Analysis of the two stage construction, Civil Engineering

Assignment Help:

A County is planning to build a new roadway connector in the rapidly developing area of the county. The road can be built at a reduced capacity now for $30 million and can be widened 15 years later for an additional $20 million. An alternative is to construct the full capacity connector now for $40 million. Both alternatives would provide the needed capacity for the 25-year analysis period. Maintenance cost differences are small and may be ignored. At 6% interest, which alternative should be selected:

a. Two stage construction with a $1,700,000 savings

b. Single stage construction with a savings of $1,700,000

c. Two stage construction with a $300,000 savings

d. Single stage construction with a savings of $300,000

Solution: Analysis of the two-stage construction:

PW of cost = $30 million + $20 million (P/F, 6%, 15)

= $30 million + $8.3 million

= $38.3 million

Analysis of the single-stage construction: From the information provided:

PW of cost = $40 million

Two-stage construction alternative is preferred with a $1,700,000 savings.


Related Discussions:- Analysis of the two stage construction

Cutting edge in well foundation, Q. Cutting edge in well foundation? Th...

Q. Cutting edge in well foundation? The function of cutting edge on well foundation is basically to cut through the earth which being sunk. The angle of well curb pushes the ea

BOLTED CONNECTIONS, compare riveted joints with welded joints

compare riveted joints with welded joints

Define ways of providing the anti slip device - by bolting, Define Ways of ...

Define Ways of providing the anti slip device - By Bolting? The elastomeric bearing can be vulcanised with a stainless steel outer plate. The stainless steel plate is provided

Explain transpiration and infiltration, Explain Transpiration and Infiltrat...

Explain Transpiration and Infiltration Transpiration: The part of evaporation in which water vapor enters the atmosphere through the plants. The "transpired" water originated

Preloading - control of settlements, Q. Preloading - Control of settlements...

Q. Preloading - Control of settlements? This method consists of loading the soil strata by a load intensity which will be equal to or higher than the expected load intensity. T

Trigo, a pilot entering a bay on course

a pilot entering a bay on course

Stability of column, what is end condition how effected length is calculate...

what is end condition how effected length is calculated

Thermal coefficient, Thermal Coefficient Inside of the building's tempe...

Thermal Coefficient Inside of the building's temperature can increase or reduce the snow weight. As these types of structures normally cover a wide area and heating or even tur

Write short notes on bulking of sand, Q. Write short notes on Bulking of Sa...

Q. Write short notes on Bulking of Sand? Volume of sand fluctuates with variations in moisture content when sand is wet then each particle sets coating of water due to surface

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd