ABC Company manufactures both interior and exterior paints from 2 raw materials M1 and M2. The following table gives basic data of problem.

 

 

Exterior paint

Interior paint

Availability

N1

6

4

24

N2

1

2

6

Profit per ton

5

4

 

A market survey signifies that every day demand for interior paint cannot surpass that for exterior paint by more than 1 ton. Also maximum routine demand for interior paint is 2 tons. Develop LPP to find out the top product mix of interior and exterior paints that maximizes the daily total gain (profit).

Answer

Assume

 x1 - number of units of exterior paint

      x2 - number of units of interior paint

 

Maximize Z = 5x1 + 4x2         

Subject to

6x1 + 4x2 ≤ 24

x1 + 2x2 ≤ 6

x2 - x1≤ 1

x2≤ 2

                 x1≥0, x2 ≥0

 

b) The highest routine demand for exterior paint is almost 2.5 tons

                 x1≤ 2.5

c) Routine demand for interior paint is as a minimum 2 tons

                 x2 ≥ 2

d) Routine demand for interior paint is accurately 1 ton more than that for exterior paint.

                 x2 > x1 + 1

 

 

 


Related Discussions:- Answering lp problems

Operation research techniques, High Costs are Involved in the Use of O. R...

High Costs are Involved in the Use of O. R Techniques: O. R techniques usually prove very expensive. Services of specialized persons are invariably called for ( and along w

Assignment answer, Q2.Six Operators are to be assigned to five jobs with th...

Q2.Six Operators are to be assigned to five jobs with the cost of assignment in Rs. given in the matrix below. Determine the optimal assignment. Which operator will have no assignm

First paper, discuss the seauencing decision problem for n jobs on two and ...

discuss the seauencing decision problem for n jobs on two and three machines

Vogel''s approximation method, I''m getting a negative value in the one of ...

I''m getting a negative value in the one of the Supply/Stock columns while solving a problem in Vogel''s approximation method. Is it possible or am I doing anything wrong?

Assignment, discuss about assignment and steps involved in it

discuss about assignment and steps involved in it

Queuing theory, A certain type of machine breaks down at an average rate of...

A certain type of machine breaks down at an average rate of 5/hour. the break down is in accordance with Poisson process.cost of idle machine hour is $15/hour. 2 repairmen Peter an

Linear programming problem, #Solve the following Linear Programming Problem...

#Solve the following Linear Programming Problem using Simplex method. Maximize Z= 3x1 + 2X2 Subject to the constraints: X1+ X2 = 4 X1 - X2 = 2 X1, X2 = 0

Assignment, A paper mill produces two grades of paper viz., X and Y. Becaus...

A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y paper i

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd