Advantages of continuous multiple-span deck, Civil Engineering

Assignment Help:

Q. Advantages of continuous multiple-span deck over simply supported multiple-span deck?

Movement joints are generally added to bridge structures to accommodate movements because of dimensional changes arising from temperature variation, shrinkage, creep and effect of pre-stress. Though provision of excessive movement joints must be avoided in design since movement joints always encounter problems giving rise to trouble in normal operation and this increases cost of maintenance. 

A number of designers may prefer to add more movement joints to guard against possible occurrence of differential settlements. Though the effect of continuity is disabled by this excessive introduction of movement joints.

From structural point of view, use of continuous deck increases the reduction of bridge deck thickness. Furthermore deck continuity allows the potential increase in headroom in mid-span of bridges by using sucker deck principle. 

Some designers may prefer to employ the use of simply supported multiple-span deck to guard against probable occurrence of differential settlements. But the effect of continuity is undermined by the introduction of movement joints. In essence structural reserve provided by a continuous bridge is destroyed by multiple-span statically determinate structure resulting from the addition of joints.

Furthermore the reduction of joints in bridge structures signifies substantial cost savings arising from construction and maintenance costs of movement joints. Reduction of deck thickness helps to cut the cost for both deck and foundation. Particularly the number of bearings in every piers is substantially decreased when compared with the case of simply supported multiple-span deck.

Advantages of using the bridge form of precast pre-stressed beams supporting in-situ concrete top slab.

The potential benefits of employing the useof bridge form of precast pre-stressed beams supporting in-situ concrete top slab are:

(i)  For bridges which are built on top of rivers and carriageway, this bridge form provides working platform by precast beams so that erection of falsework isn't required.

(ii)  This bridge form normally doesn't require any transverse beams or diaphragms (excepting at the location of bridge supports) leading to reduction of construction cost andtime. 

(iii) It creates the potential for concurrent construction with several spans.


Related Discussions:- Advantages of continuous multiple-span deck

Manage civil work design, Ask question #Minimum 1Make a detailed list of al...

Ask question #Minimum 1Make a detailed list of all constraints and requirements to the bridge design00 words accepted#

Determine the stage of cracking moment of pre-stress, Determine the stage o...

Determine the stage of Cracking moment of pre-stress  At the stage of transfer of pre-stress in the pre-stressed beam element, only the pre-stressing force and the self weight

Inadequate pile founding level, Reasons of common occurrence of "inadequate...

Reasons of common occurrence of "inadequate pile founding level" in piles of piers The most severe load on piers usually is the horizontal load owing to berthing and mooring o

Shear strength of concrete., why do we use effective depth ''d'' in calcula...

why do we use effective depth ''d'' in calculating the shear capacity of uncracked Concrete beam. If it is uncracked, why cant we use the full depth ''D''.

How are freeway bridges built, After measuring the anticipated traffic for ...

After measuring the anticipated traffic for the bridge, cement/reinforced- with- rebar stanchions are spaced over the freeway to accommodate the bridge. An 'off-ramp' from the free

Stormwater, Design of the stormwater drainage system for the sub-division ...

Design of the stormwater drainage system for the sub-division Work needed: The following tasks require to be performed for the drainage network: Compute stormwater r

All semiconductors have how many electrons in their last orb, All semicondu...

All semiconductors have how many electrons in their last orbit? Answer: All semiconductors have  4 electrons.

Basic Structural Design, A flitched beam consists of a wooden joist 150 mm ...

A flitched beam consists of a wooden joist 150 mm wide and 300 mm deep strengthened by steel plates 12 mm thick and 300 mm deep one on either side of the joist. If the maximum st

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd