Advantages of continuous multiple-span deck, Civil Engineering

Assignment Help:

Q. Advantages of continuous multiple-span deck over simply supported multiple-span deck?

Movement joints are generally added to bridge structures to accommodate movements because of dimensional changes arising from temperature variation, shrinkage, creep and effect of pre-stress. Though provision of excessive movement joints must be avoided in design since movement joints always encounter problems giving rise to trouble in normal operation and this increases cost of maintenance. 

A number of designers may prefer to add more movement joints to guard against possible occurrence of differential settlements. Though the effect of continuity is disabled by this excessive introduction of movement joints.

From structural point of view, use of continuous deck increases the reduction of bridge deck thickness. Furthermore deck continuity allows the potential increase in headroom in mid-span of bridges by using sucker deck principle. 

Some designers may prefer to employ the use of simply supported multiple-span deck to guard against probable occurrence of differential settlements. But the effect of continuity is undermined by the introduction of movement joints. In essence structural reserve provided by a continuous bridge is destroyed by multiple-span statically determinate structure resulting from the addition of joints.

Furthermore the reduction of joints in bridge structures signifies substantial cost savings arising from construction and maintenance costs of movement joints. Reduction of deck thickness helps to cut the cost for both deck and foundation. Particularly the number of bearings in every piers is substantially decreased when compared with the case of simply supported multiple-span deck.

Advantages of using the bridge form of precast pre-stressed beams supporting in-situ concrete top slab.

The potential benefits of employing the useof bridge form of precast pre-stressed beams supporting in-situ concrete top slab are:

(i)  For bridges which are built on top of rivers and carriageway, this bridge form provides working platform by precast beams so that erection of falsework isn't required.

(ii)  This bridge form normally doesn't require any transverse beams or diaphragms (excepting at the location of bridge supports) leading to reduction of construction cost andtime. 

(iii) It creates the potential for concurrent construction with several spans.


Related Discussions:- Advantages of continuous multiple-span deck

Overhanging beams, Do we take the whole length (including the over hanging ...

Do we take the whole length (including the over hanging portion when we say the "whole span" of th beam ?

What is multiple-cell box girder, Q. What is Multiple-cell box girder? ...

Q. What is Multiple-cell box girder? Multiple-cell box girder: cells connected by top flanges vs. cells connected both by top and bottom flanges When the depth of a box gi

Explain the equalization basins - hydraulic system, Equalization Basins - H...

Equalization Basins - Hydraulic System For influent flow to publicly owned treatment works (POTWs), flow rates may be excessive for short or long durations, especially in combi

How the water table is lowered, The water table is lowered from a depth of ...

The water table is lowered from a depth of 3 m to a depth of 6 m in a deposit of silt. The silt remains saturated even after the water table is lowered. What would be the enhance i

Calculate the horizontal distance, Calculate the Horizontal Distance A ...

Calculate the Horizontal Distance A surveyor's total station measured slope distance near station 3245+26.35 is recorded as 437.380-m with a zenith angle of 118º 48' 07" and a

Simply-supported beam, A simply-supported beam (AB) with an overhang (BC) i...

A simply-supported beam (AB) with an overhang (BC) is illustrated in Figure 1(a), with the cross-sectional details given in Figure 1(b). The dead load comprises self weight only; f

Convert the azimuth reading of 273.34 to a land bearing, Convert the azimut...

Convert the azimuth reading of 273.34º to a land bearing:  Solution: Convert 273.34º to degrees minutes and seconds = 273º 20' 24" Next, convert the angle to orient to IV

Numericals on settlement of foundation, A footing foundation for a water to...

A footing foundation for a water tower carries a load of 9000 kN and is 3.6 metres square. It rests on dense sand of 9 m thickness overlying a clay layer of 3 metres depth. The cla

Hexagon, how to draw a regular hexagon using semicircle method

how to draw a regular hexagon using semicircle method

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd