1. A factory operates two eight-hour shifts per day, five days per week. Their design capacity is 240 units per hour. Last week they produced 15,000 units. What was their utilization last week?
State answer as a precent rounded to two decimal places
2. A factory operates three eight-hour shifts per day, five days per week. Their effective capacity is 175 units per hour. Last week they produced 19194 units.
What was their efficiency last week?
3. Jo's Furnace Repair has a nine technicians that work five days per week. The effective capacity is four repairs per day per technician. Last week the total number of repairs was 149.
What was the efficiency for the group last week?
Round to two decimal places.
4. A company operates 8 hours per shift, two shifts per day, five days a week with 9 hours maintenance per week and other downtime of 2 hours per week.
What is the effective capacity in hours per week?
5. A factory operates two eight-hour shifts per day, five days per week. Their design capacity is 215 units per hour. Last week they produced 15,000 units. What was their utilization last week?
State answer as a precent rounded to two decimal places