There are 10 vehicles in a queue when an attendant opens a toll booth. Vehicles arrive at the booth at a rate of 4 per minute. The attendant opens the booth and improves the service rate over time following the function u(t) = 1.1 + .30t, where u(t) is in vehicles per minute and t is in minutes. When will the queue clear?

Reference no: EM13210620

Questions Cloud

What types of attacks can still occur : Do the administrators of server systems still have to be concerned about, and take further countermeasures against DoS attacks, if so, what types of attacks can still occur, and what measures can be taken to reduce their impact?
What will be the total vehicle delay : Assuming D/D/1 queuing, what will be the total vehicle delay?
What is the probability that the vehicle pulling out : what is the probability that the vehicle pulling out will get in an accident with oncoming traffic?
What type of exercise takes place in a classroom : What type of exercise takes place in a classroom setting arranged to look like an emergency operations center or in an actual emergency operations center, and involves simulation using written, telephone, and radio messaging.
When will the queue clear : where u(t) is in vehicles per minute and t is in minutes. When will the queue clear?
Explain whats the anode charge : whats the anode charge. please include the answer and why and a step process please
Compute normal and critical depths in a concrete culvert : compute normal and critical depths in a concrete culvert(n=0.015)with a diameter of 36in.and a bed slope of 0.002ft/ft if the design discharge is 15cfs.is the slope steep or mild?reap for S= 0.02ft/ft.
What type of contract would you want and why : If you were asked to perform an excavation contract competitively with limited data, what type of contract would you want and why?
Type of project communication : What type of project communication should Janet implement to discuss the status, technical issues and responsibilities on the project?

Reviews

Write a Review

Civil Engineering Questions & Answers

  Rankine cycle and thermal efficiency

Determine the rate at which heat is added in the boiler, the power required to operate the pumps, the net power produced by the cycle, and the thermal efficiency.

  Concentration of moles in the tank solution

HOCL is added to water in a tank as a disinfectant. After equilibrium is reached it is found that the pH of the water in the tank is 8.2 and the gas phase partial pressure is the head space of the tank is 0.2E-7 atm.

  Discharged of wastewater to aquifer

Wastewater is discharged into an aquifer. This wastewater contains 0.1 ppm atrazine (a common herbicide). The MCL of atrazine is 5 ppb, the density is 1.19 g/mL and the solubility is 50 ppm. 500 ft away from the plant effluent there is a permeable..

  Design of wastewater treatment plant for a community

Consider the design of wastewater treatment plant for a community wiyh average daily and peak hourly wastewater design flows of 2.0 mgd. The raw sewage has an average of 230 mg/l BOD5 and 260 mg/l of suspended solids.

  Type of reaction involving protonated alcohol

The reaction between 2-methyl-2-pentanol and HBr to yield 2-methyl-2-pentene is probably: A) an E1-type reaction involving the protonated alcohol as the substrate. B) an SN2-type reaction involving the protonated alcohol as the substrate.

  Deflection of a simple uniformly loaded beam

Determine the deflection of a simple uniformly loaded beam by the Ritz method,using first one term, then two terms, adn finally three terms in a sine series. Why does the coefficient of sin2piex/L vanish?

  Find the steady-state concentration of pollutant

The pollutant has a reaction rate coeeficient k of 0.25/day. Assuming is pollutant is well mixed in the lake, find the steady-state concentration of pollutant in the lake.

  Level of the service of compound-grade freeway segment

There are no interchanges in the vicinity of this freeway segment. If the peak-hour factor is .90 and all of the drivers are regular users, what is the level of the service of this compound-grade freeway segment?

  What are the surface overflow rate

a rectangular clarifier with a length:width ratio of 3:1 receives a flow of 850m3/day. the clarifiers depth is 4.0m and the detention time of the water inthe clarifier is 2.4 hrs, what are the surface overflow rate and the horizontal flow through ..

  Alternative water resource projects

Consider two alternative water resource projects, A and B. Project A will cost $2,533,000 and will return $1,000,000 at the end of 5 years and $4,000,000 at the end of 10 years.

  Find the temperature stress produced

A rod of steel is 20 m long at a temperature of 200C. find the free expansion of the rod when the temperature is raised to 650C. Find the temperature stress produced

  Engineering ethics and ethical issue

what is the engineering ethics course where to write about any engineering ethical case and discuss the ethical issue?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd