ABC Company manufactures both interior and exterior paints from 2 raw materials M1 and M2. The following table gives basic data of problem.
Exterior paint
Interior paint
Availability
N1
6
4
24
N2
1
2
Profit per ton
5
A market survey signifies that every day demand for interior paint cannot surpass that for exterior paint by more than 1 ton. Also maximum routine demand for interior paint is 2 tons. Develop LPP to find out the top product mix of interior and exterior paints that maximizes the daily total gain (profit).
Answer
Assume
x1 - number of units of exterior paint
x2 - number of units of interior paint
Maximize Z = 5x1 + 4x2
Subject to
6x1 + 4x2 ≤ 24
x1 + 2x2 ≤ 6
x2 - x1≤ 1
x2≤ 2
x1≥0, x2 ≥0
b) The highest routine demand for exterior paint is almost 2.5 tons
x1≤ 2.5
c) Routine demand for interior paint is as a minimum 2 tons
x2 ≥ 2
d) Routine demand for interior paint is accurately 1 ton more than that for exterior paint.
x2 > x1 + 1
Institutional Characteristics: An approach to an understanding of the fields of interest of individuals to be served and of the organisation as a whole could begin by acquiri
This is determined by disposable personal income( personal income minus direct taxes and other deductions ). Some people suggest the use of discretionary income in place of
Analysis of Available Information and Verification of Hypothesis: most of the time that a scientist spends in training is devoted to learning how to analyze and int
how to use simples method
A constraints in an LPP restricts? (Value of objective function,Value of decision variable,Use of available resources, uncertainty of optimum value) please help me to find out righ
maximize z=3x1+2*2 subject to the constraints x1+x2=4 x1-x2=2 x1.x2=0
These models are used to develop a method to evaluate the merit of alternative courses or action by representing with a mathematical model of the problems where various variab
Davidson construction company is building a luxury lakefront home in batangas coordination of the architech an sub contractors will require a major effort to meet the 44-week (appr
how do you use gantt chart for solving sequencing problem ? why is it not employed for solving larger problems?
use of game theory by state bank of india
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd