ABC Company manufactures both interior and exterior paints from 2 raw materials M1 and M2. The following table gives basic data of problem.
Exterior paint
Interior paint
Availability
N1
6
4
24
N2
1
2
Profit per ton
5
A market survey signifies that every day demand for interior paint cannot surpass that for exterior paint by more than 1 ton. Also maximum routine demand for interior paint is 2 tons. Develop LPP to find out the top product mix of interior and exterior paints that maximizes the daily total gain (profit).
Answer
Assume
x1 - number of units of exterior paint
x2 - number of units of interior paint
Maximize Z = 5x1 + 4x2
Subject to
6x1 + 4x2 ≤ 24
x1 + 2x2 ≤ 6
x2 - x1≤ 1
x2≤ 2
x1≥0, x2 ≥0
b) The highest routine demand for exterior paint is almost 2.5 tons
x1≤ 2.5
c) Routine demand for interior paint is as a minimum 2 tons
x2 ≥ 2
d) Routine demand for interior paint is accurately 1 ton more than that for exterior paint.
x2 > x1 + 1
models in operation research
A producer of furniture manufactures two products - tables and chairs. Processing of these products is done on two machines A and B. A chair needs 2 hours on machine A and 6 hours
what is the job scope in or?
Rehearse Making presentation is not simple. It is extremely important for us to realize the sanctity of rehearsing to improve the quality of the presentation. Unless
A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y paper i
The 2 nd phase of operations Research is to construct a mathematical model representing the system under study. It requires the identification of both static and dynam
Inventory models deal with the problem of determination of how much to order at a point in time and when to place an order. The main objective is to minimize the sum of three
Ask queA manufacturing firm has discontinued production of a certain unprofitable product line. This created considerable excess production capacity. Management is considering to d
Question: (a) Discuss briefly the four basic components of any queueing system. (b) Explain what you understand by the following models: (i) (M| M | 1 : N | FCFS) (ii
management wants to know how many supervisors should be hired, and what could be the optimum workload distribution to be applied, given a number of constraints
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd