Reference no: EM131203363
Tom Wassink's irrigation shop uses 3,500 sprinkler heads during the course of a year, and this usage is relatively constant throughout the year. These sprinkler heads are purchased from a supplier 100 miles away for $9.50 each, and the lead time is 3 days. The holding cost per sprinkler heads per year is 8% of the unit cost and the ordering cost per order is $15.75. There are 365 working days per year.
a) What is the EOQ?
b) What is the annual inventory holding cost?
d) In minimizing cost, how many orders would be made each year?
d) What would be the annual ordering cost?
e) Given the EOQ, what is the total annual inventory cost (including purchase cost)?
f) What is the time between orders?
g) What is the ROP?
Upon hearing that Tom Wassink is considering producing the sprinkler heads in house, the vendor has notified Tom that the purchase price would drop from $9.50 per sprinkler heads to $9.00 per sprinkler heads if Tom will purchase the sprinkler heads in lots of 500. Lead times, however would increase to 4 days for this larger quantity.
a) What is the total annual inventory cost plus purchase cost if Tom buys the sprinkler heads in lots of 500 at $9.00 each?
b) If Tom does buy in lots of 500 brackets, what is the new ROP?
Generate a projected income statement
: At the most recent strategic planning meeting, the board of directors of your company has voted to issue additional stock to raise capital for major expansions for the company in the next five years. The board is considering $5 million. Generate a pr..
|
Examine policies regarding personnel planning
: Personnel Planning; TDABC Recent competitive pressures have caused National Insurance Company to examine policies regarding personnel planning. As a start, the company has decided to experiment with and develop a time-driven ABC model for its claims ..
|
What would be the annual ordering cost
: Tom Wassink's irrigation shop uses 3,500 sprinkler heads during the course of a year, and this usage is relatively constant throughout the year. These sprinkler heads are purchased from a supplier 100 miles away for $9.50 each, and the lead time is 3..
|
The new product according to the new pricing policy
: Bramlett Company has several divisions and just built a new plant with a capacity of 20,000 units of a new product. A standard costing system has been introduced to aid in evaluating managers' performance and for establishing a selling price for the ..
|
Individual accounts receivable in subsidiary ledger
: Below are four specific control objectives. Classify each objective according to the following types of control activities: (1) authorization, (2) accuracy of input, (3) completeness and accuracy of accumulated data, and (4) physical controls. The in..
|
Expected net realizable value of accounts receivable
: The following transactions were completed by The Irvine Company during the current fiscal year ended December 31: Feb. 8 Received 40% of the $18,000 balance owed by DeCoy Co., a bankrupt business, and wrote off the remainder as uncollectible. Determi..
|
Information for the statement of cash flows
: The management team of Wickersham Brothers Inc. is preparing its annual financial statements. Information for the Statement of Cash Flows is indicated below. Compute the changes and use the information to finalize the Statement of Cash Flows as indic..
|