ABC Company manufactures both interior and exterior paints from 2 raw materials M1 and M2. The following table gives basic data of problem.

 

 

Exterior paint

Interior paint

Availability

N1

6

4

24

N2

1

2

6

Profit per ton

5

4

 

A market survey signifies that every day demand for interior paint cannot surpass that for exterior paint by more than 1 ton. Also maximum routine demand for interior paint is 2 tons. Develop LPP to find out the top product mix of interior and exterior paints that maximizes the daily total gain (profit).

Answer

Assume

 x1 - number of units of exterior paint

      x2 - number of units of interior paint

 

Maximize Z = 5x1 + 4x2         

Subject to

6x1 + 4x2 ≤ 24

x1 + 2x2 ≤ 6

x2 - x1≤ 1

x2≤ 2

                 x1≥0, x2 ≥0

 

b) The highest routine demand for exterior paint is almost 2.5 tons

                 x1≤ 2.5

c) Routine demand for interior paint is as a minimum 2 tons

                 x2 ≥ 2

d) Routine demand for interior paint is accurately 1 ton more than that for exterior paint.

                 x2 > x1 + 1

 

 

 


Related Discussions:- Answering lp problems

Vogel''s approximation method, I''m getting a negative value in the one of ...

I''m getting a negative value in the one of the Supply/Stock columns while solving a problem in Vogel''s approximation method. Is it possible or am I doing anything wrong?

Assignment problem, a c++ program to implement assignment problem??????????...

a c++ program to implement assignment problem???????????

Linear programning, b. A paper mill produces two grades of paper viz., X an...

b. A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y pape

Linear programing, Solve the following Linear Programming Problem using Sim...

Solve the following Linear Programming Problem using Simple method. Maximize Z= 3x1 + 2X2

Waiting queques, During busy times, 60 potential customers per hour arrive ...

During busy times, 60 potential customers per hour arrive at the booth (assume a Poisson distribution). A booth worker takes 5 minutes, on average, to meet the information needs of

Multi stage sampling - sampling decisions, Normal 0 false fal...

Normal 0 false false false EN-IN X-NONE X-NONE MicrosoftInternetExplorer4

Effect of professional development on class management, Purpose: The pu...

Purpose: The purpose of this study is to explore the effect of professional development on teachers' Lesson Planning, Class Management, Teaching Methods, Cooperation and Teac

Fromulation of LPP, A paper mill produces two grades of paper viz., X and ...

A paper mill produces two grades of paper viz., X and Y because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons ot grade Y paper in

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd