What would a prepared work breakdown structure (WBS) listing for this project with activities corresponding to a two-level task and sub-task structure look like. The WBS would need to list activity item indents and WBS codes (such as a numbering scheme) that clearly identify the level of each activity. It also would need to provide columns showing the WBS code, activity, and the WBS code of the immediate predecessor activities. This would all be for the scenario below.
A warehouse is to be established in San Diego, CA, for distributing consumer products manufactured by your company at its main factory in the Portland, OR, area. As project manager to establish the facility, you will have to develop the overall distribution plans under which the facility will be established and operated in the San Diego region. This plan will include the estimated numbers of customers’ companies, the names and locations of potential customer facilities, and the estimated sales volume.
While looking to secure a suitable, existing building to lease, you can concurrently prepare for the initial stocking of the warehouse with products from the factory in Portland.
Securing a building will involve establishing facility requirements, searching for suitable building candidates, and negotiating a lease.
After the lease is signed and you take possession of the building, you will need to establish the facility operations. Any modifications necessary for your company's particular operational needs will have to be made. You will have to secure the items needed to make the building into an operational distribution center. Establishing facility operations will include securing and installing operating items that include fixtures (like shelving), materials handling equipment (like forklift trucks), and a telephone system. The computer system for ordering and inventory control is being handled by another project team.
To prepare for stocking, you will first have to establish the regional product plan that includes specific product types and volumes for the region to be served from the warehouse (for both initial limited operation and future full-scale operation). Then, orders must be prepared and submitted to get the initial stocks of required products delivered from the Portland factory. After taking possession of a building and submitting the orders, over a period of time you will receive products from Portland that will comprise the initial stock for the warehouse. The products will have to be unloaded from trucks and placed in the appropriate location within the warehouse.
With the warehouse stocked, you will operate it for a three-month period of time taking limited orders in a controlled systems test to check out operational procedures before turning over a fully operational facility to the company's sales, marketing, and physical distribution group. Once the initial stock of product is in place, reorders and additions to products for the warehouse will be handled by standard company operational procedures already in place. Establishing transportation systems for the new distribution center is being handled by another project team.
|
Find the energy stored in each capacitor.
: Consider a group of capacitors, where C1=14 µF and C2=6.8 µF. Terminals A and B are connected to a 9.0 V battery. Find the energy stored in each capacitor.
|
|
Which of two product groups is better suited to strengths
: What do you think of the fact that Blue Nile carries more than 30,000 stones priced at $2,500 or higher while almost 60% of the products sold from the Tiffany web site are around $200? Which of the two product groups is better suited to the strengths..
|
|
Obtained using the added value method,
: Having a GDP of $2375 obtained using the added value method, How much government revenue would a value added tax of 10% generate? How much revenue would a 10% sales tax on final output generate?
|
|
Profit and shareholder wealth comparison
: General Electric Corporation and Tyco International are both classified as "conglomerates" (having many diversified business lines). General Electric has pursued a conservative growth strategy by focusing on being the number one or number two in e..
|
|
What would a prepared work breakdown structure
: What would a prepared work breakdown structure (WBS) listing for this project with activities corresponding to a two-level task and sub-task structure look like. The WBS would need to list activity item indents and WBS codes that clearly identify the..
|
|
Discuss whether you feel the sec
: Discuss whether you feel the SEC's temporary ban on short-selling financial stocks in 2008 during the financial crisis unfairly punished convertible arbitrage funds.
|
|
Determining the minimum-cost schedule
: a) What is the project's duration if only normal times are used? b) What is the minimum-cost schedule? c) What is the critical path for the minimum-cost schedule?
|
|
Should sexuality education be taught in schools
: Should sexuality education be taught in schools? Given the research on various types of sexuality education, what type of sexuality education program would you recommend and why
|
|
Two-channel solution provide the efficient operation
: Let us assume that the Best Burger restaurant pays its server $15 per hour and it assigns a cost of $10 per hour for customer waiting time. In addition, we know that λ = 24 customers per hour and µ = 30 customers per hour. Would the one-channel or tw..
|