Advantages of continuous multiple-span deck, Civil Engineering

Assignment Help:

Q. Advantages of continuous multiple-span deck over simply supported multiple-span deck?

Movement joints are generally added to bridge structures to accommodate movements because of dimensional changes arising from temperature variation, shrinkage, creep and effect of pre-stress. Though provision of excessive movement joints must be avoided in design since movement joints always encounter problems giving rise to trouble in normal operation and this increases cost of maintenance. 

A number of designers may prefer to add more movement joints to guard against possible occurrence of differential settlements. Though the effect of continuity is disabled by this excessive introduction of movement joints.

From structural point of view, use of continuous deck increases the reduction of bridge deck thickness. Furthermore deck continuity allows the potential increase in headroom in mid-span of bridges by using sucker deck principle. 

Some designers may prefer to employ the use of simply supported multiple-span deck to guard against probable occurrence of differential settlements. But the effect of continuity is undermined by the introduction of movement joints. In essence structural reserve provided by a continuous bridge is destroyed by multiple-span statically determinate structure resulting from the addition of joints.

Furthermore the reduction of joints in bridge structures signifies substantial cost savings arising from construction and maintenance costs of movement joints. Reduction of deck thickness helps to cut the cost for both deck and foundation. Particularly the number of bearings in every piers is substantially decreased when compared with the case of simply supported multiple-span deck.

Advantages of using the bridge form of precast pre-stressed beams supporting in-situ concrete top slab.

The potential benefits of employing the useof bridge form of precast pre-stressed beams supporting in-situ concrete top slab are:

(i)  For bridges which are built on top of rivers and carriageway, this bridge form provides working platform by precast beams so that erection of falsework isn't required.

(ii)  This bridge form normally doesn't require any transverse beams or diaphragms (excepting at the location of bridge supports) leading to reduction of construction cost andtime. 

(iii) It creates the potential for concurrent construction with several spans.


Related Discussions:- Advantages of continuous multiple-span deck

Compute the negative skin friction of the pile group, A square pile group o...

A square pile group of 9 piles passes by a recently filled up material of 4.5 m depth. The diameter of the pile is 30 cm and pile spacing is 90 cm centre to centre. If the unconfin

Resting on several raking piles, Question Should dolphins be designed i...

Question Should dolphins be designed in a rigid manner such as resting on several raking piles? Answer While designing dolphins, they are normally supported on a syste

Define surface water treatment rule (swtr), Define Surface Water Treatment ...

Define Surface Water Treatment Rule (SWTR) SWTR sets forth primary drinking water regulations requiring treatment of surface water supplies or groundwater supplies under the di

Inspection and quality control certificate, Q. Inspection and Quality Contr...

Q. Inspection and Quality Control Certificate : A 'lot' under inspection should be accepted by the inspector when no defect is found in the acceptance level tests and so certif

.levelling, differentiate between Dumpy level:The Wye or Y level:Cooke''s r...

differentiate between Dumpy level:The Wye or Y level:Cooke''s reversible level: Cushing''s level:Tilting level and Automatic level

List the significant engineering classification system, How do you distingu...

How do you distinguish among clay and silt in the field? State the purpose of identification and categorization of soils. List any three significant engineering classification syst

Construction material, 4. Calculate the loose volume of material needed to ...

4. Calculate the loose volume of material needed to fill in the trench as sketched below. The following information is also known: [7] o Length of trench = 250 m o Trench

Fire resistance of steelwork, Q. Fire resistance of steelwork Because ...

Q. Fire resistance of steelwork Because of the high thermal conductivity of steel, temperature of unprotected steel is almost the same as temperature of fire. Because the yiel

STRUCTURAL DYNAMICS, Consider a diver weighing 200 Ib at the end of a divin...

Consider a diver weighing 200 Ib at the end of a diving board that cantilevers out 3 ft. The diver oscillates at a frequency of 2 Hz. What is the flexural rigidity E I of the divin

Find the settlement at the centre and at edge of the footing, A load of 300...

A load of 3000 kN is being taken by a square column footing. Side of the column is 3 m, footing rests on a silty soil with a Poisson's ratio = 0.3. Modulus of elasticity of the soi

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd