Reference no: EM13899212
One Hour Loan offers customized loans. Customers call a toll free number with a specific loan request, and obtain a response within an hour. One Hour Loan’s business process includes five activities which must be conducted in the sequence described below:
Activity 1: Answer customer call and record key information (4 minutes)
Activity 2: Gather and format the information (obtain credit scores, organize customer needs) for analysis (5 minutes)
Activity 3: Analyze the information, check the credit worthiness, and decide the loan amount and APR to offer (7 minutes)
Activity 4: Perform final checks on the loan offer (2 minutes)
Activity 5: Call customer back with the new loan offer and close (4 minutes)
Three workers in a worker-paced line conduct the whole process. The assignment of tasks to workers is the following:
Worker 1 does Activity 1
Worker 2 does Activities 2 and 3
Worker 3 does Activities 4 and 5
What is the bottleneck of the process?
How much time will it take to process 100 loans, assuming the process starts with an empty production line?
What is the average labor utilization of the workers?
What are the direct labor costs for one loan application? Assume a wage rate of $20 per hour.
To increase the production rate, One Hour Loan is considering two alternatives:
Alternative I: Hire a new worker to help any one (and only one) of the workers without changing the tasks performed by each worker.
Alternative II: Redesign the assignment of tasks to workers, specifically re-assign Activity 2 from Worker 2 to Worker 1.
Suppose Alternative I is chosen. Which worker should the new employee assist?
What would be the costs of direct labor of one loan application for Alternative I?
What would be the direct labor costs for Alternative II?
Complete with gates earned value measurement rules
: What is the difference between percent complete and percent complete with gates Earned value (EV) measurement rules? What advantage does the latter have over the former?
|
Require re-baselining of the cost baseline
: Which of the following might require re-baselining of the cost baseline?
|
Capacity is measured in terms of what inputs
: In a restaurant, capacity is measured in terms of what inputs?
|
Identify errors and omissions in auditors report
: The following auditor’s report was drafted by a staff accountant of Nathan and Matthew, CPAs, at the completion of the audit of the comparative financial statements of Monterey Partnership for the years ended December 31, 2013 and 2012. Monterey is a..
|
Which worker should the new employee assist
: One Hour Loan offers customized loans. Customers call a toll free number with a specific loan request, and obtain a response within an hour. Suppose Alternative I is chosen. Which worker should the new employee assist? What would be the costs of dire..
|
Enterprise resource planning
: Respond to the following on Enterprise Resource Planning (ERP). What are the typical benefits of ERP? What are the disadvantages of ERP?
|
Does the general public seem to accept revenue management
: Airline passengers today stand in numerous lines, are crowded into small seats on mostly full airplanes, and often spend time on taxiways because of air-traffic problems or lack of open gates. Does the general public seem to accept revenue management..
|
What issues are involved in storage of pet supplies
: The Marketing Plan Coach software on the text website includes a sample marketing plan for Hillside Veterinary Clinic. Look through the “Marketing Strategy” section. To provide veterinary care to pets, Hillside needs to have a variety of medical supp..
|
Nevertheless be maintained at previous levels
: If the average amount of time a product goes without failing decreased by some amount, that product's availability could nevertheless be maintained at previous levels by __________ its __________.
|