Answering lp problems, Operation Research

Assignment Help:

ABC Company manufactures both interior and exterior paints from 2 raw materials M1 and M2. The following table gives basic data of problem.

 

 

Exterior paint

Interior paint

Availability

N1

6

4

24

N2

1

2

6

Profit per ton

5

4

 

A market survey signifies that every day demand for interior paint cannot surpass that for exterior paint by more than 1 ton. Also maximum routine demand for interior paint is 2 tons. Develop LPP to find out the top product mix of interior and exterior paints that maximizes the daily total gain (profit).

Answer

Assume

 x1 - number of units of exterior paint

      x2 - number of units of interior paint

 

Maximize Z = 5x1 + 4x2         

Subject to

6x1 + 4x2 ≤ 24

x1 + 2x2 ≤ 6

x2 - x1≤ 1

x2≤ 2

                 x1≥0, x2 ≥0

 

b) The highest routine demand for exterior paint is almost 2.5 tons

                 x1≤ 2.5

c) Routine demand for interior paint is as a minimum 2 tons

                 x2 ≥ 2

d) Routine demand for interior paint is accurately 1 ton more than that for exterior paint.

                 x2 > x1 + 1

 

 

 


Related Discussions:- Answering lp problems

Determining sample size for estimating means-sample decisons, Determining S...

Determining Sample Size for estimatingMeans a. Acceptable Errors: There  may be several errors  in the  sample  size. The researcher  will have  to decide those  errors. Whic

Research methodology, Research Methodology 1. Discuss how the researc...

Research Methodology 1. Discuss how the research will be executed to achieve the proposed research objectives. The methodology should be based on the methods that are used in

Introduction to probability distribution , Introduction to Probability Dist...

Introduction to Probability Distribution By  theoretical distribution we mean  a frequency distribution  which  is obtained  in relation to a random  variable by some  mathem

Regression Analysis, regression line drawn as Y=C+1075x, when x was 2, and ...

regression line drawn as Y=C+1075x, when x was 2, and y was 239, given that y intercept was 11. calculate the residual

requirements and characteristics of a good table , Requirements and Charac...

Requirements and Characteristics of a good table In the words  of Mr. Harry Jerome a good statistical table  is a triumph of ingenuity and  technique masterpiece of economy  o

Discuss the term group decision making, a. Determine the following with res...

a. Determine the following with respect to decision making approaches: (i) Group decision making (ii) Directive, analytic, conceptual and behavioral decision making styles (8

Standard deviation - sampling decisons, Standard Deviation The  standa...

Standard Deviation The  standard deviation of samples (s) can be estimated by  the pilot  study past studies and the  ranges of distribution. A pilot study  may be  conducted

Linear programming solution by steps for two-phase method, Solve by Steps f...

Solve by Steps for Two-Phase Method Max Z = 5x 1 + 8x 2 Subject to 3x 1 + 2x 2 ≥ 3 x 1 + 4x 2 ≥ 4 x 1 + x 2 ≤ 5     &     x 1 ≥ 0, x 2  ≥ 0 Answe

Linear Programming, A paper mill produces two grades of paper viz., X and Y...

A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y paper i

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd