Amount of water that added to achieve the optimum moisture, Civil Engineering

Assignment Help:

Geotechnical project specifications require that the soil's optimum moisture content of 24% be maintained during the roadbed's construction.   The field moisture test finds that five-pounds of soil has a water content of 11%.  The amount of water that must be added during the day's planned production of 1,250-tons to achieve the optimum moisture content is most nearly:

Solution:  The total mass of the moist soil is equal to the dry soil and water content.  The mass of water is equal to 11% of the dry soil.  This relationship is represented in the following equation:

Mtotal     = Msoil + Mwater

Mtotal     = Msoil + 0.11 Msoil

Mtotal     = 1.11 Msoil

Solve for the mass of the dry soil and water:

Msoil =  Mtotal/1.11  =   5-lb/1.11  =    4.50-lb

Mwater   = 0.11Msoil

 = (0.11) (4.50-lb) = .50-lb  

To raise the water content from 11% to 24%, the earthwork contractor must add 13% by mass of water.

 ΔMwater   = (ΔWrequired) (Msoil)

    = (0.13) (4.50-lb) 

    = 0.585-lbm of water per 5-lbs of soil

OR  = 0.117-lb of water / lb of soil  

Convert the results of the required additional water and apply it to the day's planned production:

 1,250-ton x 2,000-lb/ton = 2,500,000-lb of soil

2,500,000-lb of soil x 0.117-lbm of water/lb of soil = 292,500-lbm of water

292,500-lb of water ÷ 62.4-lb of water/ft3 = 4,688-ft3

4,688-ft3 x 7.48gal/ft3 = 35,062.5-gallons


Related Discussions:- Amount of water that added to achieve the optimum moisture

Classification of bricks based on their quality, Classification of Bricks B...

Classification of Bricks Based on their Quality The bricks used in construction are classified as following: First class bricks Second class bricks Third class bric

Amount of borrow needed to bring area to elevation of 90-ft, Surveyed eleva...

Surveyed elevations are shown in Figure for a 50' x 50' grid at a proposed parking lot location. The amount of borrow needed to bring the area to an elevation of 90-ft is most near

State the method of pre- tensioning, State the method of Pre- Tensioning ...

State the method of Pre- Tensioning It is a method of prestressing concrete in which tendons are stretched or tensioned before concreting. In this form of construction, concr

Assignment, do u do drawing assignment ( 3rd angle projection)

do u do drawing assignment ( 3rd angle projection)

Estimate the probable final settlement, A bed of sand 12 m thick is underla...

A bed of sand 12 m thick is underlain by a compressible stratum of normally loaded clay, 6 m thick. The water table is at a depth of 5 m below the ground level. The bulk densities

Fly levelling, what is meant by fly levelling and when it is carried out ?

what is meant by fly levelling and when it is carried out ?

What is unimat machine, Q. What is Unimat Machine? The machine has got ...

Q. What is Unimat Machine? The machine has got 16 independently tiltable tamping tools which enable the machine to work on points and crossing as well as on plain track. The ma

Which direction of reinforcement must be provided, Question In the desi...

Question In the designing of a simply supported skew bridge , which direction of reinforcement must be provided? Answer In conventional design of steel reinforcement f

Tests on bitumen, Tests on Bitumen: The following tests are conducted...

Tests on Bitumen: The following tests are conducted on bitumen to find its suitability as a road binder : (a) Penetration test (b) Softening Point test (c) Flash Poi

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd