Amount of water that added to achieve the optimum moisture, Civil Engineering

Assignment Help:

Geotechnical project specifications require that the soil's optimum moisture content of 24% be maintained during the roadbed's construction.   The field moisture test finds that five-pounds of soil has a water content of 11%.  The amount of water that must be added during the day's planned production of 1,250-tons to achieve the optimum moisture content is most nearly:

Solution:  The total mass of the moist soil is equal to the dry soil and water content.  The mass of water is equal to 11% of the dry soil.  This relationship is represented in the following equation:

Mtotal     = Msoil + Mwater

Mtotal     = Msoil + 0.11 Msoil

Mtotal     = 1.11 Msoil

Solve for the mass of the dry soil and water:

Msoil =  Mtotal/1.11  =   5-lb/1.11  =    4.50-lb

Mwater   = 0.11Msoil

 = (0.11) (4.50-lb) = .50-lb  

To raise the water content from 11% to 24%, the earthwork contractor must add 13% by mass of water.

 ΔMwater   = (ΔWrequired) (Msoil)

    = (0.13) (4.50-lb) 

    = 0.585-lbm of water per 5-lbs of soil

OR  = 0.117-lb of water / lb of soil  

Convert the results of the required additional water and apply it to the day's planned production:

 1,250-ton x 2,000-lb/ton = 2,500,000-lb of soil

2,500,000-lb of soil x 0.117-lbm of water/lb of soil = 292,500-lbm of water

292,500-lb of water ÷ 62.4-lb of water/ft3 = 4,688-ft3

4,688-ft3 x 7.48gal/ft3 = 35,062.5-gallons


Related Discussions:- Amount of water that added to achieve the optimum moisture

Main purpose of conducting load test for piling works, Question What is...

Question What is main purpose of conducting load test for piling works ? Answer Pile load test gives information on ultimate bearing ability but not settlement be

What are the causes of settlement, Q. What are the causes of settlement? ...

Q. What are the causes of settlement? The various causes of settlement are: 1) increasing load on the surrounding soil deposit, 2) excavation, 3) lowering of water tab

P.h.e, procedure for designing of sewage scheme

procedure for designing of sewage scheme

State the ground water levels, Ground Water Levels The location of the...

Ground Water Levels The location of the ground water level is essential for deep excavation, water-logged areas. The existing wells in the nearby vicinity of the proposed site

Estimate the minimum electric power, The sketch shows a common consumer pro...

The sketch shows a common consumer product called Water Pik. This device uses a motor to drive a piston pump that produces a jet of water (diameter d = 3 mm, temperature T = 10 °C)

Slope, how to calculate a slope

how to calculate a slope

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd