answers Please, Other Management

Assignment Help:
Question 1 of 16 4.0 Points

Six (6) samples of size five (5) were used to collect the data presented below:
sample number

1

2

3

4

5

6
sample mean (x-bar)

8.0

8.1

7.9

8.2

7.8

8.0
sample range (R)

1.8

2.4

1.9

1.8

2.1

2.0

The lower control limit (LCL) an x-bar-chart is.
A. LCL = 7.800
B. LCL = 7.034
C. LCL = 6.846
D. LCL = 21.000
E. LCL = 0.000
Reset Selection

Question 2 of 16 4.0 Points

Twenty samples of size six (6) were collected for a variable measurement. Determine the upper control limit (UCL) and lower control limit (LCL) for an R-chart if the average range, Rbar, is 4.4.
A. LCL = 0.3344, UCL = 9.3016
B. LCL = 0.0000, UCL = 1.4696
C. LCL = 1.826, UCL = 6.974
D. LCL = 0.0000, UCL = 8.8176
E. LCL = 0.0000, UCL = 176.3520
Reset Selection

Question 3 of 16 4.0 Points
Twenty-five samples of size thirty (30) were collected and a total of 48 nonconforming items were found yielding p-bar = 0.064. The three sigma upper control limit (UCL) for a p control chart would be
A. 0.833
B. 0.211
C. 0.198
D. 0.091
E. None of the above
Reset Selection

Question 4 of 16 2.0 Points

A company has calculated its CFE to be 700 and its MADt is 20. Which one of the following is the resulting TS?
A. About 0.05
B. About 20
C. About 35
D. More than 35
E. Cannot be calculated based on this information
Reset Selection

Question 5 of 16 2.0 Points
If you were trying to select a forecasting model based on a MAD statistic, which of the following MAD values reflects the most accurate model?
A. 0.425
B. 0.877
C. 2.000
D. 4.599
E. 100
Reset Selection

Question 6 of 16 3.0 Points

Given the following weekly demand and forecast figures:
Week

Demand

Forecast
1

20

40
2

25

20
3

35

30

The MAD is:
A. 0
B. -10
C. 30
D. 10
E. none of the above
Reset Selection

Question 7 of 16 3.0 Points


Given the following weekly demand and forecast figures:

Week

Demand

Forecast
1

20

40
2

25

20
3

35

30

The mean square error is:
A. -10
B. 15
C. 30
D. 150
E. 450
Reset Selection

Question 8 of 16 3.0 Points


A company wants to forecast its demand using the Simple Moving Average and has the following demand data.

Week

Demand
1

120
2

100
3

140
4

120
5

200


Which of the following is the four-period moving average forecast for period 6?


A. 120
B. 136
C. 140
D. 170
E. none of the above
Reset Selection

Question 9 of 16 3.0 Points
A company wants to forecast its demand using the Weighted Moving Average. The company uses two prior yearly sales values (i.e., Year 1 = 110 and Year 2 = 130). Using weights 0.9 and 0.1 with largest weight to demand assigned to the most recent period, which of the following is the two-period Weighted Moving Average forecast for Year 3?
A. 112
B. 117
C. 120
D. 128
E. none of the above.
Reset Selection

Question 10 of 16 3.0 Points
In Period 7 the exponentially smoothed forecast was 50 and the actual demand was 60. If alpha = 0.1, what is the exponentially smoothed forecast for Period 8?
A. 49
B. 50
C. 51
D. 59
E. 61
Reset Selection

Question 11 of 16 3.0 Points

Monthly demand for a product has been as follows in the last 2 months.
July

60 units
August

62 units

What is the forecast for September using exponential smoothing with alpha = 0.2 if the forecast for July was 50 units?
A. 54
B. 53
C. 52
D. 51
E. 50
Reset Selection

Question 12 of 16 4.0 Points

The following table gives the demand and production plan for an organization.

January February March
Demand 900 900 1,500
Production plan 1,100 1,100 1,100

The initial inventory is zero. The inventory holding cost is $1 per unit per month. The total inventory holding cost for the plan is:
A. $400
B. $600
C. $800
D. $1,200
E. None of the above
Reset Selection

Question 13 of 16 3.0 Points

Use the following data to answer questions 13-16

A Company policy calls for keeping safety-stock equal to 25% the forecasted demand for that month. The company currently has a work force of 12 people.

Demand Data
Jan. Feb. March
Beg. Inventory 200
Forecast demand 500 300 600



Production Data
Labor hours/unit 3
Workdays/month 20
Work hours/day 8


Cost Data
Labor cost/hour-straight time $14
Labor cost/hour-overtime $21

The production requirement for the month of February is
A. 300
B. 100
C. 225
D. 250
E. none of the above
Reset Selection

Question 14 of 16 3.0 Points

Use the following data to answer questions 13-16

A Company policy calls for keeping safety-stock equal to 25% the forecasted demand for that month. The company currently has a work force of 12 people.

Demand Data
Jan. Feb. March
Beg. Inventory 200
Forecast demand 500 300 600



Production Data
Labor hours/unit 3
Workdays/month 20
Work hours/day 8


Cost Data
Labor cost/hour-straight time $14
Labor cost/hour-overtime $21

The beginning inventory for the month of March is
A. 60
B. 75
C. 100
D. 150
E. none of the above
Reset Selection

Question 15 of 16 3.0 Points

Use the following data to answer questions 13-16

A Company policy calls for keeping safety-stock equal to 25% the forecasted demand for that month. The company currently has a work force of 12 people.

Demand Data
Jan. Feb. March
Beg. Inventory 200
Forecast demand 500 300 600



Production Data
Labor hours/unit 3
Workdays/month 20
Work hours/day 8


Cost Data
Labor cost/hour-straight time $14
Labor cost/hour-overtime $21

The number of units current work force of 12 workers can produce in a month during regular time is
A. 960
B. 800
C. 640
D. 600
E. none of the above
Reset Selection

Question 16 of 16 3.0 Points

Use the following data to answer questions 13-16

A Company policy calls for keeping safety-stock equal to 25% the forecasted demand for that month. The company currently has a work force of 12 people.

Demand Data
Jan. Feb. March
Beg. Inventory 200
Forecast demand 500 300 600



Production Data
Labor hours/unit 3
Workdays/month 20
Work hours/day 8


Cost Data
Labor cost/hour-straight time $14
Labor cost/hour-overtime $21

The number of workers needed to produce 960 units in a month is
A. 18
B. 16
C. 15
D. 12
E. none of the above
Reset Selection









Related Discussions:- answers Please

Information generation process, INFORMATION GENERATION PROCESS: Inform...

INFORMATION GENERATION PROCESS: Information is the product of different human activities and events. Activities are undertaken by individuals or by organisations in pursuance

Factors driving contracting , Factors Driving Contracting  In this sect...

Factors Driving Contracting  In this section let us try to analyse the factors which drive contracting decisions. Here, the buy mode is referred as contracting, subcontracting

Basic materials handling principles, Basic  Materials Handling Principles ...

Basic  Materials Handling Principles 1.  Lest Handling  is Best Handling: it is  best to keep  the handling  cost of the  minimum  because  handling  does not add value  to

Importance of the different stages in the process, QUESTION 1 (a) Descr...

QUESTION 1 (a) Describe the various stages of a strategic management process .and explain the importance of the different stages in the process (b) Can unexplained strategie

Need for project quality standards, N eed for project quality standards ...

N eed for project quality standards Project quality standard help the organisation in defining specific measurable objectives. The objective tells if the goals are being met a

Library equipment in physical planning of library , LIBRARY EQUIPMENT IN PH...

LIBRARY EQUIPMENT IN PHYSICAL PLANNING OF LIBRARY IN LIBRARY MANAGEMENT Most of the equipment used in the library is standard office equipment, sometimes adapted library use.

Explain critical ethical issues facing knowledge management, QUESTION (...

QUESTION (a) What are some of the major types of Knowledge Management roles that exist in organizations today? (b) What types of competencies should be present in a good Kno

Advanced Linear programming questions, where can i get Advanced Linear Prog...

where can i get Advanced Linear Programming questions from ??

Preparation of standard bidding document, Question: (a) Selection of C...

Question: (a) Selection of Consultant; (i) Give the reasons why an Expression of Interest may be required as a first step in the Procurement of Consultancy services. (ii

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd