Who is the best person qualified to make functional estimate

Assignment Help Project Management
Reference no: EM131860281

Assignment

Case Study: CAPITAL INDUSTRIES

In the summer of 1976, Capital Industries undertook a material development programto see if a hard-plastic bumper could be developed for medium-sized cars.By January 1977, Project Bumper (as it was called by management) had developeda material that endured all preliminary laboratory testing.

One more step was required before full-scale laboratory testing: a three-dimensional stress analysis on bumper impact collisions. The decision to performthe stress analysis was the result of a concern on the part of the technical communitythat the bumper might not perform correctly under certain conditions. Thecost of the analysis would require corporate funding over and above the originalestimates. Since the current costs were identical to what was budgeted, the additionalfunding was a necessity.

Frank Allen, the project engineer in the Bumper Project Office, was assignedcontrol of the stress analysis. Frank met with the functional manager of the engineeringanalysis section to discuss the assignment of personnel to the task.

Functional manager: "I'm going to assign Paul Troy to this project. He's a newman with a Ph.D. in structural analysis. I'm sure he'll do well."

Frank Allen: "This is a priority project. We need seasoned veterans, not newpeople, regardless of whether or not they have Ph.D.s. Why not use some otherproject as a testing ground for your new employee?"

Functional manager: "You project people must accept part of the responsibilityfor on-the-job training. I might agree with you if we were talking about bluecollarworkers on an assembly line. But this is a college graduate, coming to uswith a good technical background."

FrankAllen: "He may have a good background, but he has no experience. He needssupervision. This is a one-man task. The responsibility will be yours if he fouls up."

Functional manager: "I've already given him our book for cost estimates. I'msure he'll do fine. I'll keep in close communication with him during the project."

Frank Allen met with Paul Troy to get an estimate for the job.

Paul Troy: "I estimate that 800 hours will be required."

Frank Allen: "Your estimate seems low. Most three-dimensional analyses requireat least 1,000 hours. Why is your number so low?"

Paul Troy: "Three-dimensional analysis? I thought that it would be a two-dimensionalanalysis. But no difference; the procedures are the same. I canhandle it."

Frank Allen: "O.K. I'll give you 1,100 hours. But if you overrun it, we'll bothbe sorry."

Frank Allen followed the project closely. By the time the costs were 50 percentcompleted, performance was only 40 percent. A cost overrun seemed inevitable.The functional manager still asserted that he was tracking the job andthat the difficulties were a result of the new material properties. His section hadnever worked with materials like these before.

Six months later Troy announced that the work would be completed in oneweek, two months later than planned. The two-month delay caused major problemsin facility and equipment utilization. Project Bumper was still paying foremployees who were "waiting" to begin full-scale testing.

On Monday mornings, the project office would receive the weekly labormonitor report for the previous week. This week the report indicated that the publicationsand graphics art department had spent over 200 man-hours (last week)in preparation of the final report. Frank Allen was furious. He called a meetingwith Paul Troy and the functional manager.

Frank Allen: "Who told you to prepare a formal report? All we wanted was ago or no-go decision as to structural failure."

Paul Troy: "I don't tum in any work unless it's professional. This report will bedocumented as a masterpiece."

Frank Allen: "Your 50 percent cost overrun will also be a masterpiece. I guessyour estimating was a little off!"

Paul Troy: "Well, this was the first time that I had performed a three-dim dimensionalstress analysis. And what's the big deal? I got the job done, didn't IT'

Questions:

1. Who is the best person qualified to make functional estimates?
2. Can this task be delegated?
3. Should the estimating of this task have been delegated?
4. Should Paul Troy have been delegated the responsibility for theestimate?
5. Should Frank Allen have sensed a communication problem between Paul Troy and the functional manager?
6. Should Frank Allen have tracked the project more closely because of the above-mentioned problems?
7. Does Paul Troy appear to realize that there are also time and cost constraints on a project?
8. Is it beneficial for project office personnel to know the man­ hour estimates?

Reference no: EM131860281

Questions Cloud

Supervising the employees of its subsidiaries : Was Union Carbide Corporation responsible for training and supervising the employees of its subsidiaries?
Explain how does logistics fit into a supply chain model : Explain How does logistics fit into a supply chain model? In general, should LUML be looking at the possible use of Supply Chain Facilitators?
How are the risks of foreign investment in a plant : How are the risks of foreign investment in a plant or production facility greater than those associated with exporting or licensing?
Chemical properties of volatile organic compounds : What are the other chemical properties of Volatile Organic Compounds that make them an especially potent class of toxic chemicals?
Who is the best person qualified to make functional estimate : Who is the best person qualified to make functional estimates? Should Paul Troy have been delegated the responsibility for theestimate?
Purchase fractional amounts of goods : Mona's preferences for food, F, and clothing, C, are derived by a utility function U(F,C)=FC. Food costs $1 a unit and clothing costs $2 a unit.
Write the equation for petra budget line : Write the equation for Petra's budget line.
Provide definition of opportunity cost : Discuss what the opportunity cost of attending college is for you, noting that the concepts of opportunity costs and explicit monetary costs are not the same.
Discuss about the marketing plan and sales strategy : This assignment consists of two (2) sections: a marketing plan and sales strategy, and a marketing budget. Note: You must submit both sections as separate.

Reviews

Write a Review

Project Management Questions & Answers

  Show healthcare management quality practices

How would applying the core values and concepts of the Baldridge Health Care Criteria for performance Excellence improve health care quality

  Details regarding production management1 what are the steps

details regarding production management1. what are the steps that an organization must follow to implement a tqm

  How would you advise mike and iris to proceed with worksheet

If you could have spoken to Mike Edwards before he distributed the asset valuation worksheets, what advice would you have given him to make the consolidation process easier?

  Write an equation that expresses retail price r

If the markup policy of the store is assumed to be linear, write an equation that expresses retail price R in terms of cost C.

  Creating a closeout document and a lessons-learned document

For your capstone project, create a closeout document. The document should contain the sections - Project description, Acceptance criteria, including metrics, such as schedule, budget, and scope performance

  An adaptive project management life cycle mode

Explain the similarities and differences between an adaptive project management life cycle model and an extreme project management life cycle model.

  Principles of project managementperhaps more than any other

principles of project managementperhaps more than any other of the knowledge areas integration management is of primary

  What does the ms project output file look like

Using the following data, enter the various tasks and create a Gantt chart using MS Project. Assign the individuals responsible for each activity.

  Summarise the net cash flows for each opportunity

Summarise the net cash flows for each opportunity for a period of 5 years. For simplification purposes, ignore the effect of taxes (both corporate and income tax).

  Sustaining leader communicationformulating answers for

sustaining leader communicationformulating answers for these questions. not too sure how to approach this.1. explain

  Construction of a shopping center

A principal hired a mortgage banking firm to obtain a loan commitment of $10,000,000 from an insurance company for the construction of a shopping center.

  Explain net resent value npv

Explain Net resent value(NPV),Return on investment(ROI),pay back period(PBP

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd