In a status report, executives want to know not only where we are today, but also where we will end up. Calculating where we will end up financially is not as easy as it sounds. Selecting the wrong formula can leave the executives and customers with a faulty impression

There are several formulas available for the calculation of the estimated cost at completion (EAC). For simplicity, consider the following three formulas:

I. EAC = (ACWP/BCWP) X (budget at completion)

II. EAC = [(ACWP/BCWP) X (BCWS for work completed and in progress)] X (planned or revised planned costs of work packages not yet begun)

III. EAC = (actual to date) + (all remaining work, including work in progress, to be completed at the planned or budgeted costs)

a. Using the table below, determine the value of EAC for each of the three formulas. Assume that A, B, and C are the only work packages in the project, and BCWS(Total) is the total value for PV for each work package rather than PV for the reporting period. Use the following formula for calculating EV:
EV = [% Complete] = BCWS(Total)

b. Considering only activity B, if the reason for the cost overrun is attributed to a one-time occurrence, which of the three formulas would be best to use?

c. If the reason for the overrun in activity B is because of the higher than expected salaries of the assigned employees and these same employees will be assigned to activity C as well, which of the three formulas would be best to use?

d. Considering only activity B, if the reason for the overrun is attributed to overtime and the overtime will continue but only through the completion of activity B, which of the three formulas would be best to use?

e. Considering your answers to the above four parts, should a company be willing to change the formula for calculating EAC during the execution of the project as well as at each reporting period or gate review meeting?

Reference no: EM131244917

Questions Cloud

Construct scatter graphs - gdp per capita : Construct scatter graphs - GDP per capita v. TPES per capita and Tabulate the 10 countries with the highest CO2 emissions and their shares of total world emissions.
Calculate firm expected ending cash balance for each month : Deltona Auto Care has an ending cash balance as of January 31, 2015 (the end of its fiscal year) was $15,000. Calculate the firm's expected ending cash balance for each month
What is the new expected length of the project : How much money will be needed from the time of the report to complete the project?
Select current problem in area of the criminal justice field : Select a current problem in one area of the criminal justice field. - Identify the problem. - Quantify the problem. Use numbers to identify why the problem is growing.
Which of the three formulas would be best to use : Considering your answers to the above four parts, should a company be willing to change the formula for calculating EAC during the execution of the project as well as at each reporting period or gate review meeting?
Write and send an email as an invitation asking for feedback : Write and send an email as an invitation asking for feedback about your personal behavioral style. Share as much of the feedback that you received from the DiSC assessment as you feel comfortable with.
What is discount rate on stock : Stock price is $45. Dividend is $4.00. Treasury bill,s interest rate is 2.5percent- What is discount rate on stock.
Preface the given post : Preface the given post by saying that I believe "all Scripture is God-breathed and is useful for teaching, rebuking, correcting and training in righteousness"
How many man-hours per month are actually available : Companies usually estimate work based upon man-months. If the work must be estimated in man-weeks, the man-month is then converted to man-weeks. The problem is in the determination of how many man-hours per month are actually available for actual ..

Reviews

Write a Review

Basic Computer Science Questions & Answers

  Identifies the cost of computer

identifies the cost of computer components to configure a computer system (including all peripheral devices where needed) for use in one of the following four situations:

  Input devices

Compare how the gestures data is generated and represented for interpretation in each of the following input devices. In your comparison, consider the data formats (radio waves, electrical signal, sound, etc.), device drivers, operating systems suppo..

  Cores on computer systems

Assignment : Cores on Computer Systems:  Differentiate between multiprocessor systems and many-core systems in terms of power efficiency, cost benefit analysis, instructions processing efficiency, and packaging form factors.

  Prepare an annual budget in an excel spreadsheet

Prepare working solutions in Excel that will manage the annual budget

  Write a research paper in relation to a software design

Research paper in relation to a Software Design related topic

  Describe the forest, domain, ou, and trust configuration

Describe the forest, domain, OU, and trust configuration for Bluesky. Include a chart or diagram of the current configuration. Currently Bluesky has a single domain and default OU structure.

  Construct a truth table for the boolean expression

Construct a truth table for the Boolean expressions ABC + A'B'C' ABC + AB'C' + A'B'C' A(BC' + B'C)

  Evaluate the cost of materials

Evaluate the cost of materials

  The marie simulator

Depending on how comfortable you are with using the MARIE simulator after reading

  What is the main advantage of using master pages

What is the main advantage of using master pages. Explain the purpose and advantage of using styles.

  Describe the three fundamental models of distributed systems

Explain the two approaches to packet delivery by the network layer in Distributed Systems. Describe the three fundamental models of Distributed Systems

  Distinguish between caching and buffering

Distinguish between caching and buffering The failure model defines the ways in which failure may occur in order to provide an understanding of the effects of failure. Give one type of failure with a brief description of the failure

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd