Which techniques to insure that projects meet the needs

Assignment Help Business Management
Reference no: EM131356502

Question 1
The first step in the project control process of the measurement and evaluation of project performance is to

Set a baseline plan
Determine the project objectives
Determine the project deliverables
Analyze the project budget
Review the project priority matrix

Question 2
The third step in the project control process of the measurement and evaluation of project performance is to:

Review the baseline plan with top management
Analyze inputs to the control system
Compare the plan against actual performance
Measure both progress and performance
Review spending with team members

Question 3
A project monitoring system involves all of the following except:

Determining what date to collect
Determining how, when, and who will collect the data
Adjusting the data
Analysis of the data
Reporting current progress

Question 4
The last step in the project control process of the measurement and evaluation of project performance is to:

Take appropriate action
Prepare a report to top management
Follow up on corrective action
Measure progress and performance
Review spending with team members

Question 5
The percent complete index that looks at percent complete in terms of actual amounts is calculated by which of the following?

EV/BAC
(EV-PV)/BAC
AC/EAC
(EV-AC)/BAC
(EV-PV)/EAC

Question 6
The second step in the project control process of the measurement and evaluation of project performance is to:

Review the baseline plan with top management
Analyze inputs to control system
Compare plan against actual
Measure progress and performance
Review spending with team members

Question 7
Small refinements that eventually build to be major changes are known as:
Project erosion
Scope creep
Specification adjustments
Specification refinements
Continuous improvements

Question 8
In monitoring project time (schedule) performance actual performance should be compared to:

Budgets for the current year
Top management's targets
Project network schedule derived from the WBS/OBS
Progress on similar past projects
Previous status reports

Question 9
Implementing closedown includes the following major activities except:

Getting delivery acceptance from the customer.
Shutting down resources and releasing to new uses.
Closing accounts and seeing all bills are paid.
E-mail the project team that the project is complete.
Creating a final report.

Question 10
In the Snapshot from Practice, New Balls Goes Flat in NBA, is an example of a project gone wrong when the _______ is/are not consulted.

Manufacture
Equipment and facilities managers
End-users
The Fans
Project manager

Question 11
__________ of lessons learned are designed to improve performance on current and future projects.

Retrospectives
Corrective action plans
Introspective
Culmination
Evolution

Question 12
Many projects will fail because of circumstances beyond the control of the project team is called:

Normal
Premature
Perpetual
Failed Project
Changed Priority

Question 13
The section of the final project report that new project teams are likely to find most useful is the:

Analysis
Recommendations
Classification of project
Lessons learned
Strategic objectives

Question 14
When the project may be completed early with some parts of the project eliminated this is considered to be ___________ closure.

Normal
Premature
Perpetual
Changed Priority
Failed Project

Question 15
Items technical in nature and focus on solutions to problems that surfaced would typically appear in the _____ section of the final project report.

Analysis
Recommendations
Classification of project
Lessons learned
Strategic objectives

Question 16
When a project may start with a high priority but see its rank erode or crash during its project life cycle as conditions change this is an example of:

Normal
Premature
Perpetual
Failed Project
Changed Priority

Question 17
Which of the following is responsible for the continued support of consistent application of selection criteria, standards, processes, training, and general assistance to project managers and continued improvement and use of best practices?

Portfolio Project Management
Project Office Management
Project Management Optimization
Project Priority Matrix Management
Resource Allocation Optimization

Question 18
Which of the following is not one of the techniques to insure that projects meet the needs of the organization?

Standards
Procedures
Accountability
Controls

Question 19
The use of an organization-wide project management system tailored to specific needs of the organization is established in which of the following Maturity Model Levels?

Ad Hoc Project Management
Formal Application of Project Management
Institutionalization of Project Management
Management of Project Management System
Optimization of Project Management System

Question 20
The importance of the increase in project oversight to today's project manager includes all of the following except:

Increase in expected profits from projects
Increased interest in supporting and helping the project manager
Impact on the environment in which the project will be implemented
Impact on how the project manager's performance will be measured
The reporting of project progress to an oversight group

Question 21
Which of the following is not one of the four performance goals measures in the scorecard model?

customer
internal
financial measures
industry standards
innovation and learning

Question 22
The first appearance of standard approaches to managing projects including scope statements and WBS occurs in which of the following Maturity Model Levels?

Ad Hoc Project Management
Formal Application of Project Management
Institutionalization of Project Management
Management of Project Management System
Optimization of Project Management System

Question 23
The focus is on continuous improvement through incremental advancements of existing practices and by innovations using new technologies and methods is established in which of the following Maturity Model Levels?

Ad Hoc Project Management
Formal Application of Project Management
Institutionalization of Project Management
Management of Project Management System
Optimization of Project Management System

Question 24
Which of the follow percentages is the authors' estimate of project-driven organizations that have been implementing some form of oversight for several years?

95%
90%
85%
80%
75%

Question 25
During which of the following phase gates would the question of "Are time, costs, and scope performances within acceptable limits?" be ed?

Proposal
Screening and selection
Implementation
Progress evaluation
Closure

Reference no: EM131356502

Questions Cloud

What specific behaviors do you want to increase or decrease : Select a goal-something you would like to change about yourself. Perhaps you would like to stop smoking, control drinking, improve study habits, manage time better, or change eating or exercise habits. It is critical that your goal be measurable, ..
What are the control limits for the range chart : A process that is considered to be in control measures an ingredient in ounces. Below are the last 10 samples (each of size n = 5) taken. What are the control limits for the range chart
What is the virtue that was demonstrated : PHI 208 Ethics and Moral Reasoning Text Book Mosser, K. (2013). Understanding philosophy - Find examples from literature or media sources, or from current or past history, that demonstrate both success and failure at demonstrating a virtue. In each..
Draw an edgeworth box with well-behaved preferences : The contract curve (with cA = 0.5) can be transformed into a utility possibilities frontier, as shown in Figure 3.2.3.5. Where would point Z (from the previous question) be on this graph? Explain why.
Which techniques to insure that projects meet the needs : Bus517- Which of the following is not one of the techniques to insure that projects meet the needs of the organization? Which of the following is not one of the four performance goals measures in the scorecard model?
Discuss about the domestic violence : you will move from simply discussing the issue to developing an updated essay that takes a clear stance on one aspect of your topic. The goal of this essay is to learn how changing the purpose of the writing (from informative to more argumentative..
What your factors and numbers mean to the company : At a minimum, an analysis should always include what the matrix means, why it is important to the company, and what your factors and numbers mean to the company.
Identify the specific techniques that frito-lay is using : What are the sources of pressure on firms such as Frito-Lay to reduce their environmental footprint? Identify the specific techniques that Frito-Lay is using to become a "green manufacturer
Discuss relative advantages of each of the billing system : Discuss the relative advantages of each of the billing systems mentioned in part a, from the standpoint of both the selling company and the customer.

Reviews

Write a Review

Business Management Questions & Answers

  Caselet on michael porter’s value chain management

The assignment in management is a two part assignment dealing 1.Theory of function of management. 2. Operations and Controlling.

  Mountain man brewing company

Mountain Man Brewing, a family owned business where Chris Prangel, the son of the president joins. Due to increase in the preference for light beer drinkers, Chris Prangel wants to introduce light beer version in Mountain Man. An analysis into the la..

  Mountain man brewing company

Mountain Man Brewing, a family owned business where Chris Prangel, the son of the president joins. An analysis into the launch of Mountain Man Light over the present Mountain Man Lager.

  Analysis of the case using the doing ethics technique

Analysis of the case using the Doing Ethics Technique (DET). Analysis of the ethical issue(s) from the perspective of an ICT professional, using the ACS Code of  Conduct and properly relating clauses from the ACS Code of Conduct to the ethical issue.

  Affiliations and partnerships

Affiliations and partnerships are frequently used to reach a larger local audience? Which options stand to avail for the Hotel manager and what problems do these pose.

  Innovation-friendly regulations

What influence (if any) can organizations exercise to encourage ‘innovation-friendly' regulations?

  Effect of regional and corporate cultural issues

Present your findings as a group powerpoint with an audio file. In addition individually write up your own conclusions as to the effects of regional cultural issues on the corporate organisational culture of this multinational company as it conducts ..

  Structure of business plan

This assignment shows a structure of business plan. The task is to write a business plane about a Diet Shop.

  Identify the purposes of different types of organisations

Identify the purposes of different types of organisations.

  Entrepreneur case study for analysis

Entrepreneur Case Study for Analysis. Analyze Robin Wolaner's suitability to be an entrepreneur

  Forecasting and business analysis

This problem requires you to apply your cross-sectional analysis skills to a real cross-sectional data set with the goal of answering a specific research question.

  Educational instructional leadership

Prepare a major handout on the key principles of instructional leadership

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd