Work breakdown structure-activities for cell phone design

Assignment Help Operation Management
Reference no: EM131192559

You work for Nokia in their global cell phone group. You have been made project manager for the design of a new cell phone. Your supervisors have already scoped the project so you have a list showing the work breakdown structure and this includes major project activities. You must plan the project schedule and calculate project duration. Your boss wants the schedule on his desk tomorrow morning!

You have been given the information below. It includes all the activities required in the project and the duration of each activity. Also, dependencies between the activities have been identified. Remember that the preceding activity must be fully completed before work on the following activity can be started.

Work Breakdown Structure and Activities for the Cell Phone Design Project:

Major Subprojects / Activites - Activity Identification - Dependency - Duration (weeks)

Product Specifications (P)

- Market research P1 - 2

- Overall Product Specificatios P2 P1 4

- Hardware P3 P2 5

- Software P4 P3 5

Supplier Specificatios (S)

- Hardware S1 P4 5

- Software S2 P4 6

Product Design (D)

- Battery D1 S1 1

- Display D2 S1 2

- Camera D3 S1 1

- Outer Cover D4 D1,D2,D3 4

Product Intergration (i)

- Hardware i1 D4 3

- User Interface i2 D2 4

- Software coding i3 i2 4

- Prototype Testing i4 i1,i3 4

Subcontracting (V)

- Suppliers Selection V1 S1,S2 10

- Contract Negotiation V2 i4,V1 2

Your project is divided into five major subprojects. Subproject “P” involves developing specifications for the new cell phone. Here decisions related to such things as battery life, size of the phone, and features need to be made. These details are based on how a customer uses the cell phone. These user specifications are redefined in terms that have meaning to the subcontractors that will actually make the new cell phone in subproject “S” supplier specifications. These involve engineering details for how the product will perform.

The individual components that make up the product are the focus of subproject “D.” Subproject “I” brings all the components together, and a working prototype is built and tested.

Finally in subproject “V,” suppliers are selected and contracts are negotiated.

1. Draw a project network that includes all the activities. Question 1, use shapes, lines word art, text boxes, whatever you can to make it look good in excel

2. Calculate the Early/Late start and Early/Late finish times for each activity and determine the minimum number of weeks for completing the project. Find the activities that are on the critical path for completing the project in the shortest time. Question 2, can be done in either excel or word

3. Identify slack in the activities not on the project critical path. Question 3, can be done in either excel or word

Reference no: EM131192559

Questions Cloud

Customer loyalty can be powerful competitive advantage : Customer loyalty can be a powerful competitive advantage. And customer loyalty is more than repeat purchasing. Customers who are loyal tend to buy more over time and, more importantly, tend to recommend a company to their family, friends, and colleag..
Most significant or descriptive home parameters : For this discussion, identify what you consider to be the three most significant or descriptive home parameters (that is, price mean, price mode, home size mean, home size mode, and so on) to give your clients an understanding of the Boca market, and..
Define the leader and manager approach to solving dilemma : Juan Para hit the snooze alarm for the third time, but he knew he could never go back to sleep. Rubbing his eyes and shaking off a headache, Para first checked his IPHONE and read an urgent message from his boss, explaining that Jack Nixon, chief sec..
Calculating maintenance cost and labor cost : A machine that produces a certain piece must be turned off by the operator after each piece is completed. The machine "coasts" for 15 seconds after it is turned off, thus preventing the operator from removing the piece quickly before producing the ne..
Work breakdown structure-activities for cell phone design : You work for Nokia in their global cell phone group. You have been made project manager for the design of a new cell phone. Your supervisors have already scoped the project so you have a list showing the work breakdown structure and this includes maj..
Most important factor contributing to motivation : Why do you think making progress ranks as the most important factor contributing to motivation according to a recent study? How can managers provide a sense of progress for employees working on long-range projects that might not show results for mont..
What specific customer service measures : Describe the advantages of using a balanced scorecard to measure and control organizational performance. Suppose you created a balanced scorecard for Walmart. What specific customer service measures would you include?
Expansion project-requires an initial fixed asset investment : Down Under Boomerang, Inc., is considering a new three-year expansion project that requires an initial fixed asset investment of $2.79 million. The fixed asset will be depreciated straight-line to zero over its three-year tax life, after which it wil..
Calculate the project internal rate of return : A private school is considering the purchase of six school buses to transport students to and from school events. The initial cost of the buses is $600,000. The buses would be purchased at the beginning of the project (i.e., in year 0), and all reven..

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd