Question 1. 1.

A/an _________ activity has more than one dependency arrow flowing from it.

Parallel

Critical path

Burst

Merge

Independent

Question 2. 2.

Which of the following is least likely to be included in a Work Package?

Materials

Labor

Overhead

Duration

Responsibilities

Question 3. 3.

The requirement for a freshly poured foundation to cure before beginning construction is an example of which of the following type of lag?

Start to Start

Start to Finish

Finish to Finish

Finish to Start

Any of these could be correct

Question 4. 4.

The first step of project scope definition is to

Analyze the strategic plan

Analyze the current budget plan

Meet with team members

Select team members

Define the overall objective to meet the customer's needs

Question 5. 5.

People working on prototype development needing time to interact with the design engineers after the design is completed is an example of:

Hidden interaction costs

Things going wrong on a project

Normal conditions not applying

Changes in project scope

None of these are correct

Question 6. 6.

General and Administrative costs are usually allocated as a percent of the total of a direct cost such as labor, materials, or equipment.

True

False

Question 7. 7.

If, for some reason, the project must be expedited to meet an earlier date, which of the following actions would the project manager take first?

Check to see which activities cost the least

Check to see which activities have the longest duration

Check to see which activities are on the critical path

Check to see which activities have the most slack

Check to see which activities have the highest risk

Question 8. 8.

Scott has just been given a project that has a specific target date. After discussion with top management he finds that while the date is important the cost is more important and a slip in delivery would be acceptable if required to meet the cost targets. The target date is best classified as

Constrain

Enhance

Accept

Limit

Optional

Question 9. 9.

The backward pass in project network calculations determines the

Latest time's activities can begin

Earliest time's activities can be finished

Critical path

Both A and C are correct

A, B, and C are all correct

Question 10. 10.

By definition, the critical path always has zero slack.

True

False

Reference no: EM131010790

Questions Cloud

Which is readily obtained from school records : A psychologist operating a group home for delinquent adolescents needs to show that the home is successful at reducing delinquency. He samples 10 adolescents living in their own homes who have been identified by the police as having problems, 10 s..
What is the company''s vision statement : What role do these have on the way the business operates? Do the company's actions seem to align to their vision and mission statements?
How mobile and wearable devices benefit the business : Articulate the current company setup. Explain how mobile and wearable devices are different and Explain how mobile and wearable devices benefit the business
Write a paper on oen source business intelligence tools : Write a paper On Oen Source Business Intelligence Tools, It should contains 7 pages
Which of the following type of lag : Which of the following is least likely to be included in a Work Package?
Analysis of policy : An analysis of policy, which could be any policy of Australian government related to environmental issues such as waste, water, energy, biodiversity.
Development of statements of policy for assurance plan : For the Module Three assignment, students will be provided multiple scenarios that contain hypothetical situations pertaining to authentication and security protocols, which will assist in the development of statements of policy for the information..
What is the productivity of the processing facility : What is the productivity of the processing facility, with the equipment currently in use? What would the productivity of the plant become if the new system were purchased and implemented
Develop a process map for the medical clinic : Develop a process map for the medical clinic that shows the times of the various activities. Is the patients" dissatisfaction with the clinic justified

Reviews

Write a Review

Business Management Questions & Answers

  Elucidate the internet effects on planning

Elucidate the Internet's effects on planning by Explain how it influences 1) the motivation for planning, 2) the processes for planning, also 3) the outcomes of planning. Be sure to give complete explanations of each effect, using examples in your..

  Contributions towards martha stewart omnimedias business

contributions towards martha stewart omnimedias business success1. a synopsis of martha stewart omnimedias history.2.

  Describe the situation facing mensa

Explain develop a five-year strategic plan with cost estimates and a time line and Describe the situation facing Mensa at the time of the case

  Electronic life vs real lifewhat are some of the benefits

electronic life vs. real lifewhat are some of the benefits of participating in online communities and social networking

  Organizational behavior - leadership

Leadership. Given a situation where a manager has not been successful using a particular leadership approach, analyze the situation and identify

  Making hotplates what variations in the work situation

Making Hotplates what variations in the work situation might account for the increase in productivity and the decrease in controllable rejects?

  Show team conflict and resolution

What are the things/steps that make a team successful in solving problems and explain Tuckman's four stages of team development and the philosophy behind those stages

  Characteristics of gores organizational structure

Identify the characteristics of Gores Organizational structure with the help of examples from the case study, what type of Organization structure is found at Gores Associates.

  Current policy issues on energyshow current policy issues

current policy issues on energy.show current policy issues regarding consumption of fossil fuels the creation of

  Leader and manager roles in terms of visionleadershipneed

leader and manager roles in terms of visionleadershipneed some assistance in gathering ideas. what would be several

  Mitsubishi service department

Stephen Brooks was employed as a sales representative for the Bob King Mitsubishi car dealership. Reba Stanley, age eighteen, met with Brooks to test drive a Mitsubishi pickup truck.

  Maximum expected monetary value

1. Suppose that the management of Theme Park, Inc., has decided that three is a .35 probability that the motel's application will be approved. Chapter 5 Supplement, problem a. If management uses maximum expected monetary value as the decision crite..

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd