ABC Company manufactures both interior and exterior paints from 2 raw materials M1 and M2. The following table gives basic data of problem.
Exterior paint
Interior paint
Availability
N1
6
4
24
N2
1
2
Profit per ton
5
A market survey signifies that every day demand for interior paint cannot surpass that for exterior paint by more than 1 ton. Also maximum routine demand for interior paint is 2 tons. Develop LPP to find out the top product mix of interior and exterior paints that maximizes the daily total gain (profit).
Answer
Assume
x1 - number of units of exterior paint
x2 - number of units of interior paint
Maximize Z = 5x1 + 4x2
Subject to
6x1 + 4x2 ≤ 24
x1 + 2x2 ≤ 6
x2 - x1≤ 1
x2≤ 2
x1≥0, x2 ≥0
b) The highest routine demand for exterior paint is almost 2.5 tons
x1≤ 2.5
c) Routine demand for interior paint is as a minimum 2 tons
x2 ≥ 2
d) Routine demand for interior paint is accurately 1 ton more than that for exterior paint.
x2 > x1 + 1
A DRUG MANUFACTURER produces 2 products X1 and X2.X1 needs 2 hours on machine A AND 2 HOURS ON MACHINE B.X2 needs 3 hours on machine A and 1 hour on machine B.If machine A can run
A paper mill products two grade of paper viz., X & Y. Because of raw material restriction, it cannot produce more than 400 tons of grade X paper & 300 tons of grade Y paper in a we
Trade Literature: Trade literature consists of documents that give information on the processes and materials involved in the manufacture of a product, various types of produc
INFORMATION AND OTHER RELATED CONCEPTS - THEIR MEANING AND CHARACTERISTICS: You may often hear or read in newspapers and other popular magazines about "exponential growth of i
line drawn as Y=C+1075x, when x was 2, and y was 239, given that y intercept was 11. calculate the residualon..
Solve the following Linear Programming Problem using Simplex method. Maximize Z= 3x1 + 2X2 Subject to the constraints: X1+ X2 = 4 X1 - X2 = 2 X1, X2 = 0
QUESTION Discuss the major sources of stress and job burnout and outline the strategies for managing stress. QUESTION How can you use the „Johari Window Model? as a
Graphs of Time Series A time series is a sequence of values corresponding to successive points of time. Time series are graphed with time on the x axis and the oth
What are the computer applications of transportation and assignment problem
Inherent forces fomenting conflicts of interest Several forces have coalesced to increase the incidence of conflicts of interest in the medical industry: the vertical integrat
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd