Which estimate would you use

Assignment Help Management Information Sys
Reference no: EM131757387

THE ESTIMATING PROBLEM

Barbara just received the good news: She was assigned as the project manager for a project that her company won as part of competitive bidding. Whenever a request for proposal (RFP) comes into Barbara's company, a committee composed mainly of senior managers reviews the RFP. If the decision is made to bid on the job, the RFP is turned over to the Proposal Department. Part of the Proposal Department is an estimating group that is responsible for estimating all work.

If the estimating group has no previous history concerning some of the deliverables or work packages and is unsure about the time and cost for the work, the estimating team will then ask the functional managers for assistance with estimating.

Project managers like Barbara do not often participate in the bidding process. Usually, their first knowledge about the project comes after the contract is awarded to their company and they are assigned as the project manager.

Some project managers are highly optimistic and trust the estimates that were submitted in the bid implicitly unless, of course, a significant span of time has elapsed between the date of submittal of the proposal and the final contract award date. Barbara, however, is somewhat pessimistic. She believes that accepting the estimates as they were submitted in the proposal is like playing Russian roulette. As such, Barbara prefers to review the estimates.

One of the most critical work packages in the project was estimated at twelve weeks using one grade 7 employee full time. Barbara had performed this task on previous projects and it required one person full time for fourteen weeks. Barbara asked the estimating group how they arrived at this estimate. The estimating group responded that they used the three-point estimate where the optimistic time was four weeks, the most likely time was thirteen weeks, and the pessimistic time was sixteen weeks.

Barbara believed that the three-point estimate was way off of the mark. The only way that this work package could ever be completed in four weeks would be for a very small project nowhere near the complexity of Barbara's project. Therefore, the estimating group was not
considering any complexity factors when using the three-point estimate.

Had the estimating group used the triangular distribution where each of the three estimates had an equal likelihood of occurrence, the final estimate would have been thirteen weeks. This was closer to the fourteen weeks that Barbara thought the work package would take. While a difference of 1 week seems small, it could have a serious impact on Barbara's project and incur penalties for late delivery.

Barbara was now still confused and decided to talk to Peter, the employee that was assigned to do this task. Barbara had worked with Peter on previous projects. Peter was a grade 9 employee and considered to be an expert in this work package. As part of the discussions with Barbara, Peter made the following comments:

I have seen estimating data bases that include this type of work package and they all estimate the work package at about 14 weeks. I do not understand why our estimating group prefers to use the three point estimate.

"Does the typical data base account for project complexity when considering the estimates?"asked Barbara. Peter responded:

Some data bases have techniques for considering complexity, but mostly they just assume an average complexity level. When complexity is important, as it is in our project, analogy estimating would be better. Using analogy estimating and comparing the complexity of the work package on this project to the similar works packages I have completed, I would say that 16-17 weeks is closer to reality, and let's hope I do not get removed from the project to put out a fire somewhere else in the company. That would be terrible. It is impossible for me to get it done in 12 weeks. And adding more people to this work package will not shorten the schedule. It may even make it worse.

Barbara then asked Peter one more question:

Peter, you are a grade 9 and considered as the subject matter expert. If a grade 7 had been assigned, as the estimating group had said, how long would it have taken the grade 7 to do the job?

"Probably about 20 weeks or so," responded Peter.

QUESTIONS

1. How many different estimating techniques were discussed in the case?

2. If each estimate is different, how does a project manager decide that one estimate is better than another?

3. If you were the project manager, which estimate would you use?

Reference no: EM131757387

Questions Cloud

Government undertake because of fallen human nature : What functions must government undertake because of fallen human nature?
Define the average number of shares outstanding : the denominator should be based on the average number of shares outstanding. May this average be computed based on the sum of the shares determined
Distribution of outcomes and probabilities : For any given distribution of outcomes and probabilities, describe how preferences over risk affect behavior.
Normal probability plot of the emissions of carbon dioxide : Carbon dioxide emissions The figure below is a Normal probability plot of the emissions of carbon dioxide per person in 48 countries.
Which estimate would you use : How many different estimating techniques were discussed in the case?If you were the project manager, which estimate would you use?
Economic consultants will produce competing software : My patent expires in a year, and I know other economic consultants will produce competing software. What quantity and price will result once competing software
What are the two most abundant elements in earths crust : What are the two most abundant elements in Earth's crust? What type of motion is associated with primary seismic waves?
Discuss about the shape of the weight distribution : Weights aren't Normal The heights of people of the same gender and similar ages follow Normal distributions reasonably closely.
Flexible budget for fabrication department : Cabinaire Inc. is one of the largest manufacturers of office furniture in the United States

Reviews

Write a Review

Management Information Sys Questions & Answers

  What business benefits were derived from adopting

Was an ERP system associated with the business-process re-engineering? What business benefits were derived from adopting "best practices"?

  What controls will require to be in place for payroll cycle

Payroll cycle- harware and software, controls - What controls will require to be in place for the payroll cycle in order to integrate this cycle into an automated system?

  How has technology impacted the workplace

Important information about Technology Questions - How has technology impacted the workplace?

  Description of aggregate supply curvein a command system

description of aggregate supply curvein a command system economic decision making is carried out by which group?a.

  What are three key elements for an organization

What are three key elements for an organization to consider in strengthening its overall information security posture?

  Describing the management role in the technology

Write a 350-700 word summary describing the management's role in the technology (Smart phones) selected and the benefits of it (Smart phones) that support the organization's quality initiatives

  Compare and contrast an it audit project

Elaborate on three (3) of the obstacles that must be overcome as a business moves up the CMMI model. Suggest key methods for overcoming the obstacles.

  How will personal identifiable information be separated

Summarize the responses to the questions from your team discussion.Choose the solution that you personally feel is the right solution.Explain the reason you made your choice and justify your choice with current references.Format your memo consistant ..

  Summarize tools and techniques commonly used in project

Describe five (5) ethical situations or dilemmas that project managers might face in their role within an organization.

  Create a domain model class diagram for the rmo

Using Microsoft Visio or an open source alternative such as Dia, create a domain model class diagram for the RMO CSMS marketing subsystem.

  Discuss about the configuration management

Write a paper in which you determine which is more applicable across the widest possible range of situations: process modeling or configuration management.

  Create a seta program for the business or organization

Create a SETA program for the business or organization you chose for this week's Case Study.Describe the features you will need in each element (education, training, and awareness) of your program - including the purpose of the element, techniques to..

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd