Write a status report - indication of status of the project

Assignment Help Project Management
Reference no: EM131586934

Question:

Assume you are the project manager for a software company and your team is in charge of delivering an update to tax preparation software for the next tax season. The project team has ten software developers working together, but located across the country.

You have the following information about the project, and need to provide a status to the sponsors.

New items you learned this month about the project:

There is a three day weekend in the coming month.

Nine of the developers are on track to finish their tasks two weeks early.

One software developer took the recently announced "early retirement" package, and is leaving in one week. He is confident he will be able to finish his piece of the work before he leaves.

It is hurricane season in Florida, where three of the developers are located.

The developer who is retiring is the only person who knows how to get approval for the final product from the IRS.

The project costs are under budget and there has been no need for overtime.

Write a one page status report (excluding the title page) to the sponsors providing a clear indication of status of the project (suggestion: use green, yellow, or red for status). Students are welcome to copy the boxes below into their assignment.

Green

Yellow

Red

The sponsors also like to only know the two most important risks, and what could be done to mitigate the risk if it happens. The conclusion of the status report should include a paragraph that describes any requests for additional resources, if they are necessary.

The best status reports use bullets, memos or templates since they provide an at a glance status. If you use a template or memo you can create your own or find one from a respected source that meets the above objectives. If you use a template/memo from another source, you must cite the source in a reference page. In addition, you do not need to use any scholarly sources; however, if a reference is used it must be cited and included on a separate references page. Your paper must be formatted according to APA style guidelines as outlined in the Ashford Writing Center.

Verified Expert

Report for update in tax preparation software has been generated and circulated to the sponsors, with greetings. Current scenario of the team has been taken care while preparing the report. A helpful and healthy environment has been the primary concern while preparing this report. Possible risk and its solution have been discussed in the above paragraph.

Reference no: EM131586934

Questions Cloud

Briefly explain the sunk cost fallacy : ECO5000 Assessment Questions/Problems. An ice cream factory has set up shop in town. Briefly explain the sunk cost fallacy
Characteristics of a competitive market : Compare and contrast the characteristics of a competitive market, monopoly, monopolistic competition, and oligopoly.
Write out the first several terms of the given sequence : For each of the following closed forms, write out the first several terms of the sequence (at least five) and use this to create a recursion for the sequence.
Profit-maximizing price per drug treatment : Suppose that the marginal cost per drug treatment is constant at $20. What is the profit-maximizing price per drug treatment?
Write a status report - indication of status of the project : Write a one page status report (excluding the title page) to the sponsors providing a clear indication of status of the project
Define how you would monitor the effectiveness of your plan : Define how you would monitor the effectiveness of your plan while also setting new goals for the next influenza season.
Create a class called salaried that is derived from employee : Create a class called Salaried that is derived from Employee. Create a class called Hourly that is also derived from Employee.
How will price and output in this industry adjust : What will happen to the number of spinach growers in the long run? How will price and output in this industry adjust in the long run?
What are the types of cost reimbursable contracts : What are the types of Cost Reimbursable contracts? Describe the benefits of using these types of contracts .

Reviews

Write a Review

Project Management Questions & Answers

  Identify different types of intentional respondent error

Identify different types of intentional respondent error and the controls used to minimize them.- Identify different types of unintentional respondent error and the controls used to minimize them.

  What impact will higher visibility have on the firm

What impact will higher visibility have on the firm? Would it be difficult to get a high search engine ranking for a company that sells e-books?

  Develop a list of quality standards that you could use

Assume that your organization wants to hire new instructors for your project management course. Develop a list of quality standards that you could use in making this hiring decision. Suppose that some current instructors do not meet these standards. ..

  Determine the critical path and identify the activities

Develop an estimated duration for each activity and determine the critical path and identify the activities that make up the critical path.

  Contract type for product or service purchase

Which contract type is the most appropriate for the product or service purchase?

  How conflict can interfere with the goals of a project team

Define the term Conflict and describe how conflict can interfere with the goals and objectives of a project team. How, as the project manager, do you recognize Team Conflict(s)?

  Question 1the person who wishes to share information with

question 1the person who wishes to share information with someone else is known as the .answer

  What is the theoretical minimum number of workstations

Draw a precedence diagram of this operation. -  Given the demand, what is the cycle time for this operation? - What is the theoretical minimum number of workstations?

  Custom decision support system for an international airline

ITEC 841 : PROJECT MANAGEMENT - How do the Consultants feel about this project? In your experience, how would they rate the project in terms of priority for the Client?

  Project selection explaineddo i have to do a cash flow and

project selection explaineddo i have to do a cash flow? and how? what should i recommend for john ? can you help me

  What type of training did you receive in order to perform

What type of training did you receive in order to perform your job?- Did you receive training on statutes such as ADA, FMLA, ADEA, and Title VII?

  What are the different types of adoption

Based on the text's discussion, what are the different types of adoption? What are the issues involved with a transracial adoption?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd