A County is planning to build a new roadway connector in the rapidly developing area of the county. The road can be built at a reduced capacity now for $30 million and can be widened 15 years later for an additional $20 million. An alternative is to construct the full capacity connector now for $40 million. Both alternatives would provide the needed capacity for the 25-year analysis period. Maintenance cost differences are small and may be ignored. At 6% interest, which alternative should be selected:

a. Two stage construction with a $1,700,000 savings

b. Single stage construction with a savings of $1,700,000

c. Two stage construction with a $300,000 savings

d. Single stage construction with a savings of $300,000

Solution: Analysis of the two-stage construction:

PW of cost = $30 million + $20 million (P/F, 6%, 15)

= $30 million + $8.3 million

= $38.3 million

Analysis of the single-stage construction: From the information provided:

PW of cost = $40 million

Two-stage construction alternative is preferred with a $1,700,000 savings.


Related Discussions:- Analysis of the two stage construction

Explain the modular incinerators, Explain the Modular Incinerators 1. P...

Explain the Modular Incinerators 1. Prefabricated units with capacities of 4.5 to 107 tons of solid waste/day 2. Most use a system involving two combustion chambers.

Test on specially moulded test piece, Test on specially moulded test piece ...

Test on specially moulded test piece The test piece shall be moulded by the manufacturer with identical compound and under identical vulcanizing conditions as used in manufact

Syphon, what is the design of syphon

what is the design of syphon

Lintel, Classification of lintels

Classification of lintels

R.c.c design, how to write the beam design using c -language

how to write the beam design using c -language

Determine the late start time for activity, For the project network shown, ...

For the project network shown, the late start time (day) for activity "Q" is most nearly: Solution:  List the paths leading to "Q" and calculate the duration for each.

Geofabric strengthening of perth soils, I need technical assistance. The pr...

I need technical assistance. The project is incomplete. I need someone to proofread it. Do you have someone who know Plaxis, Slope/W and Flac?. Can you arrange a case study for Geo

Lintel, Ask question #classfication of lintel Minimum 100 words accepted#

Ask question #classfication of lintel Minimum 100 words accepted#

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd