Review the Scenario and the addenda items detailed below. ODHS selected the Worldview Globalcom product for implementation in the E-mail Upgrade Project.

The project was accomplished in 14,960 hours versus the planned 12,000 hours, at a total cost of 1.56M versus the planned 1.25M over a ten month (versus nine month planned) schedule.

The Worldview vendor team had five key deliverables in the project, one of which was delivered 30 days late and another 10 days early.

The Ohio Department of Corrections, as a result of watching this effort, is deploying the Globalcom product for their organization.

Users report that they are very happy with the new e-mail system.

Mahoning County's infrastructure was too old to support the new e-mail system; they are being migrated next month as a separate project.

The Worldview contract was completed within established cost.

The Globalcom product's spam filter requires a different network configuration than is currently in place for the network.

The project team suffered from a 20% turnover rate during the life of this project, and exit interviews reveal salary was the overall cause.

Develop a Lessons Learned document for the Worldview project with these specific action items:

Write three project success criteria that would have been included in the charter-you may use or reference the project objectives you wrote in Unit One. Explain your criteria.

Using the addenda items detailed above in addition to information you creatively develop, write your lessons learned based on the criteria and the three components of cost, schedule, and performance (you may use these as individual sections of your paper). Note, not all the addenda items may even be pertinent.

Answer the following in a summarizing, final page:

Was the project a success? Why or why not?

If not, were portions of the project a success, and what was the impact of those success areas on the overall determination of project success?

Reference no: EM13797573

Questions Cloud

What methods evaluating project management context : What methods would you use for evaluating your listed criteria in a project management context
Assignment self-management behavioral contract : Individual Assignment Self-Management Behavioral Contract
Estimate the magnitude of each elemental error : The transducer is chosen to measure a nominal pressure of 500 cm H2O. The ambient temperature is expected to vary between 18° and 25°C during tests. Estimate the magnitude of each elemental error affecting the measured pressure
Delineating the significance of the documents : Using 750-1,000 words, create a chronological narrative delineating the significance of the documents/events listed below that impacted the evolution of the United States Constitution.
Write three project success criteria : Write three project success criteria that would have been included in the charter-you may use or reference the project objectives you wrote in Unit One. Explain your criteria.
Example of an act of government : Which of the following is an example of an act of government?
Describing and analyzing the events : Create a chronological narrative of 750-1,000 words describing and analyzing the events that impacted the process of Arizona becoming a state. Include the key events from the following periods in Arizona history:
Explain concept of human diversity and cultural competence : Explain the concept of human diversity and cultural competence
Laid down rules in the discharge of duties : In 2-3 pages answer the following: Do you think that public administrators should be restricted to only laid down rules in the discharge of their duties as espoused by Max Weber or should they have some amount of discretion.

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd