ABC Company manufactures both interior and exterior paints from 2 raw materials M1 and M2. The following table gives basic data of problem.

 

 

Exterior paint

Interior paint

Availability

N1

6

4

24

N2

1

2

6

Profit per ton

5

4

 

A market survey signifies that every day demand for interior paint cannot surpass that for exterior paint by more than 1 ton. Also maximum routine demand for interior paint is 2 tons. Develop LPP to find out the top product mix of interior and exterior paints that maximizes the daily total gain (profit).

Answer

Assume

 x1 - number of units of exterior paint

      x2 - number of units of interior paint

 

Maximize Z = 5x1 + 4x2         

Subject to

6x1 + 4x2 ≤ 24

x1 + 2x2 ≤ 6

x2 - x1≤ 1

x2≤ 2

                 x1≥0, x2 ≥0

 

b) The highest routine demand for exterior paint is almost 2.5 tons

                 x1≤ 2.5

c) Routine demand for interior paint is as a minimum 2 tons

                 x2 ≥ 2

d) Routine demand for interior paint is accurately 1 ton more than that for exterior paint.

                 x2 > x1 + 1

 

 

 


Related Discussions:- Answering lp problems

Simulation models - operation research model, These models are used to dev...

These models are used to develop a method to evaluate the merit of alternative courses or action by representing with a mathematical model of the problems where various variab

Solve the following Linear Programming Problem using Simple , Solve the fol...

Solve the following Linear Programming Problem using Simple method. Maximize Z= 3x1 + 2X2 Subject to the constraints: X1+ X2 = 4 X1 - X2 = 2

Use of t -tables - hypothesis testing , Use of t -tables            ...

Use of t -tables            Similar  to normal  curve  tables  there  exist t- distribution  tables. However  whereas the properties of  the normal  curve are constant for all

Problems based on lpp when feasible region is a line segment, Problems base...

Problems based on LPP when feasible region is a line segment or it does not exist. 1.    Maximize z = 2x+3y subject to the constraints X + y ≤ 1 X + y ≥ 3 X,  y ≥ 0

Lpp, Determine feasible space for x1-x2= 8

Determine feasible space for x1-x2= 8

LP - Assignment problem, I have looked at Hungarian algorithm to solve assi...

I have looked at Hungarian algorithm to solve assignment problem, but it seems like it is limited to 1-to-1 assignment. I would like to know how to do 1-to-3 assignment.

Advantages of operations research, Operation Research may be regarded as a...

Operation Research may be regarded as a tool which is utilized to increase the effectiveness of the management decisions. O R is objective supplement to the subjective feeling

Linear programming problem, A paper mill produces two grades of paper viz....

A paper mill produces two grades of paper viz., X and Y. Because of raw each) material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of g

Determine phases-states-decisions and probability , G. Ambler has € 10000 ...

G. Ambler has € 10000 available for a second hand car, but would like to buy a fast car that costs € 25000. He needs the money for that car quickly, and would like to increase his

Nass food produce tow kinds of popular dark chocolate bars, Nass food prod...

Nass food produce tow kinds of popular dark chocolate bars

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd