Which testing company should be picked if the project manage

Assignment Help Project Management
Reference no: EM13774264

A Project Manager wants to pick the most efficient vendor to test a new prototype. He has previous experience with 3 testing companies. Prototype testing is a highly variable activity as shown in the table below. (HINT: For example, Company X completes testing in 40 hours in 60% of cases while it takes 90 hours in the remaining 40% of tests).


Company Probability Hours Required Cost / Hour 
X 60% 40 $12 
40% 90 
Y 10% 10 $11 
20% 20 
30% 60 
40% 100 
Z 50% 25 $10 
40% 90 
10% 200 

a. Which testing company should be picked if the Project Manager is primarily interested in completing the task in the shortest time?

b. Which testing company should be picked if the Project Manager is primarily concerned with completing the task for the lowest cost? 

Reference no: EM13774264

Questions Cloud

For any given level of output : For any given level of output:
A goatherd has the cost function : A goatherd has the cost function c(y) = 2y2, where y is the number of tubs of goat cheese she makes per month. She faces a competitive market for goat cheese,with a price of $40 a tub. How many tubs should she produce per month?
Burning the coke deposited on the catalyst particles : Burning the coke deposited on the catalyst particles generates all the heat necessary for catalytic cracking. Therefore, the coke burning rate is a critical parameter to control the rate of cracking. The composition of dry flue gas from the regenerat..
Suppose that the equilibrium nominal exchange rate : Suppose that the equilibrium nominal exchange rate is 130 Japanese yen to the U.S. dollar. If the Federal Reserve wishes to maintain an exchange rate of 140 Japanese yen to the U.S. dollar, it must meet the private excess ________ dollars in the fore..
Which testing company should be picked if the project manage : A Project Manager wants to pick the most efficient vendor to test a new prototype. He has previous experience with 3 testing companies. Prototype testing is a highly variable activity as shown in the table below. (HINT: For example, Company X complet..
Foreign-exchange markets and buys foreign currencies : If a central bank intervenes in the foreign-exchange markets and buys foreign currencies:
Fixed exchange rate and unrestricted capital flows : Suppose that a country has a fixed exchange rate and unrestricted (financial) capital flows. Which of the following would the country NOT experience?
Makes this event pareto optimal : Harry values a new jacket at $100 and buys it from Jenny at $80 (costing her $70 to produce it). Jim then offers Harry the same jacket at $60. Harry buys the jacket from Jim, and stops buying it from Jenny. Which of the following makes this event Par..
About a lingering recession : In 1992, thirst Bush administration was worried about a lingering recession. The administration announced that households would receive a reduction in their taxes for the year 1992. However, this was not accompanied by a reduction in tax rates, and t..

Reviews

Write a Review

Project Management Questions & Answers

  Contract type for product or service purchase

Which contract type is the most appropriate for the product or service purchase?

  Contemporary planning techniques reccomendation

Describe why the technique that would not work within your workplace and what steps would you recommend your manager to take to plan in his decision making

  Auto plant operations managementshow your thoughts about

auto plant operations managementshow your thoughts about the unique staffing training and motivational challenges that

  Calculate the expected time and variance of each activity

Calculate the expected time and variance of each activity and draw a network diagram and identify critical path and project completion time?

  How is the project doing

How is the project doing? Is it ahead of schedule or behind schedule and is it under budget or overbudget? Should you alert your senior management and ask for assistance

  Developing the work flow sequence

Develop the work flow sequence specified in the problem shown below. Do not consider any of the scheduling information provided below in your work.

  Project review or audit

Explain what are some reasons that the project review or audit does not focus on an individual's wrongdoing

  Matrix and projected project organization structure

Based on the facts in the case, do you believe that Rachel is working in a functional, a matrix, or a projected project organization structure?

  Expert response to project managementin my role as project

expert response to project managementin my role as project manager for my group called the the provision healthcare

  Project management managing stakeholder

project management managing stakeholder expectationsstakeholders may not communicate as frequently or politely as a

  Implementation of good disaster prevention procedures

A business disaster takes place when, despite the implementation of good disaster prevention procedures, normal business operations stop.

  Criteria for performance excellence improve care quality

How would applying the core values and concepts of the Baldridge Health Care Criteria for performance Excellence improve health care quality?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd