What will you need to understand and measure

Assignment Help Project Management
Reference no: EM13334047

Could you please answer these homework questions.

1. What will you need to understand and measure for an effective reengineering project? 
Cost and risk
Performance of existing processes for a baseline
Strategic analysis and workflow
Inputs and outputs

Question 2. 2. Enabling organizations to make continual improvements to many business processes and to use processes as the fundamental building blocks of corporate information systems is the goal of

PM.
BPR.
reengineering.
workflow management.

Question 3. 3. The _____ is directly responsible for the individual systems project. (Points : 1)
project management group
project team
IS steering committee
corporate strategic planning committee

Question 4. 4. Which process develops a detailed description of the functions that a new information system must perform?  1)
Feasibility study
Requirements analysis
Systems design
Test plan development

Question 5. 5. The entire system-building effort is driven by
organizational change.
feasibility studies.
the information value change.
user information requirements.

Question 6. 6. Systems design
describes what a system should do to meet information requirements.
shows how the new system will fulfill the information requirements.
always tries to increase precision.
includes the testing phases.

Question 7. 7. Transferring transaction data from a legacy system to the new system would be defined by which category of system design specifications? 
Input
Database
Manual procedures
Conversion

Question 8. 8. What is the primary driving factor in firms to select domestic outsourcing firms to build system solutions?

o take advantage of technical skills the firm does not have
To save labor costs
To avoid change management issues
All of the above

Question 9. 9. The four kinds of structural organizational change enabled by IT, in order from least to most risky, are
rationalization, automation, reengineering, and redesigning.
rationalization, automation, reengineering, and paradigm shift.
automation, rationalization, reengineering, and paradigm shifts.
automation, redesigning, restructuring, and paradigm shift.

Question 10. 10. Traditional software development methodologies often fail because

insufficient funds are allocated.
users are not an integral part of the development process.
not enough planning is done.
the IT staff does not have the necessary skills.

Question 11. 11. You have been hired by a pharmaceutical company to evaluate its inventory of systems and IT projects. Which types of projects would be best avoided?
Any high-risk projects
Any low-benefit projects
All high-risk, low benefit projects
None; any project might be beneficial

Question 12. 12. To best evaluate, from a financial standpoint, an IT investment whose benefits cannot be firmly established in advance, you would use
capital budgeting.
the real option pricing model.
the scoring model.
net present value.
Question 13. 13. What do many companies overlook when making information system investment decisions? (Points : 1)
Benefits from the new system
Organizational disruption costs
Social and organizational dimensions
All of the above

Question 14. 14. Information systems projects are valued similarly to stock options in which model of financial evaluation?
IRR
Real options pricing model
Capital budgeting
Accounting rate of return on ROI

Question 15. 15. An example of an external integration tool would be:
to define task dependencies.
to include user representatives as active members of the project team.
to create a PERT chart.
to hold frequent project team meetings.

Question 16. 16. Agile methodologies emphasize
thorough planning before the project starts.
sequential execution of the six steps of system development.
isolation of users from developers.
incremental development of small working pieces of the project.

Question 17. 17. The major variables in project management are
scope, time, cost, and performance.
scope, time, cost, quality, and risk.
time, cost, quality, performance, and risk.
time, cost, scope, and performance.

Question 18. 18. Using a strategic analysis approach, an organization's information requirements are known through a small number of
milestones and dates.
critical success factors.
key management decisions.
organizational changes.

Question 19. 19. In which approach to systems building are the development stages organized so that tasks in one stage are completed before the tasks in the next stage have begun? )
Traditional
Prototyping
RAD
All of the above

Question 20. 20. The process of building an experimental system quickly and inexpensively for demonstration and evaluation so that users can better determine information requirements.
agile.
JAD.
prototyping.
agile or prototyping.

Reference no: EM13334047

Questions Cloud

Determine the potential energy of the pair of charges : Two point charges Q1 = +4.30 nC and Q2 = -2.30 nC are separated by 27.0 cm. What is the potential energy of the pair of charges
Develop an entity-relationship diagram : List the entity classes and attributes that would be necessary for this information system.
What is probability that more of the business travelers say : A Travel Weekly International Air Transport Association survey asked business travelers about the purpose for their most recent business trip. 19% responded that it was for an internal company visit.
Calculate the total electric potential at the origin : Two point charges are on the y-axis. A 5.0 µC charge is located at y = 1.40 cm, and a -2.30 µC charge is located at y = -1.60 cm. Find the total electric potential at the origin
What will you need to understand and measure : 1. What will you need to understand and measure for an effective reengineering project?
Determine how much must be remitted for the purchase : The current price of the $1,000 bond is $978. On February 1, you purchase $10,000 face amount, and your broker charges a $25 commission. How much must you remit for the purchase
What is the maximum speed during the motion : A horizontal spring-mass system has low friction, spring stiffness 150 N/m, and mass 0.4 kg. What is the maximum speed during the motion
Explain the molar mass of fecl2 : Find the percentage of FeCl2 in a 35.5g sample of ore which has been dissolved in aqueous acid and titrated to the endpoint with 23.55 ml of 0.309 M Cr2O7^2- . the molar mass of FeCl2 is 126.0 g/mol. Cr2O7^2- + Fe^2+ ------> Cr^3+ + Fe^3+
How far apart will the three teddy bears land : At a county fair, a boy and two friends bring their teddy bears on the giant Ferris wheel. The boys are seated in positions 45° from each other. How far apart will the three teddy bears land

Reviews

Write a Review

Project Management Questions & Answers

  Firm-s break-even point increase

Would the firm's break-even point increase or decrease if it made the change?

  Creating table to show different elements-internal proposal

Create a table that shows the different elements that are found in an internal proposal and an external proposal for this training.

  Project management and team building

What are the three best team building techniques and how they would be used and why these three would be considered the best.

  Prepare a project scope and schedule

Develop Project Scope and Schedule for Project Management - How would a consultant develop the project scope and schedule for Wal-mart?

  Important qualities for a leader and managers

What do you feel are the most important qualities for a leader to possess to be effective?

  Write a proposal for multicultural management

- Identify the most critical issues faced by managers with regard to the topic and outline solutions to the issues you identify using theories and best practices presented ininternational business subjects.

  Importance of strategic alignment in project management

Discuss the importance of strategic alignment in project management.

  Disadvantages of using project management software

What do you see as the advantages and disadvantages of using project management software such as MS Project to organize a project

  Project scope management to success or failure of project

Why is Project Scope Management important to the success or failure of a project?

  Identify Risk in project management

Identify "Risk" in project management

  Technology beneficial to manufacturing-service operations

Your process team has been requested to identify technology that would be beneficial to manufacturing and service operations clients.

  Effectiveness of the project manager

Evaluation form after project termination for effectiveness of the project manager

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd