Aashto method, Civil Engineering

Assignment Help:

Question 1: A stationary 40 kN single axle load (applied on a circular contact area of radius = 152 mm = 6") is applied to each of the flexible pavement structures indicated below. Assuming linear elastic behaviour and no edge effects, use KENLAYER to determine for the two pavement systems given below:

a.  total maximum surface deflection of the pavement system;

b.  horizontal strain at the bottom of the HMA layer; and,

c.  vertical stress on the top of the subgrade.

Pavement systems:

i)  150 mm of HMA with 3,500 MPa modulus; placed directly on a sandy subgrade with 75 MPa modulus.

ii)  75 mm of HMA with 3,900 MPa; 200 mm of granular base with 150 MPa modulus; and clay subgrade with 40 MPa modulus.

2.) Assuming the HMA is the Asphalt Institute "standard mix", use both the Asphalt Institute and Shell methods (at 95% reliability) to predict the failure mode by either fatigue or rutting, and estimate the limiting number of load repetitions to achieve this failure mode for the two pavement systems described in Problem 1.

3.) Using the AASHTO method, design a flexible pavement system consisting of HMA and granular base placed on the subgrade described in Table 3.1 below, for the following conditions:

5-year predicted design traffic = W18 = 1.5(106) ESAL pt=1.8;R=95%;S0=0.35 Granular base modulus, E2 = K1-K2, where K1 = 7000 and K2 = 0.6 Base is expected to be exposed to moisture levels approaching saturation for 2% of the time.

Question 2:

Design a flexible pavement overlay using the AASHTO method for a 5-year old pavement structure consisting of 5.75 inches of HMA and 23 inches of granular base, placed on a silty clayey sand subgrade. The future traffic to be sustained over the next five years will be 2.1(106) ESAL.     Deflection testing conducted in October at a temperature of 68°F, using a load of 18 kips, provided a mean surface deflection of 0.191349 inches centred under the 5.9-inch radius loading plate and 0.022955 inches at a distance of 48 inches from the centre of the loading plate. Assume m2 = 1.10 due to contamination of the granular base with fines. Use p1 = 4.2, pt= 1.5, R=95% reliability and assume a standard deviation of 0.49.

Question 3: 

a)Using the PCA method, design the minimum slab thickness (to the nearest 1⁄2 inch) required for a 4-lane divided major highway (2 lanes in each direction separated by a grass median). Design a rigid concrete pavement with doweled joints and with concrete shoulders to be placed on a 9-inch thick untreated granular subbase which overlays a clay subgrade having a k-value of 100 pci. Modulus of rupture for the concrete is 650 psi. Design period = 20 years; current ADT is 13,500; annual growth rate is 3.5%; and ADTT = 20%.

b)Design the welded wire mesh reinforcement, tie bars, dowels and joints, and shoulders required if this pavement is to be a jointed reinforced concrete pavement with a lane width of 12 ft. Use a maximum allowable joint opening of 0.25 inches for a doweled joint.


Related Discussions:- Aashto method

Scales and sludges, Discussscales and sludges. Writea note on internal trea...

Discussscales and sludges. Writea note on internal treatment of water

Shear Iosipescu Test, First Can I use this device to test concrete specimen...

First Can I use this device to test concrete specimen? Second it is very important for me that wouldn’t have tensile strength when I want to fix specimens. Because the specimens su

Process in terms of shrinkage of concrete, In bridge widening projects, mea...

In bridge widening projects, means of stitching is normally employed for connecting existing deck to a new deck. What are the problems that occur connected with this process in ter

Statics, Currently I am struggling with masteringengineering.com So is it f...

Currently I am struggling with masteringengineering.com So is it fine to give you my username and password so you could solve my problems. please show your work.

Show acceptance testing, Level 2 Acceptance Testing : This will also includ...

Level 2 Acceptance Testing : This will also include the same tests as in Level 1 A. General inspection B. Test on specially moulded test piece C. Test on complete bearings

Joints in box culverts and channels, Joints in box culverts and channels - ...

Joints in box culverts and channels - necessity of water tightness The joints for box culverts and channels must be capable of accommodating movements arising from moisture an

Show ph value of water, Q. PH Value of Water? It is a symbol for hydrog...

Q. PH Value of Water? It is a symbol for hydrogen ion concentration and indicates acidity or alkalinity. When P H Value more than 7 water is alkaline and less than 7 water is a

All semiconductors have how many electrons in their last orb, All semicondu...

All semiconductors have how many electrons in their last orbit? Answer: All semiconductors have  4 electrons.

Unsealed contraction joints in concrete pavement, Unsealed contraction join...

Unsealed contraction joints in concrete pavement For unreinforced concrete pavement, contraction joint is an approximately 3mm wide groove with a depth of about one-third to o

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd