Answering lp problems, Operation Research

Assignment Help:

ABC Company manufactures both interior and exterior paints from 2 raw materials M1 and M2. The following table gives basic data of problem.

 

 

Exterior paint

Interior paint

Availability

N1

6

4

24

N2

1

2

6

Profit per ton

5

4

 

A market survey signifies that every day demand for interior paint cannot surpass that for exterior paint by more than 1 ton. Also maximum routine demand for interior paint is 2 tons. Develop LPP to find out the top product mix of interior and exterior paints that maximizes the daily total gain (profit).

Answer

Assume

 x1 - number of units of exterior paint

      x2 - number of units of interior paint

 

Maximize Z = 5x1 + 4x2         

Subject to

6x1 + 4x2 ≤ 24

x1 + 2x2 ≤ 6

x2 - x1≤ 1

x2≤ 2

                 x1≥0, x2 ≥0

 

b) The highest routine demand for exterior paint is almost 2.5 tons

                 x1≤ 2.5

c) Routine demand for interior paint is as a minimum 2 tons

                 x2 ≥ 2

d) Routine demand for interior paint is accurately 1 ton more than that for exterior paint.

                 x2 > x1 + 1

 

 

 


Related Discussions:- Answering lp problems

Describe the demand curve, The following equation gives Jane's linear deman...

The following equation gives Jane's linear demand curve for visits to a nearby national park.  Q is the number of visits per week and P represents the price of a pass (price per vi

Operations research as a decision-making sci, Short Define operations resea...

Short Define operations research as a decision-making science

Machine tabulation, Machine  Tabulation This methods  of tabulating i...

Machine  Tabulation This methods  of tabulating information  is generally used in  case of extensive  large scale  surveys. Mechanical sorting and tabulating equipments and su

Effect of professional development on class management, Purpose: The pu...

Purpose: The purpose of this study is to explore the effect of professional development on teachers' Lesson Planning, Class Management, Teaching Methods, Cooperation and Teac

Techniques of operations research, There is no unique set of problems which...

There is no unique set of problems which can be solved by using operations Research Models r techniques. Several operations Research Models or techniques can be grouped into some b

Liner programming problem, A constraints in an LPP restricts? (Value of obj...

A constraints in an LPP restricts? (Value of objective function,Value of decision variable,Use of available resources, uncertainty of optimum value) please help me to find out righ

Waiting queques, During busy times, 60 potential customers per hour arrive ...

During busy times, 60 potential customers per hour arrive at the booth (assume a Poisson distribution). A booth worker takes 5 minutes, on average, to meet the information needs of

Replacement theory.., a pipe lis dur for rpair,the repair would cost 10000 ...

a pipe lis dur for rpair,the repair would cost 10000 and it would last for 3 years.alternatively a new pipe line can be purchase at 30000 for 10 years.assuming 10% depriciation rat

Application of the chi square test - hypothesis testing, Application of the...

Application of the chi Square Test   The  chi square distribution  has a number of applications are given  below: a.Chi Square test of goodness of fit. b.Chi square te

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd