Question: Consider the project network pictured in Figure. Assume that the times attached to each node are the means and the variances of the project completion times, respectively.

a. Identify all paths from nodes 1 to 6.

b. Which path is critical based on the expected completion times?

c. Determine the probability that the project is completed within 20 weeks assuming that the path identified in part (b) is critical.

d. Using independence of paths A-C-E and B-F-G only, recompute the answer to part (c).

e. Recompute the answer to part (c) assuming independence of the paths identified in part (a).

f. Which answer, (c), (d), or (e), is probably the most accurate?

1127_10-18.png

Reference no: EM131469606

Questions Cloud

Warehouse makes up a majority of the picking activity : In this profile, just a minority of the items in a warehouse makes up a majority of the picking activity, certain items in the warehouse tend to be requested to
Receipt of all materials coming into the warehouse : the orderly unloading and receipt of all materials coming into the warehouse,
What is the pert time briefly explain : Draw a network for this project and determine the critical path based on the most likely times by inspection.
How strategic framework analysis tools can be used : Demonstrate an awareness of how strategic framework analysis tools can be used to determine the effectiveness of ICT
Which path is critical based on the expected completion time : Consider the project network pictured in Figure. Assume that the times attached to each node are the means and the variances of the project completion times.
Avoid delegating projects to the people in their groups : Suppose the managers in your organization tend to avoid delegating projects to the people in their groups.
Less-expensive alternative to classroom training : Many organizations turn to e-learning as a less-expensive alternative to classroom training.
Compute the standard deviation of each of the activity times : Consider the project described in Problem. Suppose that the activity times are random variables with a constant coefficient of variation of 0.2.
Summarize how you would conduct a needs assessment : Is training the solution to this problem? How can you determine the need for training? Summarize how you would conduct a needs assessment.

Reviews

Write a Review

Engineering Mathematics Questions & Answers

  Develop an estimate of the number of fortune companies

A sample of 50 Fortune 500 companies (Fortune. April 14. 2003) showed that 5 were based in New York. 6 in California. 2 in Minnesota.

  What is the crsp

Focus on the daily log returns, in percentages, of EXXON-Mobil stock and the S&P composite index used in Example. Fit a BEKK(1,1) model to the innovations of log returns. Write down the fitted model and obtain mean, standard error, minimum, and ma..

  Maximize the angle theta subtended

"A painting in an art gallery has height h and is hung so that its lower edge is a distance d above the eye of an observer. How far from the wall should the observer stand to get the best view? (In other words, where should the observer stand so a..

  Write down a dual formulation of linear program

Write down a dual formulation of this linear program - describe how the dual formulation can be used to obtain a feasibility cut in the L-shaped method.

  Appropriate forecast model for the bank

Develop an appropriate forecast model for the bank to use to forecast Treasury note rates in the future and indicate how accurate it appears to be compared to historical data.

  Aesthetic principles expressed in visual arts

Problem 1: Write an essay explaining the aesthetic principles expressed in visual arts and describe how they changed from the Baroque period through the early twentieth century.

  Find the mean mode and median investment

Survey at least 30 engineering students to obtain each student's total investment in calculators and computers in the past 18 months.

  Find standard deviation who will be home owners

A political action group is planning to interview home owners to assess the impact caused by a recent slump in housing prices.

  What is the resulting cipher

Fix a modulus m and use the affine cipher with key k1 = (a, b) to encrypt an element x; then encrypt the result with a key k2 = (c, d). What is the resulting cipher

  What is the special structure of the formulation

Formulate his decision problem of which bottle to select each year as an integer linear program. What is the special structure of the formulation? How can this structure help in solving the problem?

  Describe the problem that can happen

Conflicts of interest are a type of one of the problems created by asymmetric information. Describe the problem that can happen when an institution provides multiple services?

  How do the coefficient estimates from the usual rule

These are the results of running 5-fold cross-validation on each of the ridge and lasso models, and using the usual rule (min) or the one-standard-error rule (1se) to select λ. How do the coefficient estimates from the usual rule compare to those ..

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd