Reference no: EM132767283
Problem 1: Which of the following correctly pairs a capacity strategy with a relevant risk?
a) Capacity lead strategy; risk of increased demand not materializing
b) Capacity lag strategy; risk of excess capacity sitting idle
c) Capacity lag strategy; risk of slower demand growth than anticipated
d) Average capacity strategy; risk of demand not decreasing as anticipated
Problem 2: Which of the following statements is true?
a) Process mapping is exclusively used for business process management (BPM) and business process re-engineering (BPR).
b) BPM focuses exclusively on applying technology to automate processes.
c) BPM builds on BPR by adding a broader managerial perspective
d) BPR examines not only the processes, but also the underlying assumptions about why things are done.