What was the labour rate variance for the month

Assignment Help Managerial Accounting
Reference no: EM132608251

The following labour standards have been established for a particular product:

Standard labour hours per unit of output 7.5 hours

Standard labour rate $15.25 per hour

The following data pertain to operations concerning the product for the last month:

Actual hours worked 9,600 hours

Actual total labour cost $144,480

Actual output 1,200 units

Problem 1: What was the labour rate variance for the month?

A) $240 unfavourable.

B) $1,920 unfavourable.

C) $240 favourable.

D) $1,920 favourable.

Reference no: EM132608251

Questions Cloud

Report using experimental findings of your redox titration : Produce a laboratory report using the experimental findings of your REDOX titration - Diagrams, graphs and pictures must be clearly labelled and figure captions
Define reasons why the issue is important to organizations : There are many issues affecting organizations today, such as employee retention, flexible work schedule, contingent workforce, talent management.
Which is directly associated with a higher denominator level : Which is directly associated with a higher denominator level of activity? Frequent occurrence of a volume variance./ More profitable operations.
What is your profit or loss : You purchase a long call option giving you the right to buy 100 shares of Isher Corporation for a total premium of $2,700. What is your profit or loss
What was the labour rate variance for the month : What was the labour rate variance for the month? The data pertain to operations concerning the product for the last month, Actual hours worked 9,600 hours
What was the budgeted maintenance cost per machine hour : At Overland Company, If 8,000 machine hours were actually worked during July, what was the budgeted maintenance cost per machine hour?
What is the budgeted fixed factory overhead for the year : If the variable portion of the predetermined overhead rate is $3.00 per machine hour, what is the budgeted fixed factory overhead for the year?
How much is the balance of the Malibu branch account : The home office instructed Venice to transfer 75% of the goods. How much is the balance of the Malibu branch account on the Home Office books
What was the direct labour rate variance for march : What was the direct labour rate variance for March? Bryan Company employs a standard cost system in which direct materials inventory

Reviews

Write a Review

Managerial Accounting Questions & Answers

  Manage budgets and financial plans

Explain the budgeting process and its importance to a business, identifying the components of different budgets, forecast estimates for inclusion in the budgets.

  Prepare a retained earnings statement

Prepare a retained earnings statement for the year and Prepare a stockholders' equity section of given case.

  Prepare a master budget for the three-month period

Prepare a master budget for the three-month period.

  Construct the companys direct labor budget

Construct the company's direct labor budget for the upcoming fiscal year, assuming that the direct labor workforce is adjusted each quarter to match the number of hours required to produce the forecasted number of units produced.

  Evaluate the predetermined overhead rate

Evaluate the Predetermined Overhead Rate

  Determine the company''s bid

Determine the company's bid if activity-based costing is used and the bid is based upon full manufacturing cost plus 30 percent.

  Compute the pool rates for the different activities

Complete the schedule to compute the pool rates for the different activities.

  Prepare Company financial statements

Prepare Company financial statements

  Prepare an analysis of terracycles

This individual assignment is based on the TerraCycle Inc.

  Discuss the ethical issues

Discuss the ethical issues

  Political resources in emerging markets

Calculate the GDP in Income Approach  and Expenditure Approach

  Management accounting - ehsan electronics company

A new plant accountant suggested that the company may be able to assign support costs to products more accurately by using an activity based costing system that relies on a separate rate for each manufacturing activity that causes support costs.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd