Advantages of continuous multiple-span deck, Civil Engineering

Assignment Help:

Q. Advantages of continuous multiple-span deck over simply supported multiple-span deck?

Movement joints are generally added to bridge structures to accommodate movements because of dimensional changes arising from temperature variation, shrinkage, creep and effect of pre-stress. Though provision of excessive movement joints must be avoided in design since movement joints always encounter problems giving rise to trouble in normal operation and this increases cost of maintenance. 

A number of designers may prefer to add more movement joints to guard against possible occurrence of differential settlements. Though the effect of continuity is disabled by this excessive introduction of movement joints.

From structural point of view, use of continuous deck increases the reduction of bridge deck thickness. Furthermore deck continuity allows the potential increase in headroom in mid-span of bridges by using sucker deck principle. 

Some designers may prefer to employ the use of simply supported multiple-span deck to guard against probable occurrence of differential settlements. But the effect of continuity is undermined by the introduction of movement joints. In essence structural reserve provided by a continuous bridge is destroyed by multiple-span statically determinate structure resulting from the addition of joints.

Furthermore the reduction of joints in bridge structures signifies substantial cost savings arising from construction and maintenance costs of movement joints. Reduction of deck thickness helps to cut the cost for both deck and foundation. Particularly the number of bearings in every piers is substantially decreased when compared with the case of simply supported multiple-span deck.

Advantages of using the bridge form of precast pre-stressed beams supporting in-situ concrete top slab.

The potential benefits of employing the useof bridge form of precast pre-stressed beams supporting in-situ concrete top slab are:

(i)  For bridges which are built on top of rivers and carriageway, this bridge form provides working platform by precast beams so that erection of falsework isn't required.

(ii)  This bridge form normally doesn't require any transverse beams or diaphragms (excepting at the location of bridge supports) leading to reduction of construction cost andtime. 

(iii) It creates the potential for concurrent construction with several spans.


Related Discussions:- Advantages of continuous multiple-span deck

Hydrometer analysis - soil mechanics and foundations, Hydrometer Analysis -...

Hydrometer Analysis - soil mechanics and foundations Hydrometer Analysis used to obtain the grain size distribution of fine-grained soils (finer sands, silts and clays) smalle

Airpot, how to design a new airport

how to design a new airport

Categories of losses of prestress, Categories of losses of prestress We...

Categories of losses of prestress We may put various losses in either of two categories : Losses which take place during transfer of  prestress and those which take place after

What do you mean by manhole loss, Q. What do you mean by Manhole loss? ...

Q. What do you mean by Manhole loss? Manholes are provided in locations where there are changes in direction, size and gradient of gravity pipelines. Generally practice for str

Explain flocculation, Explain Flocculation Most important factor ef...

Explain Flocculation Most important factor effecting particle removal efficiency objective - to bring particles into contact so that they will collide, stick together

Corrosion protection of lifting anchors in precast concrete, Q. Corrosion p...

Q. Corrosion protection of lifting anchors in precast concrete? Corrosion of lifting anchors in precast concrete units has to be prevented since the corroded lifting units caus

Two pegs test, the distance between two pegs M and N is 7,063 as measured o...

the distance between two pegs M and N is 7,063 as measured on a slope. the height measured on the pegs are that M=1.814M and N=0.5687M

Stop dead restriction, With a clear sketch indicate the system of protectio...

With a clear sketch indicate the system of protection of line for works of short duration where ‘ Stop dead restriction' need to be observed on a single line section on a BG track.

coursework (commercial management), Ask que1. Identify the risks involved ...

Ask que1. Identify the risks involved in this project related to cost in the perspective of the customer and analyse the probability of acceptance of such a project by customers. 2

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd