Aspects of scheduling , Mechanical Engineering

Assignment Help:

Aspects Of Scheduling 

The difficulty is a modification of a flexible manufacturing cell at ABB's plant for the manufacturing of turbocharger in Baden, Switzerland. The difficulty is a little modified to make it  more demanding via eliminating one lading station (or else the average use of the loading stations is below 40 percent for full use of all machines) and via changing the part mix to acquire an extra uniform distribution of the load in the system. Two various cases are considered. In the initial condition, the original loading times and continuous order release throughout the shifts are supposed. This concludes in moderate average queue lengths. In the second condition, the loading times are raised, various load levels for machines are generated, and the orders are released merely at the starting of each shift. These results in a considerably more tough decision problem at the loading station where currently long queues exists and the that termed as shading effect occurs.

The layout of the flexible manufacturing system is depicted in following figure. Within the underlying industrial system, there are five machines and two of them identical and two loading stations, a deburring station, and a washing station. Now, this is supposed that only one loading station is obtainable, or else utilization of the loading stations is restricted to only 40 percent. All parts have to be loaded initially after that one or two machining operations obey, and after that deburring, reloading, washing, another one or two machining operations, deburring, unloading and washing.

                         1141_Aspects Of Scheduling.png

                                            Figure: Layout of FMS

There are 11 elements types. The greatest number of operations per element type is 11, the smallest is nine. Flow diagram of all 11 elements types are represented in following figure. The operation times for machining operations are specified in Table no.1. Operation times at the stations WASH, LOAD, DEBUR are equal for all the parts. During case 1, the operation times are as:

 

Initial loading

 

8 min

 

Unload/reload

 

13 min

 

Final unloading

 

5 min

 

Deburring (each time)

 

8 min

 

Washing (each time)

 

6 min

During case 2, all the operation times on the loading stations are raised via five minutes; the other operation times keep not changed. This generates a bottleneck on the loading station through that all elements should pass three times, and thus a more demanding decision difficulty at the loading stations results.

                         1366_Aspects Of Scheduling 1.png

                                     Figure: Machining Sequences for Part Types

                                        Table no.1: Machining Times for Part Types

 

 

                                     975_Aspects Of Scheduling 2.png


Related Discussions:- Aspects of scheduling

Why we use nickel alloys in welding, Q. Why we use Nickel Alloys in welding...

Q. Why we use Nickel Alloys in welding? Nickel weld metals have high creep-rupture strength but often have lower stress-rupture ductility and lower mechanical and thermal fatig

Hardness of water, hardness of bore well water is less than sea water .ju...

hardness of bore well water is less than sea water .justify

What is heat treatment and why is it done, What is heat treatment and why i...

What is heat treatment and why is it done? Heat treatment can be described as a combination of operations or processes in which cooling and heating of an alloy or metal is done

What are the limitations of reversed carnot cycle, (a) What are the limitat...

(a) What are the limitations of Reversed Carnot Cycle to be used in practice for refrigeration purposes? Also derive the mathematical expression of COP for reversed carnot cycle.

Determine the initial radius of curvature, Determine the initial radius of ...

Determine the initial radius of curvature:  A carriage spring, defiantly loaded and simply supported at its ends, has 12 steel plates each 60 mm wide by 6 mm thick. If the lon

Design pumps for plant layout, Q. Design Pumps for plant layout? Pumps ...

Q. Design Pumps for plant layout? Pumps handling flammable or combustible materials are relatively frequent sources of leakage and should therefore be located as far as practic

Second gear position- shifting of gear, Second Gear Position: When ge...

Second Gear Position: When gear M2 on the main shaft is in mesh with gear C2 on the countershaft then this is known as second gear position. To rotate free gear M2 with the m

Determine the isentropic flow through the nozzle, Determine the isentropic ...

Determine the isentropic flow through the nozzle: In an isentropic flow through the nozzle, air flows at rate of 600Kg/hr. At inlet to the nozzle, the pressure is 2Mpa and te

Alloy steels, Alloy Steels: Carbon steels in their commercial forms al...

Alloy Steels: Carbon steels in their commercial forms all times comprise specific amounts of other elements. A lot of of these elements enter the steel from the ores and it is

What is pre-fabricated buildings, Q. What is Pre-fabricated buildings? ...

Q. What is Pre-fabricated buildings? Buildings: Pre-fabricated buildings shall be as per specification GS-904-0520 and, when provided, conceptual drawings prepared by Engine

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd