Problem - CodeHead Software Inc. does software development. One important activity in software development is writing software code. The manager of the WordPro Development Team determined that the average software programmer could write 25 lines of code in an hour. The plan for the first week in May called for 4,650 lines of code to be written on the WordPro product. The WordPro Team has five programmers. Each programmer is hired from an employment firm that requires temporary employees to be hired for a minimum of a 40-hour week. Programmers are paid $32.00 per hour. The manager offered a bonus if the team could generate more lines for the week, without overtime. Due to a project emergency, the programmers wrote more code in the first week of May than planned. The actual amount of code written in the first week of May was 5,650 lines, without overtime. As a result, the bonus caused the average programmer's hourly rate to increase to $40.00 per hour during the first week in May.
Instructions -
1. If the team generated 4,650 lines of code according to the original plan, what would have been the labor time variance?
2. What was the actual labor time variance as a result of generating 5,650 lines of code?
3. What was the labor rate variance as a result of the bonus?
4. Are there any performance-related issues that the labor time and rate variances fail to consider? Explain.
5. The manager is trying to determine if a better decision would have been to hire a temporary programmer to meet the higher programming demand in the first week of May, rather than paying out the bonus. If another employee had been hired from the employment firm, what would have been the labor time variance in the first week?
6. Which decision is better, paying the bonus or hiring another programmer?
What amount should the inventory at december
: By what amount should the inventory at December 31, 2005 be reduced? Merchandise out on consignment, at sales price, including 25% markup
|
Is a secured loan and what kind of loan
: Is this a secured loan? What kind of loan? Explain. A wealthy entrepreneur with excellent credit reputation co-signed the promotion of Myrtle
|
Determine the standard cost per unit for direct materials
: Each employee presently provides 40 hours of productive labor per week. Determine the standard cost per unit for direct materials
|
Make table that contains the standard labor-hour requirement
: Make a table that contains the standard labor-hour requirement per unit and standard direct labor cost per unit for the 4 months, October through January.
|
What would have been the labor time variance
: If the team generated 4,650 lines of code according to the original plan, what would have been the labor time variance
|
Find how much will the preferred shareholders receive
: Shareholders should receive a distribution of $11,000. If the company pays $50,000 in 2014 of dividends how much will the preferred shareholders receive?
|
What was correct total inventory value that should be used
: Henry Corporation's inventory at December 31, 2020, What was the correct TOTAL inventory value that should be used for product XX at December 31, 2020?
|
Prepare income statement for presentation to management
: The following data were taken from the records of Griggs Company for December: Prepare income statement for presentation to management
|
How do estimate the inventory of goods on hand
: How do Estimate the inventory of goods on hand at the close of business on November 20th AND determine the amount of the theft loss.
|