Aashto method, Civil Engineering

Assignment Help:

Question 1: A stationary 40 kN single axle load (applied on a circular contact area of radius = 152 mm = 6") is applied to each of the flexible pavement structures indicated below. Assuming linear elastic behaviour and no edge effects, use KENLAYER to determine for the two pavement systems given below:

a.  total maximum surface deflection of the pavement system;

b.  horizontal strain at the bottom of the HMA layer; and,

c.  vertical stress on the top of the subgrade.

Pavement systems:

i)  150 mm of HMA with 3,500 MPa modulus; placed directly on a sandy subgrade with 75 MPa modulus.

ii)  75 mm of HMA with 3,900 MPa; 200 mm of granular base with 150 MPa modulus; and clay subgrade with 40 MPa modulus.

2.) Assuming the HMA is the Asphalt Institute "standard mix", use both the Asphalt Institute and Shell methods (at 95% reliability) to predict the failure mode by either fatigue or rutting, and estimate the limiting number of load repetitions to achieve this failure mode for the two pavement systems described in Problem 1.

3.) Using the AASHTO method, design a flexible pavement system consisting of HMA and granular base placed on the subgrade described in Table 3.1 below, for the following conditions:

5-year predicted design traffic = W18 = 1.5(106) ESAL pt=1.8;R=95%;S0=0.35 Granular base modulus, E2 = K1-K2, where K1 = 7000 and K2 = 0.6 Base is expected to be exposed to moisture levels approaching saturation for 2% of the time.

Question 2:

Design a flexible pavement overlay using the AASHTO method for a 5-year old pavement structure consisting of 5.75 inches of HMA and 23 inches of granular base, placed on a silty clayey sand subgrade. The future traffic to be sustained over the next five years will be 2.1(106) ESAL.     Deflection testing conducted in October at a temperature of 68°F, using a load of 18 kips, provided a mean surface deflection of 0.191349 inches centred under the 5.9-inch radius loading plate and 0.022955 inches at a distance of 48 inches from the centre of the loading plate. Assume m2 = 1.10 due to contamination of the granular base with fines. Use p1 = 4.2, pt= 1.5, R=95% reliability and assume a standard deviation of 0.49.

Question 3: 

a)Using the PCA method, design the minimum slab thickness (to the nearest 1⁄2 inch) required for a 4-lane divided major highway (2 lanes in each direction separated by a grass median). Design a rigid concrete pavement with doweled joints and with concrete shoulders to be placed on a 9-inch thick untreated granular subbase which overlays a clay subgrade having a k-value of 100 pci. Modulus of rupture for the concrete is 650 psi. Design period = 20 years; current ADT is 13,500; annual growth rate is 3.5%; and ADTT = 20%.

b)Design the welded wire mesh reinforcement, tie bars, dowels and joints, and shoulders required if this pavement is to be a jointed reinforced concrete pavement with a lane width of 12 ft. Use a maximum allowable joint opening of 0.25 inches for a doweled joint.


Related Discussions:- Aashto method

Culverts, Can anyone help me in finding the formula for submerged and unsub...

Can anyone help me in finding the formula for submerged and unsubmerged flow in culverts?

What is bonded post-tensioning, What is Bonded Post-tensioning In post...

What is Bonded Post-tensioning In post-tensioned construction, ducts, in which tendons are provided, are sometimes grouted after the stressing operation. Though the mechanism

Determine the normal and shear stress elements, Determine the normal and sh...

Determine the normal and shear stress elements: The state of stress at a point is given through the stress components σ x = 70 MPa, σ y = 10 MPa, and τ xy = - 40 MPa. Using

Mohrs circle, The state of stress at a point is given through the stress co...

The state of stress at a point is given through the stress components sx = 70 MPa, sy = 10 MPa, and txy = - 40 MPa. Using Mohr''s circle find (i) Principal stresses, and (ii) Princ

Design the 2-span continuous center, Design the 2-span continuous center T-...

Design the 2-span continuous center T-beam, B2, for the floor syetem shown below. The girders that the beam frames into are all 24" wide. Using fc'= 5 ksi, and fy = 60 ksi. The ser

State the process to calculate the transmission length, State the process t...

State the process to calculate the Transmission Length It is the distance required at the end of a concrete member for developing the maximum tendon stress by bond.

Calcculate the material costs, A capital improvement project requires the i...

A capital improvement project requires the installation of a property line fence along the 250-ft Northern boundary line.The decorative aluminum fence is constructed of posts space

Manufacturing technique of ferro cement, what are the manufacturing techniq...

what are the manufacturing techniques of ferro cement?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd