Aashto method, Civil Engineering

Assignment Help:

Question 1: A stationary 40 kN single axle load (applied on a circular contact area of radius = 152 mm = 6") is applied to each of the flexible pavement structures indicated below. Assuming linear elastic behaviour and no edge effects, use KENLAYER to determine for the two pavement systems given below:

a.  total maximum surface deflection of the pavement system;

b.  horizontal strain at the bottom of the HMA layer; and,

c.  vertical stress on the top of the subgrade.

Pavement systems:

i)  150 mm of HMA with 3,500 MPa modulus; placed directly on a sandy subgrade with 75 MPa modulus.

ii)  75 mm of HMA with 3,900 MPa; 200 mm of granular base with 150 MPa modulus; and clay subgrade with 40 MPa modulus.

2.) Assuming the HMA is the Asphalt Institute "standard mix", use both the Asphalt Institute and Shell methods (at 95% reliability) to predict the failure mode by either fatigue or rutting, and estimate the limiting number of load repetitions to achieve this failure mode for the two pavement systems described in Problem 1.

3.) Using the AASHTO method, design a flexible pavement system consisting of HMA and granular base placed on the subgrade described in Table 3.1 below, for the following conditions:

5-year predicted design traffic = W18 = 1.5(106) ESAL pt=1.8;R=95%;S0=0.35 Granular base modulus, E2 = K1-K2, where K1 = 7000 and K2 = 0.6 Base is expected to be exposed to moisture levels approaching saturation for 2% of the time.

Question 2:

Design a flexible pavement overlay using the AASHTO method for a 5-year old pavement structure consisting of 5.75 inches of HMA and 23 inches of granular base, placed on a silty clayey sand subgrade. The future traffic to be sustained over the next five years will be 2.1(106) ESAL.     Deflection testing conducted in October at a temperature of 68°F, using a load of 18 kips, provided a mean surface deflection of 0.191349 inches centred under the 5.9-inch radius loading plate and 0.022955 inches at a distance of 48 inches from the centre of the loading plate. Assume m2 = 1.10 due to contamination of the granular base with fines. Use p1 = 4.2, pt= 1.5, R=95% reliability and assume a standard deviation of 0.49.

Question 3: 

a)Using the PCA method, design the minimum slab thickness (to the nearest 1⁄2 inch) required for a 4-lane divided major highway (2 lanes in each direction separated by a grass median). Design a rigid concrete pavement with doweled joints and with concrete shoulders to be placed on a 9-inch thick untreated granular subbase which overlays a clay subgrade having a k-value of 100 pci. Modulus of rupture for the concrete is 650 psi. Design period = 20 years; current ADT is 13,500; annual growth rate is 3.5%; and ADTT = 20%.

b)Design the welded wire mesh reinforcement, tie bars, dowels and joints, and shoulders required if this pavement is to be a jointed reinforced concrete pavement with a lane width of 12 ft. Use a maximum allowable joint opening of 0.25 inches for a doweled joint.


Related Discussions:- Aashto method

Non destructive inspection steel/cast iron substructure, Explain the Non De...

Explain the Non Destructive Inspection Steel/Cast Iron Substructures Some of the structural defects in steel structures may not be visible during visual inspection. In that eve

Explain the process of directed track maintenance, Q. Explain the process o...

Q. Explain the process of Directed Track Maintenance? DTM is a method to maintain the track is directed every day and not as a prescribed routine. DTM essentially consists of n

M, symbols of electrical layout

symbols of electrical layout

Planning stage of the audit, Materiality is used only at the planning stage...

Materiality is used only at the planning stage of the audit. Ans: I disagree with the statement because: When planning the audit, the auditor considers what would make the fi

State the term - post-tensioned concrete, State the term - Post-tensioned c...

State the term - Post-tensioned concrete In Post-tensioned concrete construction, as shown in Figure,  tendons are placed inside concrete and stretched after concrete has attai

State the volume change from the plastic limit, The plastic limit and liqui...

The plastic limit and liquid limit of a soil are 33% and 45% respectively. The percentage volume change from the liquid limit to the dry state is 36% of the dry volume. Likewise, t

Foundation, Explain briefly shallow foundation?

Explain briefly shallow foundation?

Road and traffic engineering(signal timing design), what are the basic assu...

what are the basic assumption of traffic flow model and capacity model used in signal timing design ? discuss

Explain the terms void ratio, (a) Distinguish among Black cotton soil and L...

(a) Distinguish among Black cotton soil and Laterite from an engineering point of view. (b) Explain the terms 'Void ratio', 'Degree of saturation' and 'Water content', define th

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd