASH, LOAD, DEBUR are equal for all the parts. During case 1, the operation times are as:

 

Initial loading

 

8 min

 

Unload/reload

 

13 min

 

Final unloading

 

5 min

 

Deburring (each time)

 

8 min

 

Washing (each time)

 

6 min

During case 2, all the operation times on the loading stations are raised via five minutes; the other operation times keep not changed. This generates a bottleneck on the loading station through that all elements should pass three times, and thus a more demanding decision difficulty at the loading stations results.

                         1366_Aspects Of Scheduling 1.png

                                     Figure: Machining Sequences for Part Types

                                        Table no.1: Machining Times for Part Types

 

 

                                     975_Aspects Of Scheduling 2.png


Related Discussions:- Aspects of scheduling

Calculate transmitted force, A machine having a mass of 100 Kg and supporte...

A machine having a mass of 100 Kg and supported on springs of total stiffness 7.84 x 105 n/m has an unbalanced rotating element which results in a disturbing force of 400 N at a sp

What is ifd in project management, Q. What is IFD in project management? ...

Q. What is IFD in project management? The P&IDs now reflect the next intermediate stage of development and incorporate any changes requested by the Customer during the IFA revi

Shear force and bending moment of simply supported beam., #questicalculatio...

#questicalculation of shear fon\rce and bending moment..

System of loads - beam, System of loads -  Beam: Build the SFD & BMD ...

System of loads -  Beam: Build the SFD & BMD for 10 m span simply supported beam subjected to a system of loads as illustrated in Figure . Figure Taking moment a

Design loading - unloading facilities in plant layout, Q. Design Loading - ...

Q. Design Loading - Unloading Facilities in plant layout? Loading and unloading areas should be separated. These facilities should be situated on the edge of the site near road

What are the limitations with rectangular combined footings, What are the l...

What are the limitations with rectangular combined footings? In this section the analysis is limited to the determination of plan dimensions of the footing. The physical dimens

V pulley design, What will be the criteria to be looked into get the pulley...

What will be the criteria to be looked into get the pulley rpm increase

Selection of metallic materials, Q. Selection of metallic materials? Th...

Q. Selection of metallic materials? This Engineering Practice has been written to assist those involved in the construction of new equipment and for the maintenance of existing

Describe the term critical insulation thickness, Q. Describe the term ‘Crit...

Q. Describe the term ‘Critical Insulation thickness'. What is its significance? Derive an expression for the critical insulation radius of a spherical system. A bar of square cr

What is hydraulic press, (i) Hydraulic press:   This can be used...

(i) Hydraulic press:   This can be used to lift a heavy load placed on the platform of larger piston or to press the things placed among the piston and the heavy platfor

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd