Answering lp problems, Operation Research

Assignment Help:

ABC Company manufactures both interior and exterior paints from 2 raw materials M1 and M2. The following table gives basic data of problem.

 

 

Exterior paint

Interior paint

Availability

N1

6

4

24

N2

1

2

6

Profit per ton

5

4

 

A market survey signifies that every day demand for interior paint cannot surpass that for exterior paint by more than 1 ton. Also maximum routine demand for interior paint is 2 tons. Develop LPP to find out the top product mix of interior and exterior paints that maximizes the daily total gain (profit).

Answer

Assume

 x1 - number of units of exterior paint

      x2 - number of units of interior paint

 

Maximize Z = 5x1 + 4x2         

Subject to

6x1 + 4x2 ≤ 24

x1 + 2x2 ≤ 6

x2 - x1≤ 1

x2≤ 2

                 x1≥0, x2 ≥0

 

b) The highest routine demand for exterior paint is almost 2.5 tons

                 x1≤ 2.5

c) Routine demand for interior paint is as a minimum 2 tons

                 x2 ≥ 2

d) Routine demand for interior paint is accurately 1 ton more than that for exterior paint.

                 x2 > x1 + 1

 

 

 


Related Discussions:- Answering lp problems

Question, A paper mill produces two grades of paper viz., X and Y. Because ...

A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y paper i

Least cost method of transportation model, how do you calculate using this ...

how do you calculate using this method where the least cost appears twice

Effect of professional development on class management, Purpose: The pu...

Purpose: The purpose of this study is to explore the effect of professional development on teachers' Lesson Planning, Class Management, Teaching Methods, Cooperation and Teac

Methodology of operation research, The systematic methodology developed f...

The systematic methodology developed for an operation research study with problems involving conflicting multiple objective policies and alternatives. Operation research in

Operational performance and price, An electro-mechanical product for use in...

An electro-mechanical product for use in a vehicle has been in widespread use for some time and has proved popular with customers, in terms of its operational performance and price

Maths, Solve the following Linear Programming Problem using Simple method. ...

Solve the following Linear Programming Problem using Simple method. Maximize Z= 3x1 + 2X2, Subject to the constraints: X1+ X2 = 4 X1+ X2 = 2 X1, X2 = 0

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd