ABC Company manufactures both interior and exterior paints from 2 raw materials M1 and M2. The following table gives basic data of problem.

 

 

Exterior paint

Interior paint

Availability

N1

6

4

24

N2

1

2

6

Profit per ton

5

4

 

A market survey signifies that every day demand for interior paint cannot surpass that for exterior paint by more than 1 ton. Also maximum routine demand for interior paint is 2 tons. Develop LPP to find out the top product mix of interior and exterior paints that maximizes the daily total gain (profit).

Answer

Assume

 x1 - number of units of exterior paint

      x2 - number of units of interior paint

 

Maximize Z = 5x1 + 4x2         

Subject to

6x1 + 4x2 ≤ 24

x1 + 2x2 ≤ 6

x2 - x1≤ 1

x2≤ 2

                 x1≥0, x2 ≥0

 

b) The highest routine demand for exterior paint is almost 2.5 tons

                 x1≤ 2.5

c) Routine demand for interior paint is as a minimum 2 tons

                 x2 ≥ 2

d) Routine demand for interior paint is accurately 1 ton more than that for exterior paint.

                 x2 > x1 + 1

 

 

 


Related Discussions:- Answering lp problems

#, Six Operators are to be assigned to five jobs with the cost of assignmen...

Six Operators are to be assigned to five jobs with the cost of assignment in Rs. given in the matrix below. Determine the optimal assignment. Which operator will have no assignment

Linear Programming, A paper mill produces two grades of paper viz., X and Y...

A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y paper i

requirements and characteristics of a good table , Requirements and Charac...

Requirements and Characteristics of a good table In the words  of Mr. Harry Jerome a good statistical table  is a triumph of ingenuity and  technique masterpiece of economy  o

Word problems based on formulation of linear programming, Word problems bas...

Word problems based on formulation of linear programming problems. 2.   A manufacturer produces nuts and bolts for industrial machinery. It takes 1 hour of work on machine 1 an

Standara deviation - measure of dispersion , STANDARA DEVIATION Standa...

STANDARA DEVIATION Standard  deviation  is the  square  root of the  arithmetic  average of  squares of all  the deviations from the  mean. In short  it may  be defined  as th

Production option and the ato process design, The plant is using the chase ...

The plant is using the chase production option and the ATO process design. The BOM is illustrated below.   Requirement The factory works on a process layout but

Replacement theory.., a pipe lis dur for rpair,the repair would cost 10000 ...

a pipe lis dur for rpair,the repair would cost 10000 and it would last for 3 years.alternatively a new pipe line can be purchase at 30000 for 10 years.assuming 10% depriciation rat

Assignment, Six Operators are to be assigned to five jobs with the cost of ...

Six Operators are to be assigned to five jobs with the cost of assignment in Rs. given in the matrix below. Determine the optimal assignment. Which operator will have no assignment

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd