Analysis of the two stage construction, Civil Engineering

Assignment Help:

A County is planning to build a new roadway connector in the rapidly developing area of the county. The road can be built at a reduced capacity now for $30 million and can be widened 15 years later for an additional $20 million. An alternative is to construct the full capacity connector now for $40 million. Both alternatives would provide the needed capacity for the 25-year analysis period. Maintenance cost differences are small and may be ignored. At 6% interest, which alternative should be selected:

a. Two stage construction with a $1,700,000 savings

b. Single stage construction with a savings of $1,700,000

c. Two stage construction with a $300,000 savings

d. Single stage construction with a savings of $300,000

Solution: Analysis of the two-stage construction:

PW of cost = $30 million + $20 million (P/F, 6%, 15)

= $30 million + $8.3 million

= $38.3 million

Analysis of the single-stage construction: From the information provided:

PW of cost = $40 million

Two-stage construction alternative is preferred with a $1,700,000 savings.


Related Discussions:- Analysis of the two stage construction

What is tendonand describe its working, What is Tendonand describe its work...

What is Tendonand describe its working It is a steel element, such as a wire, cable, bar or strand which is provided, in a stretched form, to impart prestressing force in con

Engineering Mechanics, the jet transport B is flying north with a velocity ...

the jet transport B is flying north with a velocity vB = 600 km/h when a smaller aircraft A passes underneath the transport headed in the 60 degree direction shown. To passengers i

Butt weld – from one side vs from both sides, Q. Butt weld – from one side ...

Q. Butt weld – from one side vs from both sides? In the design of butt weld strength, it's normally presumed that its strength is at least equivalent to parent metal. To improv

Describe the features of physical survey phase, Describe the features of ph...

Describe the features of physical survey phase The Physical Survey (field and laboratory test) for the purpose of determination of physical and engineering properties of the ma

Critical-depth relationship, If y1 and y2 are alternate depths of a rectang...

If y1 and y2 are alternate depths of a rectangular channel show that Yc³ =2y1²y2²/(y1+y2) Also specific energy E = y1²+y1y2+y2²/(y1+y2)

Foundation, difference between piles and pier

difference between piles and pier

Determine the axial strength of the plates in direct tension, The two plate...

The two plates shown below are each 10-in. wide by ¾- in. thick. The gage distance, g, and the longitudinal spacing on each member is set at 4-in. Determine the axial strength of t

Calculate the total duration for the four activity project, Calculate the T...

Calculate the Total Duration for the Four Activity Project Solution:      Scheduling work activity has associated time duration. The durations shown in the Table were e

Marine piles circular in cross section, Question Give reason that why a...

Question Give reason that why are most marine piles circular in cross section? Answer As marine piles, there are a number of options existing for selection, name as H-

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd