Question 1

A critical path refers to:

a sequence of task activities whose order and durations indirectly affect the completion date of a project.

a sequence of task activities whose order and durations directly affect the completion date of a project.

a sequence of task activities whose order must be performed in parallel.

a sequence of task activities whose duration cannot last more than 40 percent of the time allotted to the project.

None of these.

Question 2

A scheduling technique where the order and duration of the sequence of activities directly affect the completion date of a project refers to:

critical path scheduling.

Gantt scheduling.

task management.

activity scheduling.

sequencing strategy.

Question 3

A technique that uses optimistic, pessimistic, and realistic time to calculate the expected time for a particular task best defines:

flowcharting.

Unified Modeling Language (UML).

Gantt.

Program Evaluation Review Technique (PERT).

Computer Aided Software Engineering (CASE).

Question 4

An example of a project management system is:

Microsoft Project for Windows.

Microsoft Office.

QuarkXpress.

Word Perfect.

Lotus 1-2-3.

Question 5

Any person, group of people, piece of equipment, or material used in accomplishing an activity is referred to as a(n):

expense.

agent.

identifier.

entity.

resource.

Question 6

Automated tools available to help you manage a development project are referred to as:

diagram generators.

utility software.

desktop publishing software.

project management software.

systems development software.

Question 7

Changes to the baseline project plan might be motivated by:

a slipped completion date of an activity.

a bungled activity that must be redone.

the identification of a new activity that becomes evident later in the project.

an unforeseen change in personnel due to sickness, resignation, or termination.

All of these.

Question 8

Determining the strengths and weaknesses of project deliverables, the processes used to create them, and the project management process is done during:

closing the customer contract.

establishing the communication plan.

conducting post project reviews.

communicating the project status.

closing down the project.

Question 9

Developing an understanding of the content and complexity of the project is the purpose of:

determining project standards and procedures activity of the project planning phase.

describing the project scope, alternatives, and feasibility activity of the project planning phase.

setting a baseline project plan activity of the project planning phase.

closing down the project activity of the project planning phase.

developing a project charter activity of the project planning phase.

Question 10

During which of the following project planning activities do you use the information regarding tasks and resource availability to assign time estimates to each activity in the work breakdown structure?

Dividing the project into manageable tasks

Developing a preliminary schedule

Developing a project scope statement

Describing project scope, alternatives, and feasibility

Setting a baseline project plan

Question 11

Ensuring that all contractual terms of the project have been met is done during:

setting a baseline project plan.

conducting post project reviews.

communicating the project status.

closing the customer contract.

project implementation.

Question 12

Identifying, assessing, and managing the risks and day-to-day changes that occur during a project best defines which of the following project manager activities?

Customer relations

Risk and change management

Conflict management

Technical problem solving

Team management

Question 13

Indicating when and how written and oral reports will be provided by the team, how team members will coordinate work, what messages will be sent to announce the project to interested parties, and what kinds of information will be shared with vendors and external contractors involved with the project describes:

developing a project scope statement.

establishing the project initiation team.

determining project standards and procedures.

developing a communication plan.

setting a baseline project plan.

Question 14

Influencing the activities of others toward the attainment of a common goal through the use of intelligence, personality, and abilities refers to which of the following project manager activities?

Management

Conflict management

Customer relations

Team management

Leadership

Question 15

Managing conflict within a project team to ensure that conflict is not too high or too low best defines which of the following project manager activities?

Risk management

Leadership

Conflict management

Team management

Problem solving

Question 16

Skills that include defining and sequencing activities, communicating expectations, assigning resources to activities, and monitoring outcomes best represent:

management.

team management.

leadership.

technical problem solving.

customer relations.

Question 17

The amount of time that an activity can be delayed without delaying the project refers to:

slack time.

delay time.

stop time.

down time.

noncritical time.

Question 18

The final phase of the project management process that focuses on bringing a project to an end is called:

project initiation and planning.

project closedown.

project evaluation.

project implementation.

project review.

Question 19

The process of dividing the project into manageable tasks and logically ordering them to ensure a smooth evolution between tasks defines:

work breakdown structure.

work structuring.

task division.

critical path scheduling.

project division.

Question 20

The responsibility for keeping all team members informed of the project status best describes:

updating project status.

monitoring project progress against the baseline project plan.

communicating the project status.

executing the baseline plan.

establishing the project initiation plan.

Question 21

Which of the following is NOT a task characteristic?

A task should have well-accepted predecessor and successor steps.

A task should have a known method or technique.

A task should be completed by only one person.

A task is measurable so that percent completed can be determined.

A task should have a single and identifiable deliverable.

Question 22

Which of the following is NOT a true statement regarding network diagrams?

All activities with a slack time equal to zero are on the critical path.

To construct a network diagram, a horizontal bar is drawn for each activity that reflects its sequence and duration.

Nodes not on the critical path can be delayed (for some amount of time) without delaying the final completion of the project.

The critical path of a network diagram is represented by the sequence of connected activities that produce the longest overall time period.

The latest expected completion time refers to the time in which an activity can be completed without delaying the project.

Question 23

Which of the following is a true statement regarding project time estimates?

Hardware and software are the most important, and expensive, part of project resource planning.

Project time estimates are always on target.

Project time estimates for task completion and overall system quality are significantly influenced by the assignment of people to tasks.

Resource estimates should not be revised based upon the skills of the actual person assigned to a particular activity.

Staff learning can be enhanced by assigning individuals to tasks which are "over their heads."

Question 24

Which of the following is true regarding Gantt chart construction?

To construct the Gantt chart, a horizontal bar is drawn for each activity that reflects its sequence and duration.

Ellipses are used to represent activities.

To show precedence relationships, arrows are used to connect the nodes.

Arrows are used to reflect the sequence of activities.

Squares are used to represent activities.

Question 25

Which of the following refers to the time in which an activity can be completed without delaying the project?

Latest expected completion time

End time

Earliest expected completion time

Critical time

Delay time

Reference no: EM132116114

Questions Cloud

What is its payables turnover : What is its payables turnover? (Use 365 days a year. Round your answer to 2 decimal places.)
Design data dictionary for the given case and details : Design Data Dictionary that contains: all entities documented, all PK and FK documented, all attributes identified and documented.
Backups or copies of important documents : Think of a risk that an individual faces and find a specific example. Then apply the 6 Methods of Risk Control. Select which of the Method you believe to be the
Prepare project about wk ashman company : Prepare Project about WK Ashman company - Introduction of WK project - Use same data of this report and prepare short report about 500 words including points
Which of the following is not a task characteristic : A technique that uses optimistic, pessimistic, and realistic time to calculate the expected time for a particular task best defines.
How much are his monthly payments expected to be : His loan requires him to make monthly payments over a 10-year period at 4.2% annual rate. How much are his monthly payments expected to be?
What is the amount of the pretax profit on the sale : The firm no longer uses this property so is selling it today at a price of $13,500. What is the amount of the pretax profit on the sale?
Will it be profitable to take the $2,000 today : Someone just offered you $2,000 today to buy out your investment. Will it be profitable to take the $2,000 today?
How much if you want to pay yourself : How much if you want to pay yourself $450 at the beginning of each month?

Reviews

Write a Review

Computer Engineering Questions & Answers

  Design an australian population calculator program

You will design and implement an Australian population (AP) calculator program for client that allows users to input state/territory name and the population.

  Insert at least five sample rows of data into the employee

The database should have a table named Employee , with columns for employee ID, name, position, and hourly pay rate.

  Define a nonce and its use in entity authentication

Explain the general idea behind challenge-response entity authentication. Define a nonce and its use in entity authentication.

  Determine the process used to add content and publish the

write a 200- to 300-word short-answer response to the followingwhat is the process used to add content and publish the

  Create a bar chart of the average loan amount by racial

Create a bar chart of the average loan amount by racial and ethnic group. Make sure your axes are properly labeled and your chart has a title.

  Take any three features of linux and trace them back

Take any 3 features of Linux and trace them back to earlier mainframe operating system. How did spooling help to improve the throughput of operating system.

  Types of exploitation that prevalently occur over internt

Identify at least three (3) types of exploitation that prevalently occur over the Internet

  Java program that asks the user to enter two numbers x and b

Java program that asks the user to enter two numbers x and b.

  Explain how net neutrality will affect data networks

Base on your article review and the assigned reading, discuss how net neutrality will affect data networks and the availability of information to businesses.

  Write a business case for the new hwe accessories website

Write a 2- to 3-page business case for the new HWE Accessories website using Microsoft Word. Include the problem statement and Analysis of the situation.

  Problems on word processing application

Problems on word processing application

  Define some interfaces and abstract classes

In this project you will define some interfaces, abstract classes, and concrete classes, all placed in a specific package.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd