ABC Company manufactures both interior and exterior paints from 2 raw materials M1 and M2. The following table gives basic data of problem.

 

 

Exterior paint

Interior paint

Availability

N1

6

4

24

N2

1

2

6

Profit per ton

5

4

 

A market survey signifies that every day demand for interior paint cannot surpass that for exterior paint by more than 1 ton. Also maximum routine demand for interior paint is 2 tons. Develop LPP to find out the top product mix of interior and exterior paints that maximizes the daily total gain (profit).

Answer

Assume

 x1 - number of units of exterior paint

      x2 - number of units of interior paint

 

Maximize Z = 5x1 + 4x2         

Subject to

6x1 + 4x2 ≤ 24

x1 + 2x2 ≤ 6

x2 - x1≤ 1

x2≤ 2

                 x1≥0, x2 ≥0

 

b) The highest routine demand for exterior paint is almost 2.5 tons

                 x1≤ 2.5

c) Routine demand for interior paint is as a minimum 2 tons

                 x2 ≥ 2

d) Routine demand for interior paint is accurately 1 ton more than that for exterior paint.

                 x2 > x1 + 1

 

 

 


Related Discussions:- Answering lp problems

Goal programming, Goal Programming This provides a more realistic model...

Goal Programming This provides a more realistic model. In a modern setting, profit maximization may not be the only objective of a business concern. Other objectives or goals c

Linear programming problem, Solve the following Linear Programming Problem ...

Solve the following Linear Programming Problem using Simple method. Maximize Z= 3x1 + 2X2 Subject to the constraints: X1+ X2 = 4 X1 - X2 = 2 X1, X2 = 0

Linear pograming, application area of linear programing problem

application area of linear programing problem

Research paper, Research Paper Overview Research Topic: •    Research ...

Research Paper Overview Research Topic: •    Research the effects of federal mandates in your state.  Examples include the Americans with Disabilities Act, the No Child Left B

Jaguar, how jaguar implements aggregate planning?

how jaguar implements aggregate planning?

First paper, discuss the seauencing decision problem for n jobs on two and ...

discuss the seauencing decision problem for n jobs on two and three machines

ANSWER OF PROBLEM RELATING TO PERT AND CPM., ANSWER OF ACTIVITY WITH THEIR ...

ANSWER OF ACTIVITY WITH THEIR PRECEDING ACTIVITY AND DURATION OF TIME IN WEEKS?

LPP, A paper mill produces two grades of paper viz. X and Y. Because of raw...

A paper mill produces two grades of paper viz. X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y paper in

Lp model, A company produce three sizes of windows fans small,medium and la...

A company produce three sizes of windows fans small,medium and large. The manager has formulated an LP model for production.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd