A Project Manager wants to pick the most efficient vendor to test a new prototype. He has previous experience with 3 testing companies. Prototype testing is a highly variable activity as shown in the table below. (HINT: For example, Company X completes testing in 40 hours in 60% of cases while it takes 90 hours in the remaining 40% of tests).

Company Probability Hours Required Cost / Hour 

  • X 60% 40 $12 

     40% 90 

  • Y 10% 10 $11 

             20% 20 
             30% 60 
             40% 100 

  • Z 50% 25 $10 

             40% 90 
             10% 200 

a. Which testing company should be picked if the Project Manager is primarily interested in completing the task in the shortest time?

b. Which testing company should be picked if the Project Manager is primarily concerned with completing the task for the lowest cost?

Reference no: EM13769868

Questions Cloud

Explain how each clue supports delgados inference : List 2 clues contained in the selection that support Pat Delgado's inference: Crop circles are created by extraterrestrials. Explain how each clue supports Delgado's inference.
Component of polluted air : Describe how these limestone objects are corroded by the sulfuric acid in polluted air. What chemical reaction is involved here?
Analyzes the climate change debate : Although there is a consensus among climate scientists that anthropogenic greenhouse gas emissions are contributing to global warming, an incident such as "Climate-Gate" indicates that there are those who are skeptical of the data and of the claim..
Fossil fuels for electricity generation : For this assignment, you will write a five- to eight-page paper on the pros and cons of an energy source that you believe has the most potential for widespread use as an alternative to fossil fuels for electricity generation.
Which testing company should be picked if the project manage : A Project Manager wants to pick the most efficient vendor to test a new prototype. He has previous experience with 3 testing companies. Prototype testing is a highly variable activity as shown in the table below. (HINT: For example, Company X complet..
Curb greenhouse gas emissions : Describe the economic impact of the law. Provide specific economic data from credible references.
Capital intensive or communication intensive : Green engineering has proven to be an obstacle to many industries. The reason is their misunderstanding of the potential benefits if properly implemented. In your opinion, would you classify green engineering as a quick fix program or a long-term ..
Additional financial analysis methods : Recommendations for proceeding and suggestion of two additional financial analysis methods which could be used to further support the decision.
Describe a place or environment where you perfectly content : Describe a place or environment where you are perfectly content. What do you do or experience there, and why is it meaningful to you?

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd