Problem 1.A project in its 26th week has an actual cost of $250,000. It was scheduled to have completed $325,000 worth of work at that point in the project. For the work performed to date, the budgeted value is $300,000.  The project has a total budget of $1,500,000.  What are the cost and schedule variances for the project? What are the SPI and CPI?  Assuming that both schedule and cost variances will affect the remaining work, what is the EAC?

a.       CV =

b.      SV =

c.       SPI =

d.      CPI =

e.      EAC =

Problem 2. A project has just completed its 87thtask of a total of 150 tasks in its project plan. The project has a total budget of $1,500,000.  It was scheduled to have spent $500,000 at this point in the plan, but has actually spent only $400,000. The project manager estimates that the value of the work actually finished is $300,000.   What are the spending and schedule variances for the project? What are the SPI and CPI?  What is the EAC, assuming the remaining work will be completed as budgeted?  Is this likely?

a.       CV =

b.      SV =

c.       SPI =

d.      CPI =

e.      EAC =

Problem 3. The following project is at the end of its 6th week. Find the cost and schedule variances. Also find the CPI and SPI. Then find the critical ratio of the project using earned value calculations. Finally, calculate the EAC for the project by at least two different methods.

Activity

Predecessor

Duration (wks)

Budget  at Completion    ($)

Actual Cost ($)

%Complete

a

-

2

300

400

100

b

a

3

200

250

100

c

b

3

300

300

100

d

b

5

600

200

30

e

c,d

4

400

-

0

a.       CV =

b.      SV =

c.       CPI =

d.      SPI=

e.      CR=

f.        EAC=

Problem 4. Answer the questions for the following case:

Stoneworth Paving Company specializes in highway paving jobs for state of Virginia. When the State first awarded Stoneworth the contract, they stipulated a 1% penalty for each week Stoneworth was late on a completion date. Preston Flintrock, the project coordinator for Stoneworth, began to notice that the last two jobs were three weeks late, and the paving job that was due to be completed in the next two weeks was behind schedule. When Preston went in the field to investigate, he found the job to be understaffed, supplier delays, and a high work rejection/repaving needed. As a result, Preston decided to establish a better system of project control and present it to the boss.

a. If you were Preston, what characteristics would you look for in a new control system? Explain.

b. Will a new control system be adequate for the problem? Explain.

Reference no: EM132492341

Questions Cloud

Prepare a record the correct letter increase to bank balance : Prepare a record the correct letter increase to bank balance, decrease to bank balance,increase to company cash balance, decrease to company cash balance
What are the spending and schedule variances for the project : What are the spending and schedule variances for the project? What are the SPI and CPI? What is the EAC, assuming the remaining work will be completed as budge
What value difference add to your educational experience : After learning more about what GCU is all about by reading the GCU Doctrinal Statement and Christian Identity and Heritage, how do you think GCU's Christian.
What would tell the investors about investing in the stock : Assuming CAPM is correct, what should be the price of the stock? what would you tell the investors about investing in the stock?
Will a new control system be adequate for the problem : What characteristics would you look for in a new control system and Will a new control system be adequate for the problem? Explain
Break even for the increase in machine expenses : What is the minimum change in dollar sales needed to break even for the increase in machine expenses?
What is the break-even level in dollar : If Firm B has a total fixed cost of $ 450,000 to produce cracker, a contribution margin percentage of 30%, and a required profit percentage of 10%.
Produce new and improved goods for apple customers : Which entity is likely to have more outdated capital and capital in need of repair or replacement? Why? Explain in detail.
Annual information about a hypothetical country : Given the following annual information about a hypothetical country, answer questions a through d.

Reviews

Write a Review

Applied Statistics Questions & Answers

  What is the procedure for using mean and median

Will the random variable be discrete, continuous, or neither? How do you know and will the data be qualitative or quantitative? How do you know?

  What is the mean of sampling distribution of means

The average time scheduled for a doctor's visit is 25 minutes with a standard deviation of 22 minutes.  A researcher uses a sampling distribution made up of samples of size 271.  According to the Central Limit Theore, what is the mean of sampling dis..

  Conduct the appropriate statistical test using spss

Pennsylvania State University, USA, AEE 521 Basic Applied Data Analysis in Agricultural and Extension Education Assignment Help and Solutions

  A friend has offered to play a gambling game

A friend has offered to play a gambling game with you that involves flipping a coin that he has provided. Since a flip of heads will be to his advantage, you want to test the coin for fairness before you begin to play. Your friend is willing to..

  The bad debt ratio for a financial institution

The bad debt ratio for a financial institution is defined to be the dollar value of loans defaulted divided by the total dollar value of all lonas made. A random sample of seven Ohio banks is selected. The bad debt ratios (written as percentages) for..

  Draw an updated process map

AYN443 - Electronic Commerce Cycles MYOB Assignment. Identify the major 2 control issues and suggest a solution. Your solution should state what control activity(s) it uses (See Lecture 3). Draw an updated Process Map with your solutions included

  What is the critical path

What is the critical path? Which activity (activities) have the biggest slack? How many weeks of slack does the activity with the biggest slack have?

  For each fund calculate cumulative monthly return

For each fund calculate cumulative monthly return from first observation available to the last observation available

  Project on regression analysis

Your dream home is a 2800 square foot home that you had designed especially for your family. For years, you have had the plans for your dream home; however, you have been looking for that perfect neighborhood in which to build this home

  Find the following area under the standard normal curve

Find the following area under the standard normal curve: to the right of z = 2.20; ie, P(z > 2.20) = ?

  The state university of new jersey

One measure of the risk or volatility of an individual stock is the standard deviation of the total return (capital appreciation plus dividends) over several periods of time. Al though the standard deviation is easy to compute, it does not tak..

  Prepare a bar graph that displays the number

Create the graphic displays based on the data file - Prepare a bar graph that displays the number of patients by age of diagnosis

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd