Who considers his organization as strictly support

Assignment Help Project Management
Reference no: EM132407813

On November 15, 1998, the Department of Energy Resources awarded Telestar a $475,000 contract for the developing and testing of two waste treatment plants. Telestar had spent the better part of the last two years developing waste treatment technology under its own R&D activities. This new contract would give Telestar the opportunity to "break into a new field" -that of waste treatment.

The contract was negotiated at a firm-fixed price. Any cost overruns would have to be incurred by Telestar. The original bid was priced out at $847,000. Telestar 's management, however, wanted to win this one. The decision was made that Telestar would "buy in" at $475,000 so that they could at least get their foot into the new marketplace.

The original estimate of $847,000 was very "rough" because Telestar did not have any good man-hour standards, in the area of waste treatment, on which to base their man-hour projections. Corporate management was willing to spend up to $400,000 of their own funds in order to compensate the bid of $475,000.

By February 15, 1999, costs were increasing to such a point where overrun would be occurring well ahead of schedule. Anticipated costs to completion were now $943,000, The project manager decided to stop all activities in certain functional departments, one of which was structural analysis. The manager of the structural analysis department strongly opposed the closing out of the work order prior to the testing of the first plant's high-pressure pneumatic and electrical systems.

Structures Manager: "You're running a risk if you close out this work order. How will you know if the hardware can withstand the stresses that will be imposed during the test? After all, the test is scheduled for next month and I can probably finish the analysis by then. "

* Revised, 2008.

Case Studies

Project Manager: "I understand your concern, but I cannot risk a cost overrun. My boss expects me to do the work within cost. The plant design is similar to one that we have tested before, without any structural problems being detected. On this basis, I consider your analysis unnecessary.

Structures Manager: "Just because two plants are similar does not mean that they will be identical in performance, there can be major structural deficiencies.

Project Manager: "I guess the risk is mine.

Structures Manager: "Yes, but I get concerned when a failure can reflect on the integrity of my department. You know, we 're performing on schedule and within the time and money budgeted. You're setting a bad example by cutting off our budget without any real justification.'

Project Manager: "I understand your concern, but we must pull out all the stops when overrun costs are inevitable. "

Structures Manager: "There's no question in my mind that this analysis should be completed. However, I'm not going to complete it on my overhead budget. I'll reassign my people tomorrow. Incidentally, you had better be careful; my people are not very happy to work for a project that can be canceled immediately. I may have trouble getting volunteers next time. "

Project Manager: "Well, I'm sure you'll be able to adequately handle any future work. I'll report to my boss that I have issued a work stoppage order to your department. "

During the next month 's test, the plant exploded. Post analysis indicated that the failure was due to a structural deficiency.

a. Who is at fault?

b. Should the structures manager have been dedicated enough to continue the work on his own?

c. Can a functional manager, who considers his organization as strictly support, still be dedicated to total project success?

Reference no: EM132407813

Questions Cloud

Creating business development plan : You will continue the process of creating a business development plan for your AMAZON company.
Business situations using predominant ethical theories : Analyze selected business situations using predominant ethical theories, such as utilitarian, Kantian, virtue ethics to guide ethical business decision making.
Reflection-reflect on what you have learned : Reflect on what you have learned in this course and program. Is there anything you would have liked to learn in this class or program that was not covered?
Describe the linkages of the work breakdown structure : Describe the linkages of the work breakdown structure and the time-phased budget to arrive at an earned value analysis.
Who considers his organization as strictly support : Can a functional manager, who considers his organization as strictly support, still be dedicated to total project success?
How does the merriam-webster definition of a project : How does the Merriam-Webster definition of a project compare and contrast with PMI's (Project Management Institutes) definition?
Changes in the external environment : Your readings this week identified some of the changes in the external environment that can provide business opportunity
Project management body of knowledge : What are the "triple constraint" in the PMBOK (Project Management Body of Knowledge)
Discuss an actual health care operations application : Discuss an actual health care operations application or vision of your application of a process design or redesign to improve quality healthcare

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd