Which testing company should be picked if the project manage

Assignment Help Project Management
Reference no: EM13774264

A Project Manager wants to pick the most efficient vendor to test a new prototype. He has previous experience with 3 testing companies. Prototype testing is a highly variable activity as shown in the table below. (HINT: For example, Company X completes testing in 40 hours in 60% of cases while it takes 90 hours in the remaining 40% of tests).


Company Probability Hours Required Cost / Hour 
X 60% 40 $12 
40% 90 
Y 10% 10 $11 
20% 20 
30% 60 
40% 100 
Z 50% 25 $10 
40% 90 
10% 200 

a. Which testing company should be picked if the Project Manager is primarily interested in completing the task in the shortest time?

b. Which testing company should be picked if the Project Manager is primarily concerned with completing the task for the lowest cost? 

Reference no: EM13774264

Questions Cloud

For any given level of output : For any given level of output:
A goatherd has the cost function : A goatherd has the cost function c(y) = 2y2, where y is the number of tubs of goat cheese she makes per month. She faces a competitive market for goat cheese,with a price of $40 a tub. How many tubs should she produce per month?
Burning the coke deposited on the catalyst particles : Burning the coke deposited on the catalyst particles generates all the heat necessary for catalytic cracking. Therefore, the coke burning rate is a critical parameter to control the rate of cracking. The composition of dry flue gas from the regenerat..
Suppose that the equilibrium nominal exchange rate : Suppose that the equilibrium nominal exchange rate is 130 Japanese yen to the U.S. dollar. If the Federal Reserve wishes to maintain an exchange rate of 140 Japanese yen to the U.S. dollar, it must meet the private excess ________ dollars in the fore..
Which testing company should be picked if the project manage : A Project Manager wants to pick the most efficient vendor to test a new prototype. He has previous experience with 3 testing companies. Prototype testing is a highly variable activity as shown in the table below. (HINT: For example, Company X complet..
Foreign-exchange markets and buys foreign currencies : If a central bank intervenes in the foreign-exchange markets and buys foreign currencies:
Fixed exchange rate and unrestricted capital flows : Suppose that a country has a fixed exchange rate and unrestricted (financial) capital flows. Which of the following would the country NOT experience?
Makes this event pareto optimal : Harry values a new jacket at $100 and buys it from Jenny at $80 (costing her $70 to produce it). Jim then offers Harry the same jacket at $60. Harry buys the jacket from Jim, and stops buying it from Jenny. Which of the following makes this event Par..
About a lingering recession : In 1992, thirst Bush administration was worried about a lingering recession. The administration announced that households would receive a reduction in their taxes for the year 1992. However, this was not accompanied by a reduction in tax rates, and t..

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd