Problem
Project name: Home theater systems set up. Duration of project 6 weeks. Project cost $100,000.
Experience from past project document suggests a 30% likelihood that the project will face problems which would delay duration by 2 weeks and would increase the project cost by $30,000. In this scenario, by increasing the project staff by 30% for an additional cost of $20,000, the likelihood of project facing problems would be reduced to 10%, and the delay and cost to 1 week and $10,000, respectively. The project has limitation that it cannot go over budget by more than 10%.
1) Based on above information, how to create decision tree? 2) Would you suggest to increase the size of the project staff? Why or why not?
Create a project schedule and align resources, Analyze project schedule and resource allocation
Write a report on Managerial Roles and Gap Analysis
Questionaire on Project Management
Describe the market growth rate for product and service.
Design an online system for the human resources department to manage available job positions.
How does a project risk management approach pro-vide an early warning signal for impending problems or issues
Calculate the payoff and the profits for investments
Describe the features or characteristics of your product or service.
Write paper on Inventory Management System.
Analysis of the overall project risk
Evaluate the usefulness of ROCE
Distribution strategy and project management
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd