Answering lp problems, Operation Research

Assignment Help:

ABC Company manufactures both interior and exterior paints from 2 raw materials M1 and M2. The following table gives basic data of problem.

 

 

Exterior paint

Interior paint

Availability

N1

6

4

24

N2

1

2

6

Profit per ton

5

4

 

A market survey signifies that every day demand for interior paint cannot surpass that for exterior paint by more than 1 ton. Also maximum routine demand for interior paint is 2 tons. Develop LPP to find out the top product mix of interior and exterior paints that maximizes the daily total gain (profit).

Answer

Assume

 x1 - number of units of exterior paint

      x2 - number of units of interior paint

 

Maximize Z = 5x1 + 4x2         

Subject to

6x1 + 4x2 ≤ 24

x1 + 2x2 ≤ 6

x2 - x1≤ 1

x2≤ 2

                 x1≥0, x2 ≥0

 

b) The highest routine demand for exterior paint is almost 2.5 tons

                 x1≤ 2.5

c) Routine demand for interior paint is as a minimum 2 tons

                 x2 ≥ 2

d) Routine demand for interior paint is accurately 1 ton more than that for exterior paint.

                 x2 > x1 + 1

 

 

 


Related Discussions:- Answering lp problems

Integer programming, An integer programming problem is identical to a linea...

An integer programming problem is identical to a linear programming problem except that one or more decision variables are constrained to take integer values. Such problems cannot

One tailed and two tailed tests -hypothesis testing , Normal 0 ...

Normal 0 false false false EN-IN X-NONE X-NONE

Operation Research, A paper mill produces two grades of paper viz., X & Y. ...

A paper mill produces two grades of paper viz., X & Y. Because of raw material restrictions, it cannot produce more 400 tons of grade X paper & 300 tons of grade Y paper in a week.

Operation research, Discuss the methodology of operation research

Discuss the methodology of operation research

Linear programing, Solve the following Linear Programming Problem using Sim...

Solve the following Linear Programming Problem using Simple method. Maximize Z= 3x1 + 2X2 Subject to the constraints: X1+ X2 = 4 X1 - X2 = 2 X1, X2 = 0

Construction procedure for research tool, CONSTRUCTION PROCEDURE The c...

CONSTRUCTION PROCEDURE The construction of an interview schedule or questionnaire is a time consuming task requiring considerable attention to all the details. The investig

Effect of professional development on class management, Purpose: The pu...

Purpose: The purpose of this study is to explore the effect of professional development on teachers' Lesson Planning, Class Management, Teaching Methods, Cooperation and Teac

Lpp., Paper Mill Produces Two Grades Of Paper Viz x And y Because Of Raw Ma...

Paper Mill Produces Two Grades Of Paper Viz x And y Because Of Raw Material Restrictions It Cannot Produce More Than 400 Tons Of Grade x Paper And 300 Tons Of Grade y Paper In a We

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd