The following data consists of the actual time used and potential (the best time possible for this review process)to complete each step in the review process. The actual times are based on the review of 30 projects. The potential times are subjective engineering judgment estimates.
Table: Basic Data Review for Construction Project Equipment Arrangement
Cycle Time (hours)
Step
Description
Actual
Potential
Difference
1
Read basic data package
4
-
2
Write, type, proof, sign, copy, and distribute cover letter
21.9
0.5
21.4
3
Queue
40
0
Lead engineer calls key people to schedule meeting
0.25
3.75
5
Write, type, proof, sign, copy, and distribute confirmation letter
25.4
2.1
23.3
6
Hold meeting; develop path forward and concerns
7
Project leader and specialist develop missing information
12
8
Determine plant preferred vendors
9
Review notes from meeting
10
Resolve open issues
106
104
11
Write, type, proof, sign, copy, and distribute basic data acceptance letter
26.5
26.25
Totals
267.8
151.1
116.7
Use the data in thetable above and answer the following questions in the space provided below:
1. What are the sources of value-added and non-value-added work in this process?
2. Where are the main opportunities to improve the cycle time of this process, with respect to both actual time used and the potential best times? What strategy would you use?
3. Step 10:Resolve Open Issues required 104 hours (potential) versus 106 hours (actual). Is there an OFI here? Why or why not? If so, how would you attack it?
4. What do you think are the most difficult critical issues to deal with when designing a sound cycle time study such as this one?
Identify the type of observational study (cross-sectional, retrospective, or prospective) described
Let p be the proportion of the population who responded YES. Find p-hat and q-hat. Construct the confidence interval for the population proportion p with 98% confidence. You may use technology to construct the confidence interval. Interpret the resu..
An experimenter wants to conduct a hypothesis test on a claim that there was no differencebetween two population means. That is, H0: μ1 - μ2 = 0. Which of the following 95% confidenceintervals on the difference, μ1 - μ2, would lead to rejectio..
The capacity of an elevator is 8 people or 1232 pounds. The capacity will be exceeded if 8 people have weights with a mean greater than 1232/8=154 pounds. Suppose the people have weights that are normally distributed with a mean of 162 lb and a stand..
A survey of people in Iowa showed that 40 out of 400 prefer watching TV comedy shows. Another survey in Colorado showed that 90 out of 600 prefer watching TV comedy shows. At a 1% significance level, would it seem that the true proportions of p..
Consider a class in which there are 40 students enrolled. (In what follows, ignore February 29th)John is a student in this class. What is the probability that at least one other student in the class has John's birthday (Day and month, but not necessa..
1.An experiment was performed on a certain metal to determine if the strength is a function of heating time (hours). Results based on 20 metal sheets are given below. Use the simple linear regression model. ∑X = 40 ∑X2 = 200 ∑Y = 70 ∑Y2 = 545 ∑XY = 3..
Brief literature review of factors influencing sales - investigate the relationship between advertising expenditure and sales.
question 1- search the internet and the articles database in the library for a real-life example of correlation. for a
Example Study 2: Another researcher finds 4,000 men over 40 who have not had heart attacks and are willing to participate in a study. She assigns 2,000 of them into a regular program of supervised exercise. The other 2,000 continued their usual..
The Jackson Engineering Company has a training program designed to upgrade the supervisory skills of production-line supervisors. Because the program is self-administered, supervisors require different numbers of hours to complete it. A study of pa..
Discuss how a normal probability plot is constructed. If a normal probability plot has the appearance of a straight line, what should we conclude?
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd