Advantages of continuous multiple-span deck, Civil Engineering

Assignment Help:

Q. Advantages of continuous multiple-span deck over simply supported multiple-span deck?

Movement joints are generally added to bridge structures to accommodate movements because of dimensional changes arising from temperature variation, shrinkage, creep and effect of pre-stress. Though provision of excessive movement joints must be avoided in design since movement joints always encounter problems giving rise to trouble in normal operation and this increases cost of maintenance. 

A number of designers may prefer to add more movement joints to guard against possible occurrence of differential settlements. Though the effect of continuity is disabled by this excessive introduction of movement joints.

From structural point of view, use of continuous deck increases the reduction of bridge deck thickness. Furthermore deck continuity allows the potential increase in headroom in mid-span of bridges by using sucker deck principle. 

Some designers may prefer to employ the use of simply supported multiple-span deck to guard against probable occurrence of differential settlements. But the effect of continuity is undermined by the introduction of movement joints. In essence structural reserve provided by a continuous bridge is destroyed by multiple-span statically determinate structure resulting from the addition of joints.

Furthermore the reduction of joints in bridge structures signifies substantial cost savings arising from construction and maintenance costs of movement joints. Reduction of deck thickness helps to cut the cost for both deck and foundation. Particularly the number of bearings in every piers is substantially decreased when compared with the case of simply supported multiple-span deck.

Advantages of using the bridge form of precast pre-stressed beams supporting in-situ concrete top slab.

The potential benefits of employing the useof bridge form of precast pre-stressed beams supporting in-situ concrete top slab are:

(i)  For bridges which are built on top of rivers and carriageway, this bridge form provides working platform by precast beams so that erection of falsework isn't required.

(ii)  This bridge form normally doesn't require any transverse beams or diaphragms (excepting at the location of bridge supports) leading to reduction of construction cost andtime. 

(iii) It creates the potential for concurrent construction with several spans.


Related Discussions:- Advantages of continuous multiple-span deck

Effect of prestress in an reinforced cantilever beam, Effect of prestress i...

Effect of prestress in an reinforced cantilever beam The effect of prestress in an ordinary reinforced cantilever beam and a prestressed concrete (PSC) beam. When no load is pr

Design a water supply scheme for new railway colony, Q. Design a water supp...

Q. Design a water supply scheme for new Railway colony based on the following data's. i. Requirement of Loco and domestic consumption 5 lacs gallon per day. ii. Source of wat

Forensic structural engineering, i need journals or articles of forensic st...

i need journals or articles of forensic structural engineering

Find the cumulative distribution function, Find the Cumulative Distribution...

Find the Cumulative Distribution Function: Find the cdf of Y = Z 2 where Z - N (0,l) Solution: F(y)= P(Y ≤ y) = p(z 2 ≤y) = P(-√y≤ √z≤√y) = ?(√y)- ?(-√y) = ?(√y)

What is material at site return, Q. What is Material at site Return? Th...

Q. What is Material at site Return? The authority is executive charge of a work should be responsible for holding in safe custody for controlling the consumption and to the ext

Foundation, Explain briefly shallow foundation?

Explain briefly shallow foundation?

Cantilever beam, can i use lockfix to making cantilever beam

can i use lockfix to making cantilever beam

Warm mix asphalt., how it different from hot mix asphalt . is it changes an...

how it different from hot mix asphalt . is it changes any performance compared to hot mix asphalt

Construct the correct network for project, A project requires that activiti...

A project requires that activities A and B can be started independently and activities C and D are independent but can be started after A and B have been completed. Activity E can

State the term directly below the edge of the footing, The load from a cont...

The load from a continuous footing of 1.8 metres width, which may be considered to be a strip load of considerable length, is 180 kN/m 2 . Verify the maximum principal stress at 1.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd