Which event should you be most concerned about

Assignment Help Operation Management
Reference no: EM132035615

1 Activities which can take place at the same time are termed

Parallel activity.

Merge activity.

Burst activity.

Critical path.

Independent activity.

2 An uncertain event or condition that, if it occurs, has a positive or negative effect on project objectives is termed a

Random chance.

Bad luck.

Risk.

Hazard.

Disaster.

3 Based on the following, which event should you be most concerned about?

Risk Event

Likelihood

Impact

Bad weather

2

3

Design flaw

3

5

Accident

1

5

Shipment delay

2

2

Power outage

1

5

Accident

Shipment delay

Bad weather

Power outage

Design flaw

4 If, for some reason, the project must be expedited to meet an earlier date, which of the following actions would the project manager take first?

Check to see which activities are on the critical path.

Check to see which activities cost the least.

Check to see which activities have the most slack.

Check to see which activities have the highest risk.

Check to see which activities have the longest duration.

5 Information to develop a project network is collected from the

Budget.

Organization breakdown structure.

Responsibility matrix.

Project proposal.

Work breakdown structure.

6 One common mistake made early in the risk identification process is to

Not consider all possibilities.

Encourage participants be over optimistic.

Give too much attention to past events.

Support participants being over pessimistic.

Focus on consequences and not on the events that could produce consequences.

7 Risks are evaluated in terms of

Impact and cost.

Likelihood and cost.

Time and impact.

Cost and schedule.

Likelihood and impact.

8 The amount of time an activity can be delayed and yet not delay the project is termed

Total slack.

Free slack.

Critical float.

Slip pad.

Float pad.

9 The attempt to recognize and manage potential and unforeseen trouble spots that may occur when a project is implemented is known as

Risk management.

Contingency planning.

Risk forecasting.

Scenario analysis.

Disaster protection.

10 The backward pass in project network calculations determines all of the following EXCEPT

Earliest time an activity can finish.

How long an activity can be delayed.

Latest time an activity can begin.

The critical path.

Latest time an activity can finish.

11 The cost impact of a risk event occurring as a project proceeds through its life cycle tends to

Remain about the same.

Drop sharply and then level out.

Rise sharply and then level out.

Slowly rise.

Slowly drop.

12 The critical path in a project network is the

Longest path through the network.

Shortest path through the network.

Network path with the most difficult activities.

Network path with the most merge activities.

Network path using the most resources.

13 The forward pass in project network calculations determines all of the following EXCEPT

Duration of the project.

Earliest time an activity can finish.

How soon the project can finish.

The critical path.

Earliest time an activity can begin.

14 The initial step in the risk management process is to

Set aside budget funds for managing the risks.

Assess the risk potential.

Appoint a risk manager.

Identify the risks.

Determine the level of acceptable risk.

15 The likelihood the original critical path(s) will change once the project is initiated is referred to as

Rigidity.

Concurrent engineering.

Sensitivity.

Flexibility.

Resilience.

16 When translated into a project network, a work package will become

An arrow.

A milestone.

One or more activities.

A single activity.

A critical path.

17 Which of the following correctly calculates the early finish for an activity?

LF + SL

LF + DUR

ES + SL

LS + DUR

ES + DUR

18 Which of the following correctly calculates the late start for an activity?

EF - DUR

LF - DUR

ES - DUR

LF - SL

ES - SL

19 Which of the following will correctly calculate the total slack in an activity?

LS - ES

LF - ES

LF - EF

LS - LF

Either LS - ES or LF - EF

20 ________ activities must be completed immediately before a particular activity.

Merge

Burst

Successor

Predecessor

Parallel

Reference no: EM132035615

Questions Cloud

Describe three departments that should be included : Describe three departments that should be included on the home page of a small town's Web site and describe the citizen interactions.
Do you think free agency increases competitive balance : Do you think free agency increases competitive balance? Why or why not? Explain using economic concepts.
Bea release highlights document : What trends in real GDP have occurred in the time period shown in the BEA release highlights document?
Explain the effective tactics for apn strategic positioning : Reflect on the current roles of advanced practice nurses in healthcare as the care providers at the front line of disease management and health promotion.
Which event should you be most concerned about : The attempt to recognize and manage potential and unforeseen trouble spots that may occur when a project is implemented is known as?
Difficulty of raising ticket prices when jet fuel prices : Accepting the premise that U.S. airline markets are indeed highly competitive, analyze in both the short run and long run the difficulty
Why is substance misuse among nurses a serious concern : Why is substance misuse among nurses a serious concern? What is the most appropriate way to handle a suspicion that a coworker may be involved in serious.
Traditional model of comparative advantage : Is the theory of multinational enterprise essentially consistent or inconsistent with the traditional model of comparative advantage?
Economy will be in the next six months : What are 2 indicators the government will look at to predict where the economy will be in the next six months?

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd