Advantages of continuous multiple-span deck, Civil Engineering

Assignment Help:

Q. Advantages of continuous multiple-span deck over simply supported multiple-span deck?

Movement joints are generally added to bridge structures to accommodate movements because of dimensional changes arising from temperature variation, shrinkage, creep and effect of pre-stress. Though provision of excessive movement joints must be avoided in design since movement joints always encounter problems giving rise to trouble in normal operation and this increases cost of maintenance. 

A number of designers may prefer to add more movement joints to guard against possible occurrence of differential settlements. Though the effect of continuity is disabled by this excessive introduction of movement joints.

From structural point of view, use of continuous deck increases the reduction of bridge deck thickness. Furthermore deck continuity allows the potential increase in headroom in mid-span of bridges by using sucker deck principle. 

Some designers may prefer to employ the use of simply supported multiple-span deck to guard against probable occurrence of differential settlements. But the effect of continuity is undermined by the introduction of movement joints. In essence structural reserve provided by a continuous bridge is destroyed by multiple-span statically determinate structure resulting from the addition of joints.

Furthermore the reduction of joints in bridge structures signifies substantial cost savings arising from construction and maintenance costs of movement joints. Reduction of deck thickness helps to cut the cost for both deck and foundation. Particularly the number of bearings in every piers is substantially decreased when compared with the case of simply supported multiple-span deck.

Advantages of using the bridge form of precast pre-stressed beams supporting in-situ concrete top slab.

The potential benefits of employing the useof bridge form of precast pre-stressed beams supporting in-situ concrete top slab are:

(i)  For bridges which are built on top of rivers and carriageway, this bridge form provides working platform by precast beams so that erection of falsework isn't required.

(ii)  This bridge form normally doesn't require any transverse beams or diaphragms (excepting at the location of bridge supports) leading to reduction of construction cost andtime. 

(iii) It creates the potential for concurrent construction with several spans.


Related Discussions:- Advantages of continuous multiple-span deck

#title.cement factor, Aplease provide tables for each design mix and also t...

Aplease provide tables for each design mix and also the, high early strengh.l thanks

Changeable depth bridge decks, Question What is the sucker deck principle f...

Question What is the sucker deck principle for changeable depth bridge decks ? Answer For a variable depth bridge deck, depth of continuous multi-span bridge deck is greater tha

Base of concrete retaining walls, Q. Granular fill or rock fill essential a...

Q. Granular fill or rock fill essential at the base of concrete retaining walls? It isn't uncommon that rock fill layers and granular fill layers are placed beneath the bottom

Define the finish-to-start dependency, Sheet rock cannot be installed in th...

Sheet rock cannot be installed in the new house you are building until a building inspector approves the plumbing, electrical, HVAC, and insulation.  This is an example of:

Calculate the poissons ratio, Calculate the Poissons Ratio: In separat...

Calculate the Poissons Ratio: In separate experiments, Young's Modulus and Rigidity Modulus of a material have been determined as 120 GPa and 50 GPa respectively. Calculate th

Project management, Project Management: This unit starts with the gene...

Project Management: This unit starts with the general definition of Project management. Several phases involved in project management are also desribed. Further, the technique

Disparities between regular precast and pipe jacking, Question What are...

Question What are main disparities in design between regular precast concrete pipes and pipes used for pipe jacking ? Answer For pipes used for pipe jacking, they h

Measure the safe load on the pile, A wood pile of 10 m length is driven by ...

A wood pile of 10 m length is driven by a 1500 kg drop hammer falling by 3 m to a final set equal to 1.25 cm per blow. Measure the safe load on the pile using the Engineering Ne

Compute the thermal stresses in steel, Compute the thermal stresses in stee...

Compute the thermal stresses in steel: Consider the compound bar shown in below figure consisting of a steel bolt of diameter 18 mm, surrounded through a copper tube of outer

For the plane area shown determine the first moments, for the plane area sh...

for the plane area shown determine the first moments with respects to the x & y axis & the location of the centroid

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd