Question - Bugs Ltd has provided the following amounts for the completion of a building construction
2019 $000s 2020 $000s 2021 $000s
Costs for the year $5,000 $9,000 $5,500
Costs incurred to date $4,000 $13,000 $18,500
Estimated costs to complete $12,000 $5,000
Progress Billings $5,500 $9,500 $8,000
Cash collected $4,500 $8,500 $10,000
Contract Price $23,000
Use the percentage of completion method where the extent of completion can be reliably measured and prepare the journal entries for the three years.