Aspects of scheduling , Mechanical Engineering

Assignment Help:

Aspects Of Scheduling 

The difficulty is a modification of a flexible manufacturing cell at ABB's plant for the manufacturing of turbocharger in Baden, Switzerland. The difficulty is a little modified to make it  more demanding via eliminating one lading station (or else the average use of the loading stations is below 40 percent for full use of all machines) and via changing the part mix to acquire an extra uniform distribution of the load in the system. Two various cases are considered. In the initial condition, the original loading times and continuous order release throughout the shifts are supposed. This concludes in moderate average queue lengths. In the second condition, the loading times are raised, various load levels for machines are generated, and the orders are released merely at the starting of each shift. These results in a considerably more tough decision problem at the loading station where currently long queues exists and the that termed as shading effect occurs.

The layout of the flexible manufacturing system is depicted in following figure. Within the underlying industrial system, there are five machines and two of them identical and two loading stations, a deburring station, and a washing station. Now, this is supposed that only one loading station is obtainable, or else utilization of the loading stations is restricted to only 40 percent. All parts have to be loaded initially after that one or two machining operations obey, and after that deburring, reloading, washing, another one or two machining operations, deburring, unloading and washing.

                         1141_Aspects Of Scheduling.png

                                            Figure: Layout of FMS

There are 11 elements types. The greatest number of operations per element type is 11, the smallest is nine. Flow diagram of all 11 elements types are represented in following figure. The operation times for machining operations are specified in Table no.1. Operation times at the stations WASH, LOAD, DEBUR are equal for all the parts. During case 1, the operation times are as:

 

Initial loading

 

8 min

 

Unload/reload

 

13 min

 

Final unloading

 

5 min

 

Deburring (each time)

 

8 min

 

Washing (each time)

 

6 min

During case 2, all the operation times on the loading stations are raised via five minutes; the other operation times keep not changed. This generates a bottleneck on the loading station through that all elements should pass three times, and thus a more demanding decision difficulty at the loading stations results.

                         1366_Aspects Of Scheduling 1.png

                                     Figure: Machining Sequences for Part Types

                                        Table no.1: Machining Times for Part Types

 

 

                                     975_Aspects Of Scheduling 2.png


Related Discussions:- Aspects of scheduling

Calculate the critical crack length, Calculate the critical crack length: ...

Calculate the critical crack length: A wide plate of mild steel is subjected to uniform tensile load causing a stress of 100 MPa. Calculate the critical crack length in the ce

Form tool, detals of type of form tool?

detals of type of form tool?

Determine the shear stresses, A composite shaft consists of copper rod of 3...

A composite shaft consists of copper rod of 30mm diameter enclosed in a steel tube of external diameter 50mm and 10 mm thick. The shaft is needed to transmit a shaft is required to

Pneumatic circuit design, 3. Design and draw a circuit using the cascade sy...

3. Design and draw a circuit using the cascade system to operate two cylinders (A and B) which, on the operation of a start valve, produces the sequence A – B + B – A+. The cylinde

Stroke and clearance volume - thermodynamics, Stroke and Clearance Volume: ...

Stroke and Clearance Volume: Stroke The distance traveled by piston from the topmost positions of it (also called Top dead centre TDC ), to its bottom most position (or

Coil circulation pump, Q. Coil Circulation Pump? Type of pump, vertical...

Q. Coil Circulation Pump? Type of pump, vertical in line. Locate on supply side of coil. Valving indicated, isolation valves on suction and discharge, check valves on bypass. P

Flange facing and surface finish, Q. Flange Facing and Surface Finish? ...

Q. Flange Facing and Surface Finish? Raised face flange facings are preferred. Flat face flanges to be used only when mating with like equipment (fabricated from brittle mat

What is full-scale loading for load cell, A load cell based on a simply-sup...

A load cell based on a simply-supported beam with rectangular cross-section is shown below. The beam is made using a tool steel alloy with E = 200 GPa, ν = 0.285. Two strain gages

Specifications - boilers, SPECIFIC A TION S:    The boilers are s...

SPECIFIC A TION S:    The boilers are specified as per following parameters : -     Steam Generation Rate : for instance 50 000 kg /hr. -     Maximum Pressure: for

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd