Answering lp problems, Operation Research

Assignment Help:

ABC Company manufactures both interior and exterior paints from 2 raw materials M1 and M2. The following table gives basic data of problem.

 

 

Exterior paint

Interior paint

Availability

N1

6

4

24

N2

1

2

6

Profit per ton

5

4

 

A market survey signifies that every day demand for interior paint cannot surpass that for exterior paint by more than 1 ton. Also maximum routine demand for interior paint is 2 tons. Develop LPP to find out the top product mix of interior and exterior paints that maximizes the daily total gain (profit).

Answer

Assume

 x1 - number of units of exterior paint

      x2 - number of units of interior paint

 

Maximize Z = 5x1 + 4x2         

Subject to

6x1 + 4x2 ≤ 24

x1 + 2x2 ≤ 6

x2 - x1≤ 1

x2≤ 2

                 x1≥0, x2 ≥0

 

b) The highest routine demand for exterior paint is almost 2.5 tons

                 x1≤ 2.5

c) Routine demand for interior paint is as a minimum 2 tons

                 x2 ≥ 2

d) Routine demand for interior paint is accurately 1 ton more than that for exterior paint.

                 x2 > x1 + 1

 

 

 


Related Discussions:- Answering lp problems

LPP, A paper mill produces two grades of paper viz., X and Y. Because of ra...

A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y paper i

Categorizing operations research problems, what are the categorization of o...

what are the categorization of operations research problems?

Mba , in a rectangular game pay off matrix of player a is as follows ...

in a rectangular game pay off matrix of player a is as follows B1 B2 A1 5 7 A2 4 0 salve the game write down the pay off matrix of B and then solve the ga

Case study and statistical methods, Case Study Methods: It is studying the...

Case Study Methods: It is studying the phenomenon event situation or development through a thorough and detailed analysis or intensive study. The case may be an individual a gr

Semeter 5, explian completelly the operation reserch

explian completelly the operation reserch

Uses of standard deviation - measure of dispersion, Uses   of Standard D...

Uses   of Standard Deviation Normal 0 false false false EN-IN X-NONE X-NONE

Solve by simplex method, Solve by simplex method Maximize Z = 5...

Solve by simplex method Maximize Z = 5x 1 + 3x 2 Subject to 3x 1 + 5x 2 ≤ 15 5x 1 + 2x 2 ≤ 10 &         x 1 ≥ 0, x 2  ≥ 0 [Ans. Max Z = 235/19

Techniques of work measurement, Techniques  of Work  Measurement A n...

Techniques  of Work  Measurement A number of work  measurement  techniques  have been  developed  to suit  different  types of work . There are: 1. Repetitive work: The

Yates correction for continuity for 2x 2tables , Yates Correction for Cont...

Yates Correction for Continuity for  2x 2Tables If any cell frequency in  2x 2 table isles  than 5thenfor the application of X 2 test it  is pooled with the preceding or suc

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd