Advantages and disadvantages of a matrix project structure, Project Management

Assignment Help:

C Consultancy Company gives management consultancy to a range of organisations.  It employs staff who have dissimilar industry backgrounds and who also offer dissimilar specialisms, for instance, in finance, marketing, IT, leadership, change management and logistics. The Company is currently organised around these specialist areas, with each specialism having a senior manager in charge.  Though, for some of its project work it is necessary to adopt a matrix structure to meet the client's requirements.

Explain the advantages and disadvantages of a matrix project structure for C Consultancy Company's project work

The matrix structure could bring a number of benefits to consultancy project work. For example, it would bring together a wide range of expertise cutting across specialisms to work on a client project. This would also allow the company to offer a broader portfolio of consultancy interventions. From an employee perspective, it can facilitate the development of latest skills and adaptation to unexpected problems, broadening a specialist's outlook by working with others.  

Whilst there are benefits, there can be drawbacks to the matrix project structure. One of the major problems is associated with the lack of clear responsibilities and potential clashes and tensions among the different priorities of the project tasks and the specialist area.  

 


Related Discussions:- Advantages and disadvantages of a matrix project structure

Define the process of critical path analysis, Define the process of critica...

Define the process of critical path analysis. Process of critical path analysis: 1. Break down project within a logical sequence of activities to be finished. 2. Appro

Tolerance and surface finish, Tolerance and Surface Finish Design engi...

Tolerance and Surface Finish Design engineers are always blamed of specifying closer tolerances than necessary. It  is obvious that to achieve a tolerance of ± 0.001 mm is mor

#title.Risk management and procurement, Critically evaluate the use of comp...

Critically evaluate the use of complex models of Project Risk and Procurement Management; systematically and creatively making sound judgements based on the systematic analysis and

Why does the public sector exist, Question 1: a) Why does the public s...

Question 1: a) Why does the public sector exist? b) Discuss 5 ways in which the public sector is different from the private sector. c) The public sector is a clo

Approaches of soft systems methodology and socio-technical, Why are approac...

Why are approaches as like the Soft Systems Methodology, Business Process Reengineering and the Socio-Technical Approach relevant to IS project managers? The development of inf

What are the distinguishing characteristics of a project, Question : (a...

Question : (a) What are the distinguishing characteristics of a project? (b) What are the four types of consequences of risk? (c) Explain what you understand by the term

What are necessary features of the earned value management, What are the ne...

What are the necessary features of the Earned Value Management? Necessary features of EVM systems: a. A quantified project plan which identifies work or activities to be

Risk management , Introduction to Risk Management Let us begin with def...

Introduction to Risk Management Let us begin with defining Risk. Risk, is an integral part of the business scenario, and can be termed as a potential event that can have opport

Linear Programming Problem, Maximize Z= 3x1 + 2X2 Subject to the constraint...

Maximize Z= 3x1 + 2X2 Subject to the constraints: X1+ X2 = 4 X1 - X2 = 2 X1, X2 = 0

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd