ABC Company manufactures both interior and exterior paints from 2 raw materials M1 and M2. The following table gives basic data of problem.
Exterior paint
Interior paint
Availability
N1
6
4
24
N2
1
2
Profit per ton
5
A market survey signifies that every day demand for interior paint cannot surpass that for exterior paint by more than 1 ton. Also maximum routine demand for interior paint is 2 tons. Develop LPP to find out the top product mix of interior and exterior paints that maximizes the daily total gain (profit).
Answer
Assume
x1 - number of units of exterior paint
x2 - number of units of interior paint
Maximize Z = 5x1 + 4x2
Subject to
6x1 + 4x2 ≤ 24
x1 + 2x2 ≤ 6
x2 - x1≤ 1
x2≤ 2
x1≥0, x2 ≥0
b) The highest routine demand for exterior paint is almost 2.5 tons
x1≤ 2.5
c) Routine demand for interior paint is as a minimum 2 tons
x2 ≥ 2
d) Routine demand for interior paint is accurately 1 ton more than that for exterior paint.
x2 > x1 + 1
role of computer software in operation research
line drawn as Y=C+1075x, when x was 2, and y was 239, given that y intercept was 11. calculate the residualon..
The demand of ice cream during the three summer months (June, July, and August) at All-Flavors Parlor is estimated at 500,600, and 400 20-gallon cartons, respectively. Two wholesal
Calculation of Standard Deviation - Continuous Series: In the continuous series the methods of calculation standard deviation is almost the same as in a discrete frequency distrib
The NW corner rule described earlier considers only the availability and supply requirements in making assignments. It takes no account of the shipping costs given in
Disadvantage of standard Deviation It is not easy to understand and calculate. It gives more weight to the extremes and less to the items nearer to mean. Since
#questiSix Operators are to be assigned to five jobs with the cost of assignment in Rs. given in the matrix below. Determine the optimal assignment. Which operator will have no ass
The systematic methodology developed for an operation research study with problems involving conflicting multiple objective policies and alternatives. Operation research in
In large sized linear programming problems, the solution cannot be obtained by the graphical method and hence a more systematic method has to be developed to find
models in operation research
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd