ABC Company manufactures both interior and exterior paints from 2 raw materials M1 and M2. The following table gives basic data of problem.
Exterior paint
Interior paint
Availability
N1
6
4
24
N2
1
2
Profit per ton
5
A market survey signifies that every day demand for interior paint cannot surpass that for exterior paint by more than 1 ton. Also maximum routine demand for interior paint is 2 tons. Develop LPP to find out the top product mix of interior and exterior paints that maximizes the daily total gain (profit).
Answer
Assume
x1 - number of units of exterior paint
x2 - number of units of interior paint
Maximize Z = 5x1 + 4x2
Subject to
6x1 + 4x2 ≤ 24
x1 + 2x2 ≤ 6
x2 - x1≤ 1
x2≤ 2
x1≥0, x2 ≥0
b) The highest routine demand for exterior paint is almost 2.5 tons
x1≤ 2.5
c) Routine demand for interior paint is as a minimum 2 tons
x2 ≥ 2
d) Routine demand for interior paint is accurately 1 ton more than that for exterior paint.
x2 > x1 + 1
Pamphlets - classification of documents: A pamphlet is an independent publication. It is normally a document of a few printed pages, usually less than 49. Pamphlets cover an e
This methods studies development from simpler forms through a long series of a small change. Each change by itself results in minor modification in the phenomenon but the
Two Handed process Chart of Signing a Latter A multiple activity chart records the related sequence of activities of more than one subject, men and / or machine o
Bibliography Format a. Introduction : Bibliographies tell readers where they can locate information about a topic. It is a list of sources of information for a repo
Paper Mill Produces Two Grades Of Paper Viz x And y Because Of Raw Material Restrictions It Cannot Produce More Than 400 Tons Of Grade x Paper And 300 Tons Of Grade y Paper In a We
A certain type of machine breaks down at an average rate of 5/hour. the break down is in accordance with Poisson process.cost of idle machine hour is $15/hour. 2 repairmen Peter an
I have looked at Hungarian algorithm to solve assignment problem, but it seems like it is limited to 1-to-1 assignment. I would like to know how to do 1-to-3 assignment.
These models have been developed to establish a trade off between costs of providing and the waiting time of a customer in the queuing system. Constructing a model entails desc
Assumption of F- Test The theoretical assumption on which F test is based are: 1.The populations for each sample must be normally distributed with identical mean
cumulative discount factor
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd