Reference no: EM132650124
Your company operates in a job cost environment. Last year, your budgets for the following items were:
Factory Overhead Budget $ 60,000
Direct Labor Cost Budget $25,000
Direct Labor Hours Budget 4,000 hours
Machine Hours Budget 10,000 hours
Your actual activity for the same year resulted in the following:
Factory Overhead, Actual $52,000
Direct Labor Cost, Actual $30,000
Direct Labor Hours, Actual 4,200 hours
Machine Hours, Actual 11,000 hours
Question 1: What would be your over/(under) applied overhead if you used: (If it is under applied, it should be a NEGATIVE number. Please round UP to the nearest whole dollar and do not use dollar signs): Note: this question will not be auto graded.
a. Direct Labor Cost
b. Direct Labor Hours
c. Machine Hours?