Aspects of scheduling , Mechanical Engineering

Assignment Help:

Aspects Of Scheduling 

The difficulty is a modification of a flexible manufacturing cell at ABB's plant for the manufacturing of turbocharger in Baden, Switzerland. The difficulty is a little modified to make it  more demanding via eliminating one lading station (or else the average use of the loading stations is below 40 percent for full use of all machines) and via changing the part mix to acquire an extra uniform distribution of the load in the system. Two various cases are considered. In the initial condition, the original loading times and continuous order release throughout the shifts are supposed. This concludes in moderate average queue lengths. In the second condition, the loading times are raised, various load levels for machines are generated, and the orders are released merely at the starting of each shift. These results in a considerably more tough decision problem at the loading station where currently long queues exists and the that termed as shading effect occurs.

The layout of the flexible manufacturing system is depicted in following figure. Within the underlying industrial system, there are five machines and two of them identical and two loading stations, a deburring station, and a washing station. Now, this is supposed that only one loading station is obtainable, or else utilization of the loading stations is restricted to only 40 percent. All parts have to be loaded initially after that one or two machining operations obey, and after that deburring, reloading, washing, another one or two machining operations, deburring, unloading and washing.

                         1141_Aspects Of Scheduling.png

                                            Figure: Layout of FMS

There are 11 elements types. The greatest number of operations per element type is 11, the smallest is nine. Flow diagram of all 11 elements types are represented in following figure. The operation times for machining operations are specified in Table no.1. Operation times at the stations WASH, LOAD, DEBUR are equal for all the parts. During case 1, the operation times are as:

 

Initial loading

 

8 min

 

Unload/reload

 

13 min

 

Final unloading

 

5 min

 

Deburring (each time)

 

8 min

 

Washing (each time)

 

6 min

During case 2, all the operation times on the loading stations are raised via five minutes; the other operation times keep not changed. This generates a bottleneck on the loading station through that all elements should pass three times, and thus a more demanding decision difficulty at the loading stations results.

                         1366_Aspects Of Scheduling 1.png

                                     Figure: Machining Sequences for Part Types

                                        Table no.1: Machining Times for Part Types

 

 

                                     975_Aspects Of Scheduling 2.png


Related Discussions:- Aspects of scheduling

Materials weldability, MATERIALS WELDABILITY Electron beam welding has ...

MATERIALS WELDABILITY Electron beam welding has the ability to weld a variety of materials including dissimilar combinations. These can be split into general categories as to t

Yield stress and ultimate stress yield stress, Y ield stress and ultimate ...

Y ield stress and ultimate stress Yield stress: Yield stress can be defined as lowest stress at which extension of test piece increases without increase in the load. It is

How pipe flanges are electrically insulated, Pipe flanges are protected fro...

Pipe flanges are protected from corrosion by means of electrolysis, with dielectric flanges. The piping system is electrically insulated by what is known as a sacrificial anode. A

Calculate value of cutting speed, a) A carbide tool with mild steel work pi...

a) A carbide tool with mild steel work piece was found to give life of 2hours while cutting at 50 mpm. Calculate the tool life if the same tool is used at a speed 25% higher than p

Manufacturing processes of a hunting scope, I am trying to find out how a h...

I am trying to find out how a hunting scope is manufactured with proper steps and what machines are used to make a scope?

Determine the tension in string, A String LM long is tied to the ends of a ...

A String LM long is tied to the ends of a uniform rod that weight 60 N and is 1.6m long. The string passes over a nail so that the rod hangs horizontally. Determine the tension in

Carnot cycle, matlab programme for carnot cycle

matlab programme for carnot cycle

Determine standard for the specific standard technical areas, Standard for ...

Standard for the specific standard technical areas These norms are based on previously described models. Typical categories of these norms are: (a)  drafting, which describe

Milling, milling machine time calcutation

milling machine time calcutation

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd