Problem 1: Several team members are overallocated, and you want to see only their assignments in your schedule. Which feature can help you focus on those overallocations?
a. the Overallocation field
b. the Overallocated Resources filter
c. the Resource Graph
d. the Resource Usage view
Problem 2: You have numerous customized views to use with all your projects. What is the easiest way to ensure that these views are available to all your projects?
a. Turn on the Automatically add new views, tables, filters, and groups to the global option.
b. Nothing. Customized views are automatically available to all projects.
c. Copy each customized view to the global template via the Organizer.
d. In the Organizer, select all the customized views and then click Copy.
Problem 3: Nathan needs to overlap a task for 25% of its predecessor's duration. Which value must he enter in the link's Lag field to accomplish this?
a. 25%
b. -25%
c. -25
d. 25