Aashto method, Civil Engineering

Assignment Help:

Question 1: A stationary 40 kN single axle load (applied on a circular contact area of radius = 152 mm = 6") is applied to each of the flexible pavement structures indicated below. Assuming linear elastic behaviour and no edge effects, use KENLAYER to determine for the two pavement systems given below:

a.  total maximum surface deflection of the pavement system;

b.  horizontal strain at the bottom of the HMA layer; and,

c.  vertical stress on the top of the subgrade.

Pavement systems:

i)  150 mm of HMA with 3,500 MPa modulus; placed directly on a sandy subgrade with 75 MPa modulus.

ii)  75 mm of HMA with 3,900 MPa; 200 mm of granular base with 150 MPa modulus; and clay subgrade with 40 MPa modulus.

2.) Assuming the HMA is the Asphalt Institute "standard mix", use both the Asphalt Institute and Shell methods (at 95% reliability) to predict the failure mode by either fatigue or rutting, and estimate the limiting number of load repetitions to achieve this failure mode for the two pavement systems described in Problem 1.

3.) Using the AASHTO method, design a flexible pavement system consisting of HMA and granular base placed on the subgrade described in Table 3.1 below, for the following conditions:

5-year predicted design traffic = W18 = 1.5(106) ESAL pt=1.8;R=95%;S0=0.35 Granular base modulus, E2 = K1-K2, where K1 = 7000 and K2 = 0.6 Base is expected to be exposed to moisture levels approaching saturation for 2% of the time.

Question 2:

Design a flexible pavement overlay using the AASHTO method for a 5-year old pavement structure consisting of 5.75 inches of HMA and 23 inches of granular base, placed on a silty clayey sand subgrade. The future traffic to be sustained over the next five years will be 2.1(106) ESAL.     Deflection testing conducted in October at a temperature of 68°F, using a load of 18 kips, provided a mean surface deflection of 0.191349 inches centred under the 5.9-inch radius loading plate and 0.022955 inches at a distance of 48 inches from the centre of the loading plate. Assume m2 = 1.10 due to contamination of the granular base with fines. Use p1 = 4.2, pt= 1.5, R=95% reliability and assume a standard deviation of 0.49.

Question 3: 

a)Using the PCA method, design the minimum slab thickness (to the nearest 1⁄2 inch) required for a 4-lane divided major highway (2 lanes in each direction separated by a grass median). Design a rigid concrete pavement with doweled joints and with concrete shoulders to be placed on a 9-inch thick untreated granular subbase which overlays a clay subgrade having a k-value of 100 pci. Modulus of rupture for the concrete is 650 psi. Design period = 20 years; current ADT is 13,500; annual growth rate is 3.5%; and ADTT = 20%.

b)Design the welded wire mesh reinforcement, tie bars, dowels and joints, and shoulders required if this pavement is to be a jointed reinforced concrete pavement with a lane width of 12 ft. Use a maximum allowable joint opening of 0.25 inches for a doweled joint.


Related Discussions:- Aashto method

A concrete compression machine, Question In a concrete compression test , ...

Question In a concrete compression test , usually 150mmx150mmx150mm concrete cube examples are used for testing. Why isn't 100mmx100mmx100mm concrete cube samples used in test in

What is over vibration of fresh concrete, Q. What is Over vibration of fres...

Q. What is Over vibration of fresh concrete? For proper compaction of concrete by immersion vibrators, vibrating part of the vibrators must be completely inserted into the conc

Grouting in segmental linings in tunnels, Q. Grouting in segmental linings ...

Q. Grouting in segmental linings in tunnels? Grouting is typically carried out under pressure in segmental linings at the time of tunnel construction due to the below reasons:

Explain the analysis of singly reinforced rectangular beams, Explain the An...

Explain the Analysis of Singly Reinforced Rectangular Beams: 1. Determine the area of steel reinforcement, As. Multiply the number of bars by the area of each bar. 2. Calcul

Show suspended impurities in water, Q. Show Suspended Impurities in water? ...

Q. Show Suspended Impurities in water? The solid particles which are dispersed in water are referred as suspended Impurities. These are microscopic as under-

Finite Element Analysis- MATLAB problem, I am currently enrolled in a gradu...

I am currently enrolled in a graduate Civil Engineering course in Finite Element Analysis. The final assignment and project both deal with coding in MATLAB and I am having great di

Explain detention or retention ponds - hydrology, Explain Detention or Rete...

Explain Detention or Retention Ponds Detention/Retention Ponds: Designed to reduce and contain the peak runoff from developed areas (more impervious). Attempt to limit the runo

. determine the permeability of the aquifer, An unconfined aquifer is calle...

An unconfined aquifer is called to be 32 m thick below the water table. A constant discharge of 2 cubic metres per minute is pumped out of the aquifer by a tubewell till the water

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd