ABC Company manufactures both interior and exterior paints from 2 raw materials M1 and M2. The following table gives basic data of problem.
Exterior paint
Interior paint
Availability
N1
6
4
24
N2
1
2
Profit per ton
5
A market survey signifies that every day demand for interior paint cannot surpass that for exterior paint by more than 1 ton. Also maximum routine demand for interior paint is 2 tons. Develop LPP to find out the top product mix of interior and exterior paints that maximizes the daily total gain (profit).
Answer
Assume
x1 - number of units of exterior paint
x2 - number of units of interior paint
Maximize Z = 5x1 + 4x2
Subject to
6x1 + 4x2 ≤ 24
x1 + 2x2 ≤ 6
x2 - x1≤ 1
x2≤ 2
x1≥0, x2 ≥0
b) The highest routine demand for exterior paint is almost 2.5 tons
x1≤ 2.5
c) Routine demand for interior paint is as a minimum 2 tons
x2 ≥ 2
d) Routine demand for interior paint is accurately 1 ton more than that for exterior paint.
x2 > x1 + 1
. A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y paper
Sample Size in Non Propbability The probability selection does not apply to purposive selection. The size of the non probability samples is selected in a subjective ma
A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y paper i
MEAN DEVIATION Mean deviation of a series is the arithmetic average of the deviations of various items from the median or mean of that series. Median is preferred
#question.Solve the following Linear Programming Problem using Simple method. Maximize Z= 3x1 + 2X2 Subject to the constraints: X1+ X2 = 4 X1 - X2 = 2 X1, X2 = 0.
assignment problem through c programming
if one no. is repeated 2-3 times in machine-1 and machine-2 what is to be prefer first
Select one of the topics listed 1-6 below and outline a programme of quantitative research for its investigation. The assignment should cover issues of sample design, instrumen
whatdo you mean by automation
advantage of quality circle process
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd