Which critical path activity would be the most logical

Assignment Help Financial Management
Reference no: EM13856767

Project Management and Statistical Process Control Homework Assignment

Project Management

PERT Network Diagram 1 illustrates the ten interrelated activities that comprise a certain project.

PERT Network Diagram 1

976_pert 1.png

The information presented in Table 1 represents the optimistic activity time (a), most probable activity time (m), and pessimistic activity time (b) in weeks for each activity associated with the project.

Activity

Optimistic (a)

Most Probable (m)

Pessimistic (b)

A

2

3

4

B

1

3

5

C

2

5

8

D

1

2

3

E

2

4

6

F

1

3

5

G

2

4

6

H

1

3

5

I

2

4

6

J

1

4

7

 

2084_pert 2.png

1. Using the information provided in Table 1, calculate the expected activity time (t) in weeks for each activity and then enter this information in the appropriate data field provided for each activity in PERT Network Diagram 2 in order to complete this diagram. What is the expected activity time in weeks for each of the ten activities? (Arrange your answers in alphabetical order by activity beginning with activity A and ending with activity J).

2. Using the information provided in Table 1, calculate the variance for the estimated activity time for each activity. (Arrange your answers in alphabetical order by activity beginning with activity A and ending with activity J).

3. Using the information in completed PERT Network Diagram 2, calculate the overall estimated activity time in weeks for each path through the network; identify which path constitutes the critical path.

4. Using the information provided in Table 1, calculate the standard deviation for the project.

5. Using the information provided in Table 1 and completed Project Network Diagram 2, calculate the probability of the project critical path activities being completed in less than or equal to 24 weeks.

The information presented in Table 2 represents the calculated Earliest Start, Earliest Finish, Latest Start and Latest Finish times for each activity.

Table 2

Activity

Earliest Start

Earliest Finish

Latest Start

Latest Finish

A

0

3

0

3

B

3

6

3

6

C

6

11

6

11

D

11

13

16

18

E

6

10

7

11

F

11

14

11

14

G

18

22

18

22

H

0

3

7

10

I

3

7

10

14

J

14

18

14

18

1.      Using the information provided in Table 2, calculate the slack time in weeks for each activity.  (Arrange your answers in alphabetical order by activity beginning with activity A and ending with activity J).

The information presented in Table 3 represents the total budgeted cost for each activity associated with the project. 

Activity

Total Budgeted Cost

A

$22,000

B

$30,000

C

$24,000

D

$8,000

E

$7,000

F

$9,000

G

$10,000

H

$12,000

I

$23,000

J

$11,000

2.      Using the information provided in Table 2 and Table 3, calculate the budgeted costs for week seven of the project based upon using the Earliest Start Date for each activity and calculate the budgeted costs for week seven of the project based upon using the Latest Start Date for each activity in order to then calculate the difference in the cashflow for week seven between these two scenarios.

3.      Using the information provided in Table 2 and Table 3, calculate the budgeted costs for week eighteen of the project based upon using the Earliest Start Date for each activity and calculate the budgeted costs for week eighteen of the project based upon using the Latest Start Date for each activity in order to then calculate the difference in the cashflow for week eighteen between these two scenarios.

Table 4 represents the percentage of completion and actual cost of work performed data for each activity associated with the project at a certain point in time during the project.


Activity

Total Budgeted Cost

Percent of Completion

Actual Cost of Work Completed

A

$22,000

100%

$23,000

B

$30,000

100%

$28,000

C

$24,000

100%

$27,500

D

$8,000

85%

$7,300

E

$7,000

65%

$9,800

F

$9,000

0%

$0

G

$10,000

0%

$0

H

$12,000

45%

$5,100

I

$23,000

0%

$0

J

$11,000

0%

$0

4.      Using the information provided in Table 4, calculate the value of work completed and activity difference for each activity.  Which activity evidences the single largest activity difference (regardless of whether it is a cost overrun or cost underrun) at this particular point in the project?

5.      Using the information provided in Table 4, calculate the overall cost overrun or cost underrun for the project at this particular point in the project.

Table 5 represents the estimated crash time in weeks and associated total crash cost for each activity. 

 

 

Activity

Crash Time

(Weeks)

Total Crash Cost

A

2

$25,000

B

2

$40,000

C

4

$27,000

D

1

$9,000

E

3

$8,500

F

2

$12,000

G

3

$11,000

H

2

$15,000

I

3

$26,000

J

3

$13,000

6.      Using the information in completed PERT Network Diagram 2 and Table 5, crash the network in order to reduce the estimated project duration to 20 weeks while minimizing the overall crash cost. Which critical path activity would be the most logical choice for the first activity to crash?

7.      Which critical path activity would be the most logical choice for the second activity to crash?

8.      What is the total estimated cost associated with crashing the network to reduce the estimated project duration to 20 weeks at the lowest possible overall crash cost?

9.      After successfully crashing the network to reduce the estimated project duration to 20 weeks, which path through the crashed network constitutes the critical path?

Reference no: EM13856767

Questions Cloud

The cost of preferred stock : The cost of preferred stock:
Summarizes landes hypothesis : Write a 500 word essay that summarizes landes hypothesis regarding the relationship between the emergence of European communes (cities) and European economic development.
What is the irr of the better project? : What is the IRR of the better project?
Can you identify any traits of humanity : As humans, we have something we could call human culture. Can you identify any traits of humanity that are common to all cultures
Which critical path activity would be the most logical : Which critical path activity would be the most logical choice for the second activity to crash?
Strategy for addressing any challenges you may face : Strategy for addressing any challenges you may face once you arrive at your new location and Strategy for addressing the cultural differences which may impact the achievement of team goals and objectives
Determine your weekly orders for kentucky swamp brew : You will also experience the Bull-Whip Effect as you practice in the EBBD simulation -  What feedback would you like to have, specifically, as you determine your weekly orders for Kentucky Swamp Brew? How would get such information?
Logic puzzle of five friends : Five friends had just let out a collective sigh of relief after filling their income tax statements on time, when the subject of tax write offs arose.
Explain squirrel-cage induction motor operates : A four-pole, star-connected, squirrel-cage induction motor operates from a variable voltage 50 Hz three-phase supply. The following results were obtained as the supply voltage was gradually reduced with the motor running on no-load. Stator line vo..

Reviews

Write a Review

Financial Management Questions & Answers

  Foreign company acquisition

Acquisition by a foreign company and the effects of that decision and the results of foreign exchange in Euro and the exchange rate differences.

  Financial management for profit and non profit organizations

In this essay, we are going to discuss the issues of financial management in a non-profit organisation.

  Method for estimating a venture''s value

Evaluate venture's present value, cash and surplus cash and basic venture capital.

  Replacement analysis

This document show the Replacement Analysis of modling machine. Is replacement give profit to company or not?

  Business finance task - capital budgeting

Your company is considering using the payback period for capital-budgeting. Discuss the advantages and disadvantages of this technique.

  Analysis of the investment

In this project, you will focus on one of these: the additional cost resulting from the purchase of an apple press (a piece of equipment required to manufacture apple juice).

  Conduct a what-if analysis

Review the readings and media for this unit, including the Anthony's Orchard case study media. Familiarise yourself with the Anthony's Orchard company and its current situation.

  Determine operational expenditures

Organisations' behaviour is guided by financial data. In the short term, such data will help determine operational expenditures; in the long term, historical data may help generate forecasts aimed at determining strategic plans. In both instances.

  Personal financial management

How much will you have left over each half year if you adopt the latter course of action?

  Sources of finance for expansion into new foreign markets

A quoted company is considering several long-term sources of finance for expansion into new foreign markets.

  Long term financial planning

This assignment is designed for analyze Long term financial planning begins with the sales forecast and the key input in the long term fincial planning.

  Explain the role of fincial manager

This assignment explain the role of fincial manager, function of manger. And what are the motives of financial manager.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd