Q. Afflux on account of obstruction to flow?

Even if the river constriction on account of approach banks is not excessive and bridge waterway is wider than that causing critical discharge intensity, afflux can still be generated due to obstruction to flow by piers. Separation eddies forming at such obstructions result in loss of head which shows as afflux upstream of the bridge.

h = [(V2 / 17.88) + 0.01524] [(A/a)2-1]

wherein h is afflux in m, V is velocity in m/s in unobstructed stream, A is unobstructed sectional area of the river in m2 and a is obstructed sectional area of the river in m2. Other formulae in wide use are due to Negler and Yarnell.

More recently, the Bureau of Public Roads U.S.A., have adopted procedure for estimation of afflux detailed in Hydraulics of Bridge Waterway.

 


Related Discussions:- Afflux on account of obstruction to flow

Stress analysis, • The previous load analysis represents a first and necess...

• The previous load analysis represents a first and necessary step in the analysis of the given structure but it does not tell us whether the given load can be safely supported (i.

Sub-surface drainage, Sub-surface Drainage: Sub-surface drainage is i...

Sub-surface Drainage: Sub-surface drainage is intended to take away the water seeping through the pervious layers of the soil, causing a high water table, or in cut slopes of

Minimum and maximum area of reinforcement, Q. Minimum and maximum area of r...

Q. Minimum and maximum area of reinforcement? Minimum area of reinforcement vs. maximum area of reinforcement Beams can be designed to be larger than required for strength

Geotechnical, send any civil engineering related questions . i will write t...

send any civil engineering related questions . i will write the answers , please tell us the process .

Strength of materials, Didtribution of shear stree over a triangular sectio...

Didtribution of shear stree over a triangular section

Structural analysis, steps to analysis a portal frame with sway condition

steps to analysis a portal frame with sway condition

Duration activity for cast-in-place foundation formwork, A concrete contrac...

A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF

Steel truss 15 m span, types of truss of 15 m cantilever with 1000 kg on fr...

types of truss of 15 m cantilever with 1000 kg on free end. May be steel or any lightest material aluminium anodized truss. thanks

Pumps, largest centrifugal pumps

largest centrifugal pumps

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd